- Y Diweddaraf sydd Ar Gael (Diwygiedig)
- Gwreiddiol (Fel y'i Deddfwyd)
There are currently no known outstanding effects for the Airdrie-Bathgate Railway and Linked Improvements Act 2007, Part 1 .
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
The authorised undertaker may construct—
(a)the scheduled works referred to in section 2 (“the scheduled works”); and
(b)the ancillary works referred to in section 3 (“the ancillary works”).
(1)The scheduled works are the works situated within the lateral limits of deviation shown on the Parliamentary plans, at the levels shown on the Parliamentary sections and specifically described in schedule 1 to this Act.
(2)The extent of the scheduled works for which authority is given by this section is subject to section 4 (which permits deviation within limits from the lines and levels shown on the Parliamentary plans and sections).
(1)The ancillary works are such works of the nature described in schedule 2 to this Act as may be necessary or expedient for the purposes of, in connection with or in consequence of the construction of the scheduled works.
(2)Subject to subsection (3), subsection (1) only authorises the carrying out or maintenance of works—
(a)within the limits of deviation; and
(b)on land specified in columns (1), (2) and (3) of Part 1, 2 or 3 of schedule 5 for the purpose specified in relation to that land in column (4) of that Part (being land shown on the Parliamentary plans as lying within the limits of land to be acquired or used).
(3)The authorised undertaker may construct and maintain ancillary works identified in paragraphs 10 and 11 of schedule 2 to this Act anywhere within the limits of deviation or the limits of land to be acquired or used.
In constructing or maintaining the scheduled works the authorised undertaker may—
(a)deviate laterally from the lines or situations shown on the Parliamentary plans within the limits of deviation for that work shown on those plans; and
(b)deviate vertically from the levels shown on the Parliamentary sections—
(i)upwards by a maximum of 3 metres; and
(ii)to any extent downwards.
(1)The authorised undertaker may, for or in connection with the authorised works, form and lay out means of access, or improve existing means of access, to or from any public road—
(a)at the points shown on the Parliamentary plans; or
(b)in such location or locations within the limits of deviation or the limits of land to be acquired or used as may be approved by the roads authority.
(2)Approval of the roads authority under subsection (1)(b) shall not be unreasonably withheld or delayed and any question whether an approval has been unreasonably withheld or delayed shall, unless the parties otherwise agree, be determined by arbitration.
(1)Each of the roads specified in columns (1) and (2) of Part 1 of schedule 11 to this Act, excluding any structures specified in column (3) shall, unless otherwise agreed between the authorised undertaker and the roads authority, be completed to the reasonable satisfaction of the roads authority.
(2)Following completion of any road to which subsection (1) applies, the road shall, unless otherwise agreed between the authorised undertaker and the roads authority, be maintained by and at the expense of the authorised undertaker for a period of 12 months from its completion.
(3)Subject to subsections (4) and (9), on completion of each of the authorised works specified in column (1) of Part 2 of schedule 11 to this Act, title to that work, and in the case of the road, bus lay-by or car parks—
(a)the land on which each of them is constructed; and
(b)any other land acquired by the authorised undertaker for the purpose of constructing the road, bus lay-by or car parks,
shall, at the time specified in column (2), by virtue of this section vest in the roads authority.
(4)The extent of the roads vested by virtue of subsection (3)—
(a)shall not include—
(i)any structure specified in column (3) of Part 1 of schedule 11; or
(ii)any operational land held by Network Rail; and
(b)shall be subject to any determination by the authorised undertaker;
and such vesting shall be subject to such rights as may be requisite for the benefit or protection of the authorised works or Network Rail's railway undertaking.
(5)Following completion of the structures described in column (3) of Part 1 of schedule 11 to this Act, those structures shall vest in Network Rail (if not already so vested).
(6)The authorised undertaker shall give the roads authority notice in writing with a certificate that any authorised work to which subsection (3) applies is complete.
(7)The roads authority may, within 21 days after such service, give the authorised undertaker a counter-notice in writing that the notice is disputed on the ground that the work is not complete.
(8)Any dispute as to the completion of a work shall be determined by arbitration, and the determination of the arbiter (or other person to whom the dispute is referred) shall be final and binding.
(9)Any work or associated land which is the subject of a notice under subsection (6) shall vest—
(a)28 days after the service of the notice;
(b)on the date of a determination under subsection (8) that the work is complete;
(c)on the date on which the authorised undertaker complies with any conditions for completion that are specified in the determination; or
(d)on the completion of the work as provided by subsection (3),
whichever is the latest.
