Article 39
(1) Relevant site | (2) Plot reference (as shown on Land Plans) | (3) Purpose for which temporary possession may be taken |
---|---|---|
Main development site and rail | MDS/01/02, MDS/02/09, MDS/02/35, MDS/03/02, MDS/03/04, MDS/03/05, MDS/03/08, MDS/03/09, MDS/03/11, MDS/03/18, MDS/03/19, MDS/05/20, MDS/05/21, MDS/05/22 | Construction of, and working areas in relation to, Work No. 1 |
Main development site and rail | MDS/10/15 | Construction of Work No. 4B |
Main development site and rail | MDS/03/08, MDS/03/12, MDS/03/13, MDS/03/14, MDS/03/15, MDS/03/16, MDS/03/17, MDS/07/01, MDS/08/01, MDS/08/02, MDS/08/03, MDS/08/04, MDS/08/05, MDS/08/06, MDS/08/07, MDS/09/01, MDS/09/02, MDS/09/03, MDS/09/04, MDS/09/05, MDS/09/06, MDS/09/07, MDS/09/08, MDS/09/09, MDS/09/10, MDS/09/11, MDS/09/12, MDS/10/15, MDS/10/17, MDS/10/18, MDS/10/19, MDS/10/20 | Construction of, and working areas in relation to, Work No. 4C |
Sports facilities | SF/11/01, SF/11/02 | Construction of Work No. 5 and use of the facilities by the undertaker’s workforce and the public |
Fen Meadow (Halesworth) | FM/12/04 | Construction of Work No. 6 |
Fen Meadow (Benhall) | FM/13/05 | Construction of Work No. 7 |
Northern park and ride | NPR/15/14, NPR/15/15, NPR/15/16 | Works to existing highway (Work No. 9(b)) |
Southern park and ride | SPR/16/03, SPR/16/08, SPR/16/09, SPR/16/10, SPR/16/12 | Works to existing highway (Work No. 10(b)) |
Two village bypass | 2VBP/17/01, 2VBP/17/04, 2VBP/17/07, 2VBP/17/09, 2VBP/17/10, 2VBP/17/14, 2VBP/17/16, 2VBP/17/17, 2VBP/17/17b 2VBP/17/18, 2VBP/17/19, 2VBP/17/19c, 2VBP/17/22, 2VBP/17/23, 2VBP/17/26, 2VBP/17/27, 2VBP/17/28, 2VBP/18/13, 2VBP/18/14, 2VBP/18/16, 2VBP/18/17 | Working area in relation to construction of Work No. 11 |
Two village bypass | 2VBP/18/09, 2VBP/18/11 | Working areas and construction compounds associated with carrying out Work No. 11 |
Sizewell link road | SLR/19/01, SLR/19/05, SLR/19/06, SLR/19/07, SLR/19/07d, SLR/19/07e, SLR/19/09a, SLR/19/10, SLR/19/11a, SLR/19/12, SLR/19/13, SLR/19/14, SLR/19/15, SLR/19/15b, SLR/19/15c, SLR/19/15d, SLR/19/15e, SLR/19/15f, SLR/19/16, SLR/19/17, SLR/19/18, SLR/19/19, SLR/20/01, SLR/20/01b, SLR/20/01c, SLR/20/03c, SLR/20/03d, SLR/20/05, SLR/20/06, SLR/20/07, SLR/20/09, SLR/20/10, SLR/20/10a, SLR/20/12, SLR/20/14, SLR/20/15a, SLR/20/17, SLR/21/02, SLR/21/03, SLR/21/09a, SLR/21/11, SLR/21/12, SLR/21/13, SLR/21/17, SLR/21/19b, SLR/21/24a, SLR/21/25, SLR/21/26, SLR/21/26b, SLR/21/27, SLR/21/28c, SLR/21/33, SLR/21/33c, SLR/21/35, SLR/21/36, SLR/21/40, SLR/21/43, SLR/21/45, SLR/22/01, SLR/22/03, SLR/22/05, SLR/22/08, SLR/22/12, SLR/22/16, SLR/22/25 | Working areas in relation to construction of Work No. 12 |
Sizewell link road | SLR/19/21, SLR/19/07b, SLR/19/07g | Working areas and construction compounds associated with carrying out Work No. 12 |
Freight management facility | FMF/23/01, FMF/23/02, FMF/23/03, FMF/23/04, FMF/23/06, FMF/23/07, FMF/23/08 | Works to existing highway (Work No. 13(b)) |
Yoxford roundabout | OHI/24/11; OHI/24/01, OHI/24/02, OHI/24/03, OHI/24/06, OHI/24/07, OHI/04/08, OHI/24/09 | Works to existing highway (Work No. 14) |
Yoxford roundabout | OHI/24/10 | Construction compound associated with the carrying out Work No. 14 |
A12/B1119 junction at Saxmundham | OHI/25/01, OHI/25/03 | Works to existing highway (Work No. 15) |
A1094/B1068 junction south of Knodishall | OHI/26/01, OHI/26/02, OHI/26/03, OHI/26/04, OHI/26/05, OHI/26/06, OHI/26/08 | Works to existing highway (Work No. 16) |
A12/A144 junction south of Bramfield | OHI/27/02, OHI/27/03, OHI/27/05, OHI/27/06, OHI/27/07, OHI/27/09, OHI/27/10, OHI/27/11 | Works to existing highway (Work No. 17) |
Fen Meadow (Pakenham) | FM/28/05 | Construction of Work No. 18 |
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: