42.—(1) The construction of Work Nos. 2A to 2J must not commence until the following activity details for that Work No. have been submitted to and approved by the MMO in writing. The activity details must include, but are not limited to—
(a)the start and end dates for construction;
(b)the location of the relevant phase of the construction and drilling activities;
(c)a detailed construction method statement;
(d)the navigational lighting to be used;
(e)links to the CPMMP (marine); and
(f)the vessels to be used.
(2) Work Nos. 2A to 2J must be constructed in accordance with the activity details approved by the MMO.
(3) Unless a shorter period is agreed with the MMO in writing, the undertaker must use reasonable endeavours to submit the activity details for the relevant Work No. at least 6 months prior to the proposed commencement of the relevant Work No.