SCHEDULES

SCHEDULE 2REQUIREMENTS

PART 1REQUIREMENTS

Notice of start of commissioning and notice of date of final commissioning

20.—(1) Where practicable, notice of the intended start of commissioning of Work No. 1A must be given to the relevant planning authorities prior to such start and in any event within seven days from the date that commissioning is started.

(2) Within seven days of completing final commissioning of Work No. 1A, the undertaker must provide the relevant planning authorities with notice of the date upon which such commissioning was duly completed.