The Boston Alternative Energy Facility Order 2023

General conditions

5.  The undertaker must notify the MMO at the earliest opportunity of any change to the information upon which the granting of this licence was based.

6.—(1) The undertaker must notify the HM Coastguard (mail to: nmoccontroller@hmcg.gov.uk) prior to commencement of any licensed activities.

(2) A copy of the notification must be provided to the MMO via MCMS within 24 hours of issue of the notification in sub-paragraph (1).

7.—(1) The undertaker must ensure that local mariners and fishermen’s organisations are made fully aware of all licensed activities through a local notice to mariners issued at least 5 days before the commencement of the works.

(2) The notice to mariners must be updated and re-issued at fortnightly intervals during construction activities and within 5 days of any planned operations.

(3) A copy of the notice must be provided to the MMO via MCMS within 24 hours of issue of a notice under sub-paragraphs (1) or (2).