(10)A certificate issued by or on behalf of the authorised undertaker as to the date on which the authorised undertaker complied with any conditions of the sort referred to in subsection (9)(c) together, if so requested by the roads authority, with a report from a consultant to be agreed between the authorised undertaker and the roads authority confirming such compliance, shall for the purposes of this section be conclusive evidence of such compliance.
(11)Nothing in this section shall prejudice the operation of section 146 of the 1991 Act (which enables the local roads authority to declare that a road shall become a public road); and the authorised undertaker shall not by reason of any duty under this section to maintain a road be taken to be the roads authority in relation to that road for the purposes of Part IV of that Act.
(12)Nothing in this section shall have effect in relation to road works in respect of which the provisions of Part IV of the 1991 Act apply.
(1)Subject to subsections (3) and (8), on completion of each of the private accesses specified in columns (1) and (2) of Part 3 of schedule 11 to this Act, the private access and its associated land shall, if they are vested in the authorised undertaker, by virtue of this section vest in the intended owner.
(2)Any vesting effected by subsection (1) shall be subject to such rights specified by the authorised undertaker as may be requisite to reflect public or private rights in any access for which the private access is a substitute.
(3)The extent of the private access vested by virtue of subsection (1)—
(a)shall not include—
(i)any structure specified in column (3) of Part 3 of schedule 11 to this Act; or
(ii)any operational land held by Network Rail; and
(b)shall be subject to any determination by the authorised undertaker.
(4)Following completion of the structures specified in column (3) of Part 3 of schedule 11 to this Act, those structures shall vest in Network Rail (if not already so vested).
(5)The authorised undertaker shall give every person in whom it intends to vest any access or associated land under this section not less than 28 days' notice in writing specifying—
(a)the private access or associated land that is to be vested;
(b)details of any other person in whom that access or land is to be vested; and
(c)details of any rights to which the access or land is to be subject and of every person who has or will have such rights,
together with a certificate that the access is complete.
(6)A person on whom a notice is served under subsection (5) may, within 21 days after such service, give the authorised undertaker a counter-notice in writing that the notice is disputed on the grounds that—
(a)the person on whom the notice has been served is not such a person as is described in subsection (10);
(b)the access is not complete; or
(c)any rights specified under subsection (5)(c) are not such as described in that subsection.
(7)Any dispute as to whether a person is such a person as is described in subsection (10), as to the completion of a private access or as to whether rights specified in a notice are such as described in subsection (5)(c) shall be determined by arbitration, and the determination of the arbiter (or other person to whom the dispute is referred) shall be final and binding.
(8)Any private access or associated land which is the subject of a notice under subsection (5) shall vest—
(a)28 days after the service of notice under subsection (5);
(b)on the date of a determination under subsection (7) that the person on whom the notice has been served is such a person as is described in subsection (10) and that the access is complete;
(c)on the date on which the authorised undertaker complies with any conditions for completion that are specified in the determination; or
(d)on the completion of the access as provided by subsection (1),
whichever is the latest.
(9)A certificate issued by or on behalf of the authorised undertaker as to the date on which the authorised undertaker complied with any conditions of the sort referred to in subsection (8)(c) shall for the purposes of this section be conclusive evidence of such compliance.
(10)In this section “intended owner” means a person or persons identified by the authorised undertaker to become the owner of a private access constructed under this Act as being—
(a)the owner of the private access for which the private access being vested is a substitute; or
(b)the owner of land that is served by the private access.
(1)On the completion of Work No. 1G, Work No. 46 or the provision of a rail freight and car stabling depot at Boghall, whichever is later, plots nos. 839 and 840 in West Lothian shall by virtue of this section, and subject to such rights as may be requisite for the benefit or protection of Network Rail's railway undertaking, vest in EWS Railway.
(2)The authorised undertaker shall give EWS Railway not less than 28 days' notice in writing with a certificate that any work or facility referred to in subsection (1) is complete.
(3)The provisions of subsections (7) to (10) of section 6 shall apply to a notice given under subsection (2) of this section as if any reference in those subsections to a work or associated land were a reference to any work or facility referred to in subsection (1) of this section, and as if references to the roads authority were references to EWS Railway.
(4)In this section “EWS Railway” means English Welsh and Scottish Railway Limited (company no. 02938988).
