The West Midlands Rail Freight Interchange (Amendment No. 2) Order 2025

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening OptionsExpand opening options

Close

Print Options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Statutory Instruments

2025 No. 481

Infrastructure Planning

The West Midlands Rail Freight Interchange (Amendment No. 2) Order 2025

Made

10th April 2025

Coming into force

11th April 2025

An application has been made under paragraph 2 of Schedule 6 to the Planning Act 2008(1), and in accordance with Part 1 of the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011(2) for a non-material change to the West Midlands Rail Freight Interchange Order 2020(3).

The Secretary of State, having considered the application and the responses to the publicity and consultation carried out in accordance with regulations 6 and 7 of the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011, has decided to make this Order amending the West Midlands Rail Freight Interchange Order 2020.

The Secretary of State, in exercise of the powers conferred by paragraph 2 of Schedule 6 to the Planning Act 2008, makes the following Order—

Citation and commencement

1.—(1) This Order may be cited as the West Midlands Rail Freight Interchange (Amendment No. 2) Order 2025 and comes into force on 11th April 2025.

Amendment of the West Midlands Rail Freight Interchange Order 2020

2.  Omit the table in Schedule 15 (certification documents) to the West Midlands Rail Freight Interchange Order 2020 and substitute the table set out in the Schedule to this Order.

Signed by authority of the Secretary of State for Transport

Kayla Marks

Head of the Transport and Works Act Orders Unit

Department for Transport

10th April 2025

Article 2

SCHEDULECERTIFICATION DOCUMENTS

1.  Documents for certification that they are true copies of the documents referred to in this Order

(1) Document/Plan(2) Document Number(3) Document date/Plan number with revision number
Access and rights of way plans
Key Plan2.3WSP-70001979-SK-060 Rev I
Sheet 12.3AWSP-70001979-SK-060 Rev H
Sheet 22.3BWSP-70001979-SK-060 Rev G
Sheet 32.3CWSP-70001979-SK-060 Rev F
Sheet 42.3DWSP-70001979-SK-060 Rev F
Sheet 52.3EWSP-70001979-SK-060 Rev F
Sheet 62.3FWSP-70001979-SK-060 Rev F
Sheet 72.3GWSP-70001979-SK-060 Rev B
The book of reference4.3B21 August 2019
The bridge plans
Proposed road bridges plan and long section2.18A1516-0425-WDK-SI-C-301-010 Rev P11
Road Bridge B12.18B1516-0425-WDK-SI-C-301-006 Rev P14
Road Bridge B2 and B32.18C1516-0425-WDK-SI-C-300-007 Rev P14
Proposed road bridge B4 section and elevation2.18D1516-0425-WDK-SI-C-301-008 Rev P17
The design and access statement7.53 August 2018
The environmental statement6.2

3 August 2018 (subject to the

substitutions set out below):

(i) Figures 10.001, 10.002, 10.003 and

10.004 – 12 September 2018;

(ii) Annex 10.1.1 – 12 September

2018;

(iii) Addendum to Chapter 13 (Noise

and Vibration) – 5 April 2019

(iv) Appendix I to Transport

Assessment (Appendix 15.1) (Site

Wide HGV Management Plan) – 7

May 2019

(v) Appendix H to Transport

Assessment (Appendix 15.1) (Site

Wide Travel plan) – 5 July 2019

(vi) Appendix 2.3 (Outline Demolition

and Construction Management Plan) –

5 July 2019

(vii) Appendix 10.4 (Framework

Ecological Mitigation and

Management Plan) – 5 July 2019

(viii) Updated Chapter 7 (Air Quality)

