A2.2REP7-004Benthic and Intertidal Ecology210 August 2022
A5.2.1.1REP7-013Benthic Intertidal Ecology Technical Report210 August 2022
A2.6REP5-004Commercial Fisheries220 June 2022
A4.4.4REP6-004Dredging and disposal site227 July 2022
A3.3.1AS-008Ecology and Nature Conservation Schedule of Change117 January 2022
A1.5.1AS-007Environmental Impact Assessment Methodology Schedule of Change117 January 2022
G1.2AS-020Environmental Risk Assessment of the Onshore Substation and Energy Balancing Infrastructure117 January 2022
A6.4.1REP5-010Landscape and visual resources wireframes and photomontages220 June 2022
A5.7.1REP4-009Navigational risk assessment part 1210 May 2022
A5.7.1REP4-011Navigational risk assessment part 2210 May 2022
A5.7.1REP4-013Navigational risk assessment part 3210 May 2022
A5.11.1REP3-005Offshore installation interfaces part 1221 April 2022
A5.11.1REP2-059Offshore installation interfaces part 2229 March 2022
A5.5.2REP2-003Offshore ornithology displacement analysis229 March 2022
A5.5.5.1AS-010Offshore Ornithology Migratory Birds report Schedule of Change117 January 2022
G5.25REP6-028Ornithology Environmental Impact Assessment (EIA) and Habitats Regulation Assessment (HRA) Revision 2327 July 2022
A4.4.8REP6-006Pro-rata Annex Revision 4427 July 2022
NTS1.1.1AS-022Response to post-Acceptance s51 advice: NTS1.1.1 Non Technical Summary of Schedule of Change117 January 2022
G5.9REP5a-009Revised Ornithology Baseline Revision 224 July 2022
A2.7REP5-006Shipping and Navigation220 June 2022
A1.4REP7-002Volume A4 Chapter 4: Project Description Revision 7710 August 2022