Part 3Specific duties
Giving of reasons
33Request for further information
1
The following persons may request further information in relation to a regulated procurement (other than an EU-regulated procurement)—
a
an economic operator who was excluded from participating in the procurement process before it submitted a tender,
b
an unsuccessful tenderer,
c
the successful tenderer.
2
The request must be—
a
in writing, and
b
made before the end of the period of 30 days beginning on—
i
in the case of a person mentioned in subsection (1)(a) or (b), the day the person received a notice under section 32,
ii
in the case of the successful tenderer, the day on which it was notified of the decision to award the contract.
3
The contracting authority must, before the end of the period of 30 days beginning on the day it receives the request, provide the relevant information.
4
The relevant information is—
a
in the case of an economic operator excluded from the participating in the procurement process, a summary of the reasons why the economic operator was excluded,
b
in the case of an unsuccessful tenderer—
i
a summary of the reasons why the tenderer was unsuccessful, and
ii
the characteristics and relative advantages of the successful tender,
c
in the case of the successful tenderer, a description of any improvements the contracting authority considers the tenderer could have made to its tender.