xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULE 19Protective Provisions

PART 5FOR THE PROTECTION OF NATIONAL GRID AS ELECTRICITY UNDERTAKERS

Protective works to buildings

46.  The undertaker, in the case of the powers conferred by article 26 (protective work to buildings), must exercise those powers so as not to obstruct or render less convenient the access to any apparatus without the written consent of National Grid, not to be unreasonably withheld or delayed.