(1)The Keeper of the Registers of Scotland may, without prejudice to [F1Part 2 of the Land Registration etc. (Scotland) Act 2012 (asp 5)], register any land vested under section 6, 7 or 8 on receiving the material specified in subsection (2).
(2)The material referred to in subsection (1) is—
(a)particulars of the land vested under section 6, 7 or 8 sufficient to enable the Keeper to identify it by reference to the Ordnance Map;
(b)particulars of the person or persons in whom the land is vested;
(c)an application for registration made by or on behalf of the authorised undertaker or the person in whom the land is vested;
(d)details of any rights to which the vesting is subject;
(e)such proof as the Keeper may require that the events giving rise to the vesting have happened; and
(f)such other documents and evidence as the Keeper may require in order to satisfy himself that the vesting should be registered.
Textual Amendments
F1Words in s. 9(1) substituted (8.12.2014) by Land Registration etc. (Scotland) Act 2012 (asp 5), ss. 122, 123, Sch. 5 para. 54(2) (with s. 121, Sch. 4 paras. 13, 16); S.S.I. 2014/127, art. 2
(1)Subject to the provisions of this section, the authorised undertaker may, in connection with the construction of the authorised works, stop up each of the roads specified in columns (1) and (2) of Part 1 of schedule 3 to this Act to the extent specified (by reference to the letters and numbers shown on the Parliamentary plans) in column (3) of that Part.
(2)No part of a road specified in Part 1 of schedule 3 to this Act in relation to which a substitute road is specified in column (4) of that Part shall be stopped up under this section until either—
(a)the substitute has been completed to the reasonable satisfaction of the roads authority and is open for public use; or
(b)a temporary alternative route is first provided and thereafter maintained by the authorised undertaker to the reasonable satisfaction of the roads authority between commencement and termination points of the road to be stopped up until completion of the new road in accordance with paragraph (a).
(3)Where any part of a road has been stopped up under this section—
(a)all rights of way over or along the stopped up part of the road shall be extinguished; and
(b)the authorised undertaker may, without making any payment, appropriate and use for the purposes of the authorised works so much of the site of the road as is bounded on both sides by land within the limits of deviation of the authorised works.
(4)Any person who suffers loss by the extinguishment of any private right of way under this section shall be entitled to compensation to be determined, in case of dispute, under the 1963 Act.
(5)Any dispute under subsection (2) as to the completion of a substitute road or the provision or maintenance of an alternative route shall, unless the authorised undertaker and the roads authority otherwise agree, be determined by arbitration.
(6)This section is subject to paragraph 2 of schedule 7 to this Act.
(1)If the authorised undertaker proceeds with the authorised works it shall make and maintain the private crossings under or over the railway described in Part 1 of schedule 4 to this Act (“the continuing private crossings”).
(2)The continuing private crossings shall be provided for the use of the persons (if any) entitled under any existing enactment to use the existing private crossings at those points, and those persons shall be entitled to use the continuing private crossings on the same basis in all respects as they are entitled to use the existing private crossings.
(3)The authorised undertaker shall provide and maintain at each of the continuing private crossings such equipment as may from time to time be required for compliance with any requirement made under any enactment and, subject to such compliance, as may be agreed in relation to any crossing between the authorised undertaker and the person entitled to use the crossing.
(4)Nothing in section 60 of the 1845 Act, as incorporated with this Act, shall require the authorised undertaker to provide any other private crossing for the purpose of making good any interruption caused by the authorised works to the use of any lands to which there attaches an entitlement to use any of the continuing private crossings.
(5)The authorised undertaker may stop up and discontinue the private crossings described in Part 2 of schedule 4 to this Act and on such stopping up and discontinuance all rights of way across those crossings (if any) shall be extinguished and any obligation to maintain them as crossings (howsoever arising) shall cease to have effect.
(6)Any right or servitude which relates to a crossing of the former railway and which is not described in Part 2 of schedule 4 to this Act shall be extinguished and any obligation relating to such a crossing (however arising) shall cease to have effect.
(7)Any person who suffers loss by the extinguishment of any right of way over any of the crossings described in Part 2 of schedule 4 to this Act shall be entitled to compensation to be determined, in case of dispute, under the 1963 Act.
(1)The authorised undertaker may, for the purposes of exercising the powers conferred by this Act to construct any scheduled work having a junction with a road, enter upon any road and execute any works required for or incidental to the exercise of those powers.
