SCHEDULES
SCHEDULE 8PROTECTIVE PROVISIONS
PART 4FOR THE PROTECTION OF THE LOCAL HIGHWAY AUTHORITY REGARDING VEHICULAR HIGHWAYS
I132
1
Before commencing the construction of, or the carrying out of any work authorised by this Order which involves interference with a local highway (including interference with the use by the public of a local highway and temporary or permanent stopping up of any part of a local highway), the undertaker must use reasonable endeavours to agree with the local highway authority a Detailed Local Operating Agreement covering the following—
a
communications and customer care: communication with stakeholders and identification of which party is responsible for each activity;
b
operational areas – scheme operational areas: definitions and scheme extents for the works areas, zone of influence and Free Recovery Area;
c
asset handover: describing the scheme existing assets and activities to be undertaken to enable commencement and completion of Works, and the party responsible for each;
d
asset inspection;
e
routine maintenance and repair;
f
winter maintenance and severe weather;
g
continuity of technology;
h
occupancy management;
i
incidents;
j
traffic management: provides the key activities to be undertaken with regard to the design, installation, maintenance and removal of Traffic Management; and
k
claims made by and against the undertaker.
2
Any agreement completed under sub-paragraph (1) must continue in force until the completion of the Works or the removal of the undertaker from all local highways, whichever is the earlier.
3
Where agreement cannot be reached under sub-paragraph (1), the terms of the detailed local operating agreement will be resolved by arbitration under article 45 (arbitration).