Print Options
PrintThe Whole
Act
PrintThe Whole
Part
PrintThe Whole
Cross Heading
PrintThis
Section
only
Status:
This version of this provision is prospective.
Status
The term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section. A version of a provision is prospective either:
- where the provision (Part, Chapter or section) has never come into force or;
- where the text of the provision is subject to change, but no date has yet been appointed by the appropriate person or body for those changes to come into force.
Commencement Orders listed in the ‘Changes to Legislation’ box as not yet applied may bring this prospective version into force.
Changes to legislation:
There are currently no known outstanding effects for the Infrastructure (Wales) Act 2024, Section 64.
Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Prospective
64Purpose for which compulsory acquisition may be authorisedE+W
This section has no associated Explanatory Notes
(1)An infrastructure consent order may include provision authorising the compulsory acquisition of land only if the Welsh Ministers are satisfied that the conditions in subsections (2) and (3) are met.
(2)The condition is that the land—
(a)is required for the development to which the development consent relates,
(b)is required to facilitate or is incidental to that development, or
(c)is replacement land which is to be given in exchange for the order land under section 70 or 71.
(3)The condition is that there is a compelling case in the public interest for the land to be acquired compulsorily.