2024 No. 674

Infrastructure Planning

The Keuper Underground Gas Storage Facility (Amendment) Order 2024

Made

Coming into force

An application has been made to the Secretary of State under paragraph 2 of Schedule 6 to the Planning Act 20081 (“2008 Act”) in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 20112 (“2011 Regulations”) for a non-material change to the Keuper Underground Gas Storage Facility Order 20173 (“2017 Order”).

The Secretary of State, having considered the application and the responses to the publicity and consultation carried out in accordance with regulations 6 and 7 of the 2011 Regulations, has decided to make this Order amending the 2017 Order.

Accordingly, the Secretary of State, in exercise of the powers conferred by section 153 of, and paragraph 2 of Schedule 6 to, the 2008 Act, makes the following Order.

Citation and commencement1

This Order may be cited as the Keuper Underground Gas Storage Facility (Amendment) Order 2024 and shall come into force on 16th May 2024.

Amendment of the Keuper Underground Gas Storage Facility Order 20172

The Keuper Underground Gas Storage Facility Order 2017 (“the 2017 Order”) is amended in accordance with this Order.

Amendments to Article 2 (Interpretation)3

Article 2 (Interpretation) of Part 1 is amended as follows—

a

in the definition of “Canal & River Trust”, for “whose address is Navigation Road, Northwich, Cheshire CW8 1BH” substitute “whose address is National Waterway Museum, Ellesmere Port, South Pier Road, Ellesmere Port, Cheshire, England, CH65 4FW”; and

b

in the definition of “undertaker”, for “whose registered office is at Runcorn Site HQ, South Parade, PO Box 9, Runcorn, Cheshire, WA7 4JE” substitute “whose registered office is at Bankes Lane Office, Bankes Lane, PO Box 9, Runcorn, Cheshire, WA7 4JE”.

Amendments to Article 35 (Certification of plans etc.)4

Article 35 (Certification of plans etc.), is amended as follows—

a

in paragraph (1)(e)—

i

for “13-03-01/HOL/24/500-506/B1” substitute “13-03-01/HOL/24/500-503/B1, 13-03-01/HOL/24/504/B2, 13-03-01/HOL/24/505-506/B1”; and

ii

for “13-03-01/HOL/24/510/B2” substitute “13-03-01/HOL/24/510/B3”;

b

in paragraph (i)(ii)—

i

for “13-03-01/HOL/24/270/B4” substitute “13-03-01/HOL/24/270/B5”; and

ii

for “13-03-01/HOL/24/274/B1” substitute “13-03-01/HOL/24/274/B2”;

c

in paragraph (1)(j) for “the seismic survey report (document ref: 9.1)” substitute “the seismic survey report (document ref: 9.1) Revision A”;

d

in paragraph (1)(k) for “the sub-surface safety assessment report (document ref: 9.2)” substitute “the sub-surface safety assessment report (document ref: 9.2) Revision B”;

e

in paragraph (1)(l) for “the preliminary study of gas design capacity (document ref: 9.3)” substitute “the preliminary study of gas design capacity (document ref: 9.3) Revision B”; and

f

in paragraph (1)(m)—

i

for “13-03-01/HOL/24/240-264/B1” substitute “13-03-01/HOL/24/240-262/B1, 13-03-01/HOL/24/263-264/B2”; and

ii

for “13-03-01/HOL/24/266-268/B1” substitute “13-03-01/HOL/24/266/B2 and 13-03-01/HOL/24/267-268/B1”.

Amendment to Schedule 9 (Protective Provisions)5

In Part 5 (for the protection of Holford Gas Storage limited) of Schedule 9 (Protective Provisions) in paragraph 62(10), for “the undertaker must comply with” substitute “the promoter must comply with”.

Certification of new, revised or substituted plans6

1

The undertaker must, as soon as practicable after the making of this Order, submit copies of any new, revised or substituted plans to the Secretary of State for certification that they are true copies of the plans referred to in this Order.

2

A plan so certified by the Secretary of State is admissible in any proceedings as evidence of the contents of the document of which it is a copy.

3

In paragraph (1), the “undertaker” has the same meaning as in Article 2 of the 2017 Order.

Signed by authority of the Secretary of State for Energy Security and Net Zero.

Victoria DaweDirector of Energy DevelopmentDepartment for Energy Security and Net Zero
EXPLANATORY NOTE

(This note is not part of the Order)

This Order amends the Keuper Underground Gas Storage Facility Order 2017 (“the 2017 Order”), a development consent order under the Planning Act 2008.

This Order follows an application under paragraph 2 of Schedule 6 to the Planning Act 2008 for a non-material change to allow the inclusion of hydrogen gas storage in the definition of gas storage, the substitution (update of) various Certified Plans and the update to the registered address of the Undertaker.

The changes to the 2017 Order take effect from the date specified in this Order.