Interpretation
1. In this Schedule—
“commence” means beginning to carry out any material operation (as defined in section 56(4)() of the 1990 Act) forming part of the authorised development other than environmental surveys and monitoring, archaeological mitigation works, pre-construction ecological mitigation, investigations for the purpose of assessing and monitoring ground conditions and levels, remedial work in respect of any contamination or other adverse ground conditions, erection of temporary means of enclosure, receipt and erection of construction plant and equipment, diversion and laying of services and site clearance, construction of welfare facilities and temporary buildings, temporary display of site notices, information and advertisements, and establishment of construction compounds, and “commencement” is to be construed accordingly;
“City Archaeologist” means the individual nominated or appointed as such by the relevant planning authority;
“design principles report” means the document certified by the Secretary of State as the design principles report for the purposes of this Order;
“DMRB” means the Design Manual for Roads and Bridges, which accommodates all current standards, advice and other documents relating to the design, assessment and operation of trunk roads and motorways, or any equivalent replacement to the DMRB published;
“drainage strategy” means the document certified by the Secretary of State as the Environmental Statement – Appendix 13.1 – Drainage Strategy Report (Parts 1 and 2 of 2) for the purposes of this Order;
“Ecological Clerk of Works” means the individual appointed as such by the undertaker;
“environmental masterplan” means figure 2.3 in the document certified by the Secretary of State as “the Environmental Statement - Chapter 2 - The Scheme and its Surroundings - Figures (Part 2 of 4) for the purposes of this Order;
“EMP (First Iteration)” means the plan certified by the Secretary of State as the First Iteration Environmental Management Plan for the purposes of this Order;
“EMP (Second Iteration)” means the second iteration of the environmental management plan produced in accordance with the DMRB, which is to be a refined version of the EMP (First Iteration) including more detailed versions of the outline plans contained or listed within the EMP (First Iteration) or any other plans as required;
“EMP (Third Iteration)” means the third iteration of the environmental management plan produced in accordance with the DMRB, which is a refined version of the EMP (Second Iteration) and which relates to the operational and maintenance phase of the authorised development;
“European protected species” has the same meaning as in regulations 42 (European protected species of animals) and 46 (European protected species of plants) of the Conservation of Habitats and Species Regulations 2017();
“flood risk assessment” means the document certified by the Secretary of State as the flood risk assessment for the purposes of this Order;
“lead local flood authority” means Hampshire County Council;
“Manual of Contract Documents for Highway Works” means the document of that name published electronically by or on behalf of the strategic highway authority for England, or any equivalent replacement published for that document;
“Outline Landscape and Ecological Management Plan” means that plan certified by the Secretary of State as the Environmental Statement – Appendix 7.6 - Outline Landscape and Ecological Management Plan for the purposes of this Order;
“outline traffic management plan” means the document certified by the Secretary of State as the outline traffic management plan for the purposes of this Order;
“protected species” means species which are subject to protection under the laws of England or which are “European protected species”.