SCHEDULE 8Deemed approval of requirements relating to Sizewell B relocated facilities permission 1 and 2
PART 1SIZEWELL B RELOCATED FACILITIES PERMISSION 1
(1) Sizewell B relocated facilities permission 1 condition | (2) Order requirement |
---|---|
2, 5 | 16 (Main development site: Approved buildings, structures and plant) |
6 | 14 (Main development site: Construction lighting) and 28 (Main development site: Permanent operational lighting) |
18, 19 | Requirement 6 (Emergency Planning) |
15, 22, 23, 25, 26 | 5 (Project-wide: Surface and foul water drainage) |
20, 21 | 3 (Project wide: Archaeology) |
30 | 15 (Main development site: Outage car park) |