SCHEDULE 1Matters to be included in flood risk management plans
Part 2Components of the subsequent update of flood risk management plans
11
A summary of any changes which have been made as compared to the previous version of the plan.
12
An assessment of the progress made towards the achievement of the objectives included in the plan under paragraph 1(a).
13
A summary of any measures included in the previous plan under paragraph 1(b) which were not implemented, with reasons for the non-implementation.
14
A description of any other measures implemented since the publication of the previous version of the plan which SEPA considers have contributed to the achievement of the objectives included in the plan under paragraph 1(a).