SCHEDULES

SCHEDULE 11E+W+SDEEMED MARINE LICENCE UNDER THE 2009 ACT - GENERATION ASSETS

PART 2E+W+SCONDITIONS

Aviation safetyE+W+S

10.—(1) The undertaker must exhibit such lights, with such shape, colour and character as are required in writing by Air Navigation Order 2016(1) and determined necessary for aviation safety in consultation with the Defence Infrastructure Organisation Safeguarding and as directed by the Civil Aviation Authority. Lighting installed specifically to meet Ministry of Defence aviation safety requirements must remain operational for the life of the authorised development unless otherwise agreed in writing with the Ministry of Defence.

(2) The undertaker must notify the Defence Infrastructure Organisation Safeguarding, the Civil Aviation Authority and the MMO, at least 14 days prior to the commencement of the licensed activities, in writing of the following information—

(a)the date of the commencement of the licensed activities;

(b)the date any wind turbine generators are to be installed;

(c)the maximum height of any construction equipment or vessels to be used;

(d)the maximum heights of any wind turbine generator and offshore accommodation platform to be constructed (including any antennae);

(e)the latitude and longitude of each wind turbine generator and offshore accommodation platform to be constructed,

and the Defence Infrastructure Organisation Safeguarding and the Civil Aviation Authority must be notified of any changes to the information supplied under this paragraph of this condition and of the completion of the construction of the authorised scheme. Copies of notifications must be provided to the MMO.

Commencement Information

I1Sch. 11 para. 10 in force at 3.8.2023, see art. 1