Flood Risk Management (Scotland) Act
2009 asp 6
The Act – Section by Section
Part 5 – Sepa: Other Flood Risk Management Functions
Section 76 – Provision, alteration etc. of flood warning system
214.This section allows SEPA to provide, operate, alter and maintain flood warning systems and to carry out any building or engineering work required to provide and install apparatus for that purpose. “Flood warning system” is defined in section 75(4).
215.This section replaces sections 92 and 94 of the Agriculture Act 1970, which are repealed by paragraph 2 of schedule 3. SEPA’s general powers under section 37 of the Environment Act 1995 apply in relation to its functions under this section, including powers to acquire and dispose of land and other property and carry out such engineering or building operations as it considers appropriate.
216.Subsection (2) and section 77(2) require SEPA to consult the relevant local authorities and chief constables before it exercises its powers to provide a new flood warning system or to make material alterations to an existing system.
- Previous
- Explanatory Notes Table of contents
- Next