Work No. 12A
Works associated with the construction of Work No. 12B, Work No. 12C and Work No. 12D, to include—
(a)site preparation works including construction hoardings, perimeter enclosure, ecological fencing and security, construction related buildings, structures, plant, machinery and construction lighting;
(b)earthworks including creation of acoustic bunds, utilities trenches, surface water drainage system including flood relief basins and landscape works, including ecological works;
(c)access roads, tracks and hardstanding;
(d)construction of bridges and civil structures;
(e)highway works including kerbs, footways and paved areas;
(f)traffic signal poles and fittings;
(g)lighting poles and fittings; and
(h)perimeter fencing, ecological fencing, animal corrals, signage, gates and barriers.
Work No. 12B
A bypass of Middleton Moor and Theberton, to include—
(a)a road (6.8km in length) commencing at a new three-arm roundabout located 180m north of The Red House Farm and terminating at a new three arm roundabout on the B1122 (west of the main development site), and including a bridge over the East Suffolk line;
(b)associated realignments and tie-ins of existing roads bi-sected by the bypass and other existing roads adjoining the bypass; and
(c)new and altered private means of access.
Work No. 12C
A motorised user bridge over Work No. 12B(a), connecting to Pretty Road on either side.
Work No. 12D
(a)A junction to Moat Road to maintain access to properties including Theberton Grange and Moat House.
(b)Realignment of the road to Theberton Grange for 300m to join George Road.
The location of the above works is shown on sheet nos. 18, 19, 20, 21 and 22 of the Works Plans.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: