Land Reform (Scotland) Act 2016, Cross Heading: Strategic plan and programme of work is up to date with all changes known to be in force on or before 23 December 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
(1)The Commission must prepare a strategic plan setting out how the Commission, the Land Commissioners and the Tenant Farming Commissioner propose to exercise their respective functions for the period to which the plan relates.
(2)A strategic plan must, in particular, set out—
(a)the objectives and priorities of—
(i)the Commission,
(ii)the Land Commissioners,
(iii)the Tenant Farming Commissioner,
(b)estimates of the costs of the exercise of their respective functions of—
(i)the Commission,
(ii)the Land Commissioners,
(iii)the Tenant Farming Commissioner.
(3)The Commission must submit the strategic plan to the Scottish Ministers—
(a)in the case of the first plan, before the end of the period of 6 months beginning with the day on which this section comes into force,
(b)in the case of each subsequent plan, before the end of the period of 3 years beginning with the day on which the Commission last submitted its strategic plan.
(4)The Scottish Ministers may—
(a)approve the strategic plan,
(b)approve the strategic plan with such modifications as they consider appropriate in consultation with the Commission,
(c)reject the strategic plan and direct the Commission to submit a revised plan before the end of such period as the Scottish Ministers may determine.
(5)Where the Scottish Ministers approve the strategic plan under subsection (4)(a) or (4)(b), the Commission must as soon as practicable—
(a)publish the plan in such form as it considers appropriate, and
(b)lay a copy of the plan before the Scottish Parliament.
(6)The Commission—
(a)must comply with any direction to submit a revised strategic plan under subsection (4)(c),
(b)may from time to time submit a revised strategic plan.
(7)Subsections (4) and (5) apply to a revised strategic plan as they apply to a strategic plan.
Commencement Information
I1S. 8 in force at 1.4.2017 by S.S.I. 2016/250, reg. 2(3), sch. 2
(1)The Land Commissioners must prepare a programme of work setting out—
(a)information on any proposed reviews under section 22(1)(a),
(b)information on any other activities,
(c)timetables for the programme.
(2)The Commission must submit the Land Commissioners' programme of work to the Scottish Ministers when it submits the strategic plan under section 8.
(3)The Commission must—
(a)publish the programme of work in such form as it considers appropriate, and
(b)lay a copy of the programme before the Scottish Parliament.
(4)The Commission may from time to time submit a revised programme of work.
(5)Subsection (3) applies to a revised programme of work as it applies to a programme of work.
Commencement Information
I2S. 9 in force at 1.4.2017 by S.S.I. 2016/250, reg. 2(3), sch. 2
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the Scottish Government to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Acts of the Scottish Parliament except those which result from Budget Bills.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: