Print Options
PrintThe Whole
Instrument
PrintThe Whole
Part
PrintThis
Section
only
Changes over time for: Section 33
Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Version Superseded: 01/04/2021
Status:
Point in time view as at 25/10/2013. This version of this provision has been superseded.
Status
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Changes to legislation:
There are currently no known outstanding effects for the The Nitrate Pollution Prevention (Wales) Regulations 2013, Section 33.
Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Further requirements applicable to temporary field sites from 1 January 2014E+W
33. Further to regulation 32, from 1 January 2014—
(a)topsoil must not be removed from the ground upon which a temporary field site is to be constructed;
(b)a temporary field site must not be located within 30m of a watercourse on land identified on the risk map as having an incline of greater than 12�; and
(c)the surface area of a temporary field site should be as small as reasonably practicable to minimise the leaching effect of rainfall.
Back to top