Part 5 SMiscellaneous and General

66Compliance with Code of Construction Practice and Noise and Vibration PolicyS

(1)The authorised undertaker shall employ all reasonably practicable means to ensure that—

(a)the authorised works are carried out in accordance with the code of practice as may from time to time be amended or superseded and any relevant local construction plan; and

(b)the policy as may from time to time be amended or superseded is applied to the use and operation of the authorised works and in particular any scheme made under section 63 of this Act is drawn up in accordance with the policy.

(2)Neither the code of practice nor the policy shall be amended or superseded so as to reduce the standards of mitigation and protection contained in them.

(3)In this section—