1SA summary of the characterisation of the river basin district carried out under section 5.
Commencement Information
I1Sch. 1 para. 1 in force at 20.5.2005 by S.S.I. 2005/256, art. 2(b)
2SA summary of significant pressures, and the impact of human activity, on the status of the water environment within the district.
Commencement Information
I2Sch. 1 para. 2 in force at 20.5.2005 by S.S.I. 2005/256, art. 2(b)
3SA summary of the register of protected areas maintained under section 7, including information sufficient to identify each protected area within the district.
Commencement Information
I3Sch. 1 para. 3 in force at 20.5.2005 by S.S.I. 2005/256, art. 2(b)
4SInformation as to the arrangements for monitoring water status under section 8 and as to the results of such monitoring.
Commencement Information
I4Sch. 1 para. 4 in force at 20.5.2005 by S.S.I. 2005/256, art. 2(b)
5SA list of the environmental objectives set under section 9 for every body of water in the district.
Commencement Information
I5Sch. 1 para. 5 in force at 20.5.2005 by S.S.I. 2005/256, art. 2(b)
6SA summary of the programme of measures prepared under section 9 to be applied to achieve those objectives.
Commencement Information
I6Sch. 1 para. 6 in force at 20.5.2005 by S.S.I. 2005/256, art. 2(b)
7SInformation as to any sub-basin plan.
Commencement Information
I7Sch. 1 para. 7 in force at 20.5.2005 by S.S.I. 2005/256, art. 2(b)
8SA non-technical summary of the information provided under paragraphs 1 to 7.
Commencement Information
I8Sch. 1 para. 8 in force at 20.5.2005 by S.S.I. 2005/256, art. 2(b)
9SA summary of—
(a)the steps taken under subsections (3) to (6) of section 11 in relation to the plan, and
(b)changes made to the plan in light of—
(i)the views and representations received on it, and
(ii)any advice given by a River Basin District Advisory Group under section 17(2).
Commencement Information
I9Sch. 1 para. 9 in force at 20.5.2005 by S.S.I. 2005/256, art. 2(b)
10SInformation as to—
(a)SEPA, and
(b)every responsible authority and regulator (within the meaning of schedule 2) having functions in relation to the river basin district.
Commencement Information
I10Sch. 1 para. 10 in force at 20.5.2005 by S.S.I. 2005/256, art. 2(b)
11SThe arrangements for making available to the public documents and information relevant to the preparation and implementation of the plan.