Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
(1)In this Act—
“award notice” has the meaning given in section 23(6),
“community benefit requirement” has the meaning given in section 24,
“contract notice” has the meaning given in section 23(6),
“contracting authority” has the meaning given in section 1,
“economic operator” means any person who offers the execution of works, the supply of products or the provision of services on the market,
“financial year” means the period of 12 months in respect of which the accounts of the contracting authority in question are prepared,
“public contract” [F1means a contract for pecuniary interest concluded in writing between one or more economic operators and one or more contracting authorities and having as its object the execution of works, the supply of products or the provision of services]
“Public Contracts website” has the meaning given in section 22,
“public works contract” [F2means a public contract having as its object one of the following—
the execution or the design and execution of works related to one of the activities within the meaning of schedule 2 of the Public Contracts Regulations,
the execution or the design and execution of a work,
the realisation, by whatever means, of a work corresponding to the requirements specified by the contracting authority exercising a decisive influence on the type or design of the work,
(except in a subsidised public works contract),]
“regulated procurement” has the meaning given in section 2.
[F3“work” means the outcome of building or civil engineering works taken as a whole which is sufficient in itself to fulfil an economic or technical function.]
(2)In this Act, a contracting authority's area is the area by reference to which the contracting authority primarily exercises its functions, disregarding any areas outside Scotland.
Textual Amendments
F1Words in s. 42 substituted (31.12.2020) by The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 3(7)(a) (with sch. paras. 1-5)
F2Words in s. 42 substituted (31.12.2020) by The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 3(7)(b) (with sch. paras. 1-5)
F3Words in s. 42(1) inserted (31.12.2020) by The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 3(7)(c) (with sch. paras. 1-5)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the Scottish Government to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Acts of the Scottish Parliament except those which result from Budget Bills.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: