Print Options
PrintThe Whole
Instrument
PrintThe Whole
Part
PrintThis
Section
only
Status:
Point in time view as at 25/10/2013. This version of this provision has been superseded.
Status
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Changes to legislation:
There are currently no known outstanding effects for the The Nitrate Pollution Prevention (Wales) Regulations 2013, Section 33.
Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Further requirements applicable to temporary field sites from 1 January 2014E+W
33. Further to regulation 32, from 1 January 2014—
(a)topsoil must not be removed from the ground upon which a temporary field site is to be constructed;
(b)a temporary field site must not be located within 30m of a watercourse on land identified on the risk map as having an incline of greater than 12�; and
(c)the surface area of a temporary field site should be as small as reasonably practicable to minimise the leaching effect of rainfall.