PART 1SIGNIFICANT INFRASTRUCTURE PROJECTS

Waste

15Hazardous waste facilities

1

The construction of a hazardous waste facility is a significant infrastructure project if—

a

the facility is in Wales or the Welsh marine area,

b

the main purpose of the facility is the final disposal or recovery of hazardous waste, and

c

the facility is expected to have the capacity specified in subsection (2).

2

The capacity is—

a

in the case of the disposal of hazardous waste by landfill or in a deep storage facility, more than 100,000 tonnes per year;

b

in any other case, more than 30,000 tonnes per year.

3

The alteration of a hazardous waste facility is significant infrastructure project if—

a

the facility is in Wales or the Welsh marine area,

b

the main purpose of the facility is the final disposal or recovery of hazardous waste, and

c

the alteration is expected to increase the capacity of the facility—

i

in the case of the disposal of hazardous waste by landfill or in a deep storage facility, by more than 100,000 tonnes per year;

ii

in any other case, by more than 30,000 tonnes per year.

4

In this section, “deep storage facility” means a facility for the storage of waste underground in a deep geological cavity.

5

The following terms used in this section have the same meanings as in the Hazardous Waste (England and Wales) Regulations 2005 (S.I. 2005/894) (as amended from time to time)—

  • disposal” (“gwaredu”);

  • hazardous waste” (“gwastraff peryglus”);

  • recovery” (“adfer”).