and Appendices 7.2, 7.3, 7.4, 7.6 and

7.7 – 7 August 2019

The future highways maintenance plans
Key Plan2.10WSP-70001979-SK-091 Rev F
Sheet 12.10AWSP-70001979-SK-091 Rev F
Sheet 22.10BWSP-70001979-SK-091 Rev C
Sheet 32.10CWSP-70001979-SK-091 Rev C
The highway classification plans
Key Plan2.13WSP-70001979-SK-068 Rev I
Sheet 12.13AWSP-70001979-SK-068 Rev H
Sheet 22.13BWSP-70001979-SK-068 Rev E
Sheet 32.13CWSP-70001979-SK-068 Rev E
The highway general arrangement plans
Key Plan/Highway Masterplan2.9WSP-70001979-GA-100 Rev M
General Arrangement Plan 1012.9AWSP-70001979-GA-101 Rev E
General Arrangement Plan 1022.9BWSP-70001979-GA-102 Rev E
General Arrangement Plan 1032.9CWSP-70001979-GA-103 Rev I
General Arrangement Plan 1042.9DWSP-70001979-GA-104 Rev M
General Arrangement Plan 1052.9EWSP-70001979-GA-105 Rev E
General Arrangement Plan 1062.9FWSP-70001979-GA-106 Rev G
General Arrangement Plan 1072.9GWSP-70001979-GA-107 Rev H
General Arrangement Plan 1082.9HWSP-70001979-GA-108 Rev F
General Arrangement Plan 1092.9IWSP-70001979-GA-109 Rev G
General Arrangement Plan 1102.9JWSP-70001979-GA-110 Rev H
General Arrangement Plan 1112.9KWSP-70001979-GA-111 Rev H
The land plans
Key Plan2.1Key Plan v1
Sheet 12.1ASheet 1 of 12 v0
Sheet 22.1BSheet 2 of 12 v0
Sheet 32.1CSheet 3 of 12 v0
Sheet 42.1DSheet 4 of 12 v1
Sheet 52.1ESheet 5 of 12 v0
Sheet 62.1FSheet 6 of 12 v0
Sheet 72.1GSheet 7 of 12 v0
Sheet 82.1HSheet 8 of 12 v0
Sheet 92.1ISheet 9 of 12 v0
Sheet 102.1JSheet 10 of 12 v0
Sheet 112.1KSheet 11 of 12 v0
Sheet 122.1LSheet 12 of 12 v0
Order limits plan2.44990-00011 Rev 06
The parameters plans
Development Zone Parameters Plan
Key Plan2.54990-02000 Rev 11
Sheet 12.5A4990-02001 Rev 11
Sheet 22.5B4990-02002 Rev 08
Sheet 32.5C4990-02003 Rev 12
Sheet 42.5D4990-02004 Rev 07

Floor Levels and Building Heights

Parameters Plan

Key Plan2.64990-02010 Rev 12
Sheet 12.6A4990-02011 Rev 11
Sheet 22.6B4990-02012 Rev 07
Sheet 32.6C4990-02013 Rev 11
Sheet 42.6D4990-02014 Rev 07
Green Infrastructure Parameters Plan
Key Plan2.74990-02020 Rev 14
Sheet 12.7A4990-02021 Rev 13
Sheet 22.7B4990-02022 Rev 10
Sheet 32.7C4990-02023 Rev 14
Sheet 42.7D4990-02024 Rev 09
The illustrative arrangement of railway alignment2.14TRS-DRG-FA-001003 Rev 05
The rail terminal – illustrative expanded rail terminal layout plan2.15BTRS-DRG-FA-001010 Rev 04
The rail section plans
Rail Alignment Cross Sections – Sheet 12.16ATRS-DRG-FA-001005 Rev 02
Rail Alignment Cross Sections – Sheet 22.16BTRS-DRG-FA-001006 Rev 03
Rail Alignment Cross Sections – Sheet 32.16CTRS-DRG-FA-001007 Rev 02
Long sections rail alignment Sheet 12.16DTRS-DRG-FA-001004 Rev 02
Long sections rail alignment Sheet 22.16ETRS-DRG-FA-001008 Rev 02
The speed limit plans
Key Plan2.12WSP-70001979-SK-062 Rev I
Sheet 12.12AWSP-70001979-SK-062 Rev K
Sheet 22.12BWSP-70001979-SK-062 Rev F
Sheet 32.12CWSP-70001979-SK-062 Rev E
SI facility plan2.2001
The traffic regulation plans
Key Plan2.11WSP-70001979-SK-061 Rev I
Sheet 12.11AWSP-70001979-SK-061 Rev H
Sheet 22.11BWSP-70001979-SK-061 Rev E
Sheet 32.11CWSP-70001979-SK-061 Rev F
Sheet 42.11DWSP-70001979-SK-061 Rev A
The works plans
Key Plan2.2Key Plan v3.0
Sheet 12.2ASheet 1 of 9 v3.0
Sheet 22.2BSheet 2 of 9 v3.0
Sheet 32.2CSheet 3 of 9 v1
Sheet 42.2DSheet 4 of 9 v1
Sheet 52.2ESheet 5 of 9 v1
Sheet 62.2FSheet 6 of 9 v3.0
Sheet 72.2GSheet 7 of 9 v1
Sheet 82.2HSheet 8 of 9 v1
Sheet 92.2ISheet 9 of 9 v1

EXPLANATORY NOTE

(This note is not part of the Order)

This Order further amends the West Midlands Rail Freight Interchange Order 2020 (S.I. 2020/511) (“the 2020 Order”), a development consent order within the meaning of the Planning Act 2008 (”the Act”).

This Order follows an application under paragraph 2 of Schedule 6 to the Act to make a non-material change to the 2020 Order to one spot level for road infrastructure identified on the parameters plans.

A copy of the substituted plans mentioned in this Order may be inspected free of charge during working hours at the offices of South Staffordshire Council at Wolverhampton Road, Codsall, Wolverhampton, WV8 1PX.

(1)

2008 c. 29; paragraph 2 of Schedule 6 was amended by paragraph 4(6)(a) of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23), by paragraph 72(3) to (7) of Schedule 13, and by Part 20 of Schedule 25, to the Localism Act 2011 (c. 20), by section 28(2) of the Infrastructure Act 2015 (c. 7), and by section 128 of the Levelling-up and Regeneration Act 2023 (c. 55).