SCHEDULES

SCHEDULE 7LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

Article 29

(1)

Plot Reference Number shown on Land Plans

(2)

Purpose for which temporary possession may be taken

(3)

Relevant part of the authorised development

Land Plans – Sheet 3

3/7a, 3/7b and 3/7c

Required to deliver ancient woodland enhancement measures

Work No. 76 as shown on sheets 3 and 4 of the works plans

Land Plans – Sheet 4

4/1e and 4/9a

Required for alignment of the existing A460 into the M54 Junction 1 south roundabout

Work No. 7 as shown on sheet 4 of the works plans

4/1i

Required for the stopping up of the existing A460 and construction of a turning head facility

Work No. 11 as shown on sheet 4 of the works plans

4/2

Required to deliver ancient woodland enhancement measures

Work No. 76 as shown on sheets 3 and 4 of the works plans

4/8

Required for the diversion of utilities and association infrastructure to a new utilities’ corridor

Work No. 67 as shown on sheet 4 of the works plans

4/13, 4/14a and 4/14c

Required for the alignment of the M54 Junction 1 eastbound merge slip road and the construction of an access for Tower Hill Farm connecting to the Featherstone Junction east roundabout

Work Nos. 12 and 20 as shown on sheet 4 of the works plans

4/14i

Required for the construction of a free-flowing two lane carriageway, the Featherstone Junction east roundabout, a dual carriageway dumbbell link, new private means of access, the Featherstone Junction southbound diverge slip road and the diversion of a high pressure gas main

Work Nos. 2, 4, 13, 14, 20, 21, 22, 68 as shown on sheet 4 of the works plans

4/17b, 4/18

Required for the diversion of a high pressure gas main

Work No. 68 as shown on sheet 4 of the works plans

4/20d

Required for habitat creation for visual screening and to mitigate for biodiversity loss and the installation of a replacement fence

Work No. 80 as shown on sheet 4 of the works plans

4/22

Required for the modification of an existing junction and removal of a right turn prohibition into Dark Lane

Work No. 73 as shown on sheets 4 and 5 of the works plans

Land Plans – Sheet 5

5/1

Required for the modification of an existing junction and removal of a right turn prohibition into Dark Lane

Work No. 73 as shown on sheets 4 and 5 of the works plans

5/6

Required for the construction of new northbound and southbound dual carriageways to M6 Junction 11 the realignment of Hilton Lane and construction of an accommodation overbridge and realignment of access tracks to the south of Brookfield Farm

Work Nos. 25, 26, 27 and 28 as shown on sheets 4 to 6 of the works plans

5/10

Required for the construction of new northbound and southbound dual carriageways to M6 Junction 11, realignment of Hilton Lane and the realignment of public right of way Shareshill 5

Work Nos. 25, 26, 27 and 63 as shown on sheets 4 to 6 of the works plans

5/11a

Required for the construction of new northbound and southbound dual carriageways to M6 Junction11, realignment of Hilton Lane, construction of an accommodation overbridge and realignment of access tracks to the south of Brookfield Farm, installation of a new balancing pond and works to realign public right of way Shareshill 5

Work Nos. 25, 26, 27, 28, 59 and 63 as shown on sheet 5 of the works plans

5/11g

Required for the construction of a new northbound and southbound dual carriageways to M6 Junction 11, construction of an accommodation overbridge and realignment of access tracks to the south of Brookfield Farm and the diversion of an overhead electricity cable and associated infrastructure

Work No. 25, 26, 28 and 70 as shown on sheet 5 of the works plans

5/14

Required for the construction of northbound and southbound dual carriageways to M6 Junction 11 and an accommodation overbridge and realignment of access tracks

Work Nos. 25, 26 and 28 as shown on sheets 4 to 6 of the works plans

5/25

Required for the construction of new northbound and southbound dual carriageways to M6 Junction 11, realignment of Hilton Lane and the modification of the junction between the existing A460, New Road and Dark lane and the construction of a borrow pit including the excavation, working and restoration to win material required for the construction of the authorised development

Work Nos. 25, 26, 27 and 74 as shown on sheet 4, 5 and 6 of the works plans

Land Plans – Sheet 6

6/11b, 6/13, 6/18 and 6/19

Required to realign the M6 Junction 11 northbound merge slip road

Work No. 33 as shown on sheet 6 of the works plans

6/11k, 6/11l, 6/11m, 6/11n, 6/17r, 6/17q and 6/27

Required for the demolition and removal of existing M6 Junction 11 structures and redundant sections of existing circulatory carriageway. Also required for the construction of a new M6 Junction 11 circulatory carriageway and associated infrastructure, the realignment of Wolverhampton Road and the realignment and widening by a single lane of the A460 southbound and northbound

Work Nos. 36, 38, 39 and 40 as shown on sheet 6 of the works plans

6/12

Required to realign Mill Lane

Work No. 30 as shown on sheet 6 of the works plans

6/17f

Required for the demolition of existing structures at M6 Junction 11, and construction of new M6 Junction 11 circulatory carriageway including overbridges and portal gantries

Work No. 36 as shown on sheet 6 of the works plans

6/17g, 6/20 and 6/22a

Required for the realignment of the M6 Junction 11 southbound diverge slip road

Work No. 35 as shown on sheet 6 of the works plans

6/17h, 6/17i, 6/17j, 6/17k, 6/17m, 6/32a and 6/36

Required for the realignment and widening by a single lane of the A460 southbound and northbound

Work No. 39 as shown on sheet 6 of the works plans

6/25

Required for the realignment of the M6 Junction 11 southbound merge slip road, the demolition and removal of existing M6 Junction 11 structures and redundant sections of existing circulatory carriageway. Also required for the construction of a new M6 Junction 11 circulatory carriageway and associated infrastructure. Required for the realignment of the A462 to M6 Junction 11

Work Nos. 34, 36 and 37 as shown on sheet 5 and 6 of the works plans

6/37

Required for the realignment of the M6 Junction 11 southbound diverge slip road. Required for the demolition and removal of existing M6 Junction 11 structures and redundant sections of existing circulatory carriageway. Also required for the construction of a new M6 Junction 11 circulatory carriageway and associated infrastructure. Also required for the realignment and widening by a single lane of the A460 southbound and northbound and the realignment of the existing public right of way Saredon 13

Work Nos. 35, 36, 39 and 66 as shown on sheet 6 of the works plans