Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

ExtinctionS

15DischargeS

(1)A real burden is discharged as respects a benefited property by registering against the burdened property a deed of discharge granted by or on behalf of the owner of the benefited property.

(2)In subsection (1) above, “discharged” means discharged—

(a)wholly; or

(b)to such extent as may be specified in the deed of discharge.

Commencement Information

I1S. 15 wholly in force; s. 15 in force for certain purposes at 4.4.2003 see s. 129(2)(5); s. 15 otherwise in force at 28.11.2004 by S.S.I. 2003/456, art. 2

16AcquiescenceS

(1)Where—

(a)a real burden is breached in such a way that material expenditure is incurred;

(b)any benefit arising from such expenditure would be substantially lost were the burden to be enforced; and

(c)in the case of—

(i)a burden other than a conservation burden, economic development burden or health care burden, the owner of the benefited property (if any) has an interest to enforce the burden in respect of the breach and consents to the carrying on of the activity which results in that breach, or every person by whom the burden is enforceable and who has such an interest, either so consents or, being aware of the carrying on of that activity (or, because of its nature, being in a position where that person ought to be aware of it), has not, by the expiry of such period as is in all the circumstances reasonable (being in any event a period which does not exceed that of twelve weeks beginning with the day by which that activity has been substantially completed), objected to its being carried on; or

(ii)a conservation burden, economic development burden or health care burden, the person by whom the burden is enforceable consents to the carrying on of that activity,

the burden shall, to the extent of the breach, be extinguished.

(2)Where the period of twelve weeks following the substantial completion of an activity has expired as mentioned in sub-paragraph (i) of subsection (1)(c) above, it shall be presumed, unless the contrary is shown, that the person by whom the real burden was, at the time in question, enforceable (or where a burden is enforceable by more than one person, each of those persons) was, or ought to have been, aware of the carrying on of the activity and did not object as mentioned in that sub-paragraph.

Modifications etc. (not altering text)

Commencement Information

I2S. 16 wholly in force; s. 16 in force for certain purposes at 4.4.2003 see s. 129(2)(5); s. 16 otherwise in force at 28.11.2004 by S.S.I. 2003/456, art. 2

17Further provision as regards extinction where no interest to enforceS

Where at any time a real burden is breached but at that time no person has an interest to enforce it in respect of the breach, the burden shall, to the extent of the breach, be extinguished.

Commencement Information

I3S. 17 wholly in force; s. 17 in force for certain purposes at 4.4.2003 see s. 129(2)(5); s. 17 otherwise in force at 28.11.2004 by S.S.I. 2003/456, art. 2

18Negative prescriptionS

(1)Subject to subsection (5) below, if—

(a)a real burden is breached to any extent; and

(b)during the period of five years beginning with the breach neither—

(i)a relevant claim; nor

(ii)a relevant acknowledgement,

is made,

then, subject to subsection (2) below, the burden shall, to the extent of the breach, be extinguished on the expiry of that period.

(2)Subject to subsections (5) and (6) below, where, in relation to a real burden which consists of—

(a)a right of pre-emption, redemption or reversion; or

(b)any other type of option to acquire the burdened property,

the owner of the burdened property fails to comply with an obligation to convey (or, as the case may be, to offer to convey) the property (or part of the property) and paragraph (b) of subsection (1) above is satisfied, the burden shall be extinguished in relation to the property (or part) on the expiry of the period mentioned in the said paragraph (b).

(3)Sections 9 and 10 of the Prescription and Limitation (Scotland) Act 1973 (c. 52) (which define the expressions “relevant claim” and “relevant acknowledgement” for the purposes of sections 6, 7 and 8A of that Act) shall apply for the purposes of subsections (1) and (2) above as those sections apply for the purposes of sections 6, 7 and 8A of that Act but subject to the following modifications—

(a)in each of sections 9 and 10 of that Act—

(i)subsection (2) shall not apply;

(ii)for any reference to an obligation there shall be substituted a reference to a real burden; and

(iii)for any reference to a creditor there shall be substituted a reference to any person by whom a real burden is enforceable;

(b)in section 9 of that Act, for the reference to a creditor in an obligation there shall be substituted a reference to any person by whom a real burden is enforceable; and

(c)in section 10 of that Act, for any reference to a debtor there shall be substituted a reference to any person against whom the real burden is enforceable.

(4)Section 14 of the said Act of 1973 (which makes provision as respects the computation of prescriptive periods) shall apply for the purposes of subsections (1) and (2) above as that section applies for the purposes of Part I of that Act except that paragraph (a) of subsection (1) of that section shall for the purposes of those subsections be disregarded.

(5)In relation to a breach occurring before the appointed day, subsections (1) and (2) above apply with the substitution in paragraph (b) of subsection (1), for the words “period of five years beginning with the breach”, of the words “ appropriate period ”.

(6)In the case of a right of pre-emption constituted as a rural housing burden, subsection (2) above shall apply with the modification that for the words “the burden shall be extinguished in relation to the property (or part) on” there shall be substituted “ it shall not be competent to commence any action in respect of that failure after ”.

(7)The reference, in subsection (5) above, to the “appropriate period” is to whichever first expires of—

(a)the period of five years beginning with the appointed day; and

(b)the period of twenty years beginning with the breach.

Modifications etc. (not altering text)

Commencement Information

I4S. 18 wholly in force; s. 18 in force for certain purposes at 4.4.2003 see s. 129(2)(5); s. 18 otherwise in force at 28.11.2004 by S.S.I. 2003/456, art. 2

19Confusio not to extinguish real burdenS

A real burden is not extinguished by reason only that—

(a)the same person is the owner of the benefited property and the burdened property; or

(b)in a case in which there is no benefited property, the person in whose favour the real burden is constituted is the owner of the burdened property.

Commencement Information

I5S. 19 wholly in force; s. 19 in force for certain purposes at 4.4.2003 see s. 129(2)(5); s. 19 otherwise in force at 28.11.2004 by S.S.I. 2003/456, art. 2

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the Scottish Government to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Acts of the Scottish Parliament except those which result from Budget Bills.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources