This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 01/04/2015.
Changes to legislation:
There are currently no known outstanding effects for the Reservoirs (Scotland) Act 2011, Section 4.
Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
4Multiple reservoir managers: supplementaryS
This section has no associated Explanatory Notes
(1)This section applies where by virtue of section 3 there is more than one reservoir manager of a controlled reservoir.
(2)The requirements of this Part apply in relation to each of the reservoir managers (whether or not they make a nomination under subsection (3)).
(3)Any of the reservoir managers (“the nominating manager”) may nominate another of the reservoir managers (“the nominee”) to do any of the following—
(a)fulfil on behalf of the nominating manager any requirements of this Part to which the nominating manager is subject and which are specified in the nomination,
(b)exercise any rights the nominating manager has under this Part and which are so specified.
(4)Where a nomination is made under subsection (3)—
(a)the nominating manager must give notice of the nomination to—
(i)SEPA,
(ii)any construction engineer, inspecting engineer or supervising engineer appointed in relation to the reservoir,
(b)SEPA may notify and consult the nominee in accordance with the nomination,
(c)any construction engineer, inspecting engineer or supervising engineer appointed in relation to the reservoir may give any notice, report, certificate or other document (required by this Part to be given to the reservoir manager of the reservoir) to the nominee in accordance with the nomination.