(2)In exercise of the powers of subsection (1) the authorised undertaker may break up or open the road, or any sewer, drain or tunnel under it, may tunnel or bore under or open the road and may remove and use the soil or other materials in or under the road.
(1)Works to which subsection (2) applies shall be treated for the purposes of Part IV of the 1991 Act as major works for roads purposes if—
(a)they are of a description mentioned in any of paragraphs (a) to (d), (f) and (g) of section 145(3) of that Act (which defines what roads authority works are major works for roads purposes); or
(b)they are works which, had they been executed under the powers of the roads authority, might have been carried out in exercise of the powers conferred by section 27 (dual carriageways, roundabouts and refuges) or 63 (new access over verges and footways) of the Roads (Scotland) Act 1984 (c. 54).
(2)Subject to subsection (3), this subsection applies to any of the works mentioned in section 6(1), or any scheduled work having a junction with a road, in either case where the construction of the work involves the execution of road works in relation to a road which consists of or includes a carriageway.
(3)Subsection (2) does not apply to any work executed under power delegated to a roads authority by an agreement under section 14.
(4)In Part IV of the 1991 Act, references, in relation to major works for roads purposes, to the roads authority concerned shall, in relation to the works which are major works for roads purposes by virtue of subsection (1), be construed as references to the authorised undertaker.
(1)Where under this Act the authorised undertaker is authorised to stop up or interfere with an existing road or part of an existing road, it may enter into agreements with the persons having the charge, management or control of the road concerning the construction (or contribution towards the expense of the construction) of—
(a)any new road to be provided in substitution;
(b)any alteration of the existing road; and
(c)any other related matters.
(2)The authorised undertaker may, by agreement with any such persons, delegate to them the power of constructing any such new road or any such alteration of an existing road, including any bridge over any railway, and, where the authorised undertaker is responsible for maintaining the new or altered road or bridge, the power to maintain it.
(1)During and for the purposes of the execution of the authorised works the authorised undertaker may temporarily stop up, alter or divert any road and may for any reasonable time—
(a)divert the traffic from the road; and
(b)subject to subsection (3), prevent all persons from passing along the road.
(2)Without prejudice to the generality of subsection (1), the authorised undertaker may exercise the powers of this section in relation to each of the roads specified in columns (1) and (2) of Part 2 of schedule 3 to this Act to the extent specified (by reference to the letters and numbers shown on the relevant Parliamentary plans) in column (3) of that Part.
(3)Without prejudice to the generality of subsection (1), the authorised undertaker may use any road stopped up under the powers of this section as a temporary working site.
(4)The authorised undertaker shall provide reasonable access for pedestrians going to or from premises abutting on a road affected by the exercise of the powers conferred by this section if there would otherwise be no such access.
(5)The authorised undertaker shall not exercise the powers conferred by this section—
(a)in relation to any road specified as mentioned in subsection (2), without first consulting the road works authority; and
(b)in relation to any other road, without the consent of the road works authority.
(6)Consent under subsection (5)(b) shall not be unreasonably withheld or delayed but may be given subject to such reasonable conditions as the road works authority may require.
(7)Any question whether—
(a)consent under subsection (5)(b) has been unreasonably withheld or delayed; or
(b)a condition imposed under subsection (6) is unreasonable,
shall, unless the parties otherwise agree, be determined by arbitration.
(1)The authorised undertaker may use any available watercourse or any public sewer or drain for the drainage of water, and for that purpose may—
(a)lay down, take up and alter pipes; or
(b)make openings into, and connections with the watercourse, public sewer or drain,
on any land within the limits of deviation or the limits of land to be acquired or used.
(2)The authorised undertaker shall not discharge any water into any artificial watercourse, or any public sewer or drain, except with the consent of the person to whom it belongs; and such consent may be given subject to such terms and conditions as the person may reasonably impose but shall not be unreasonably withheld or delayed.
(3)The authorised undertaker shall not make any opening into any public sewer or drain except in accordance with plans approved by, and under the superintendence (if provided) of, the person to whom the sewer or drain belongs, but such approval shall not be unreasonably withheld or delayed.
(4)The authorised undertaker shall take such steps as are reasonably practicable to secure that any water discharged under the powers conferred by this section is as free as may be practicable from gravel, soil or other solid substance or oil or matter in suspension.
(5)Any difference under this section arising between the authorised undertaker and the owner of an artificial watercourse or a public sewer or drain shall, unless the parties otherwise agree, be determined by arbitration.
(6)Nothing in this section shall affect the operation of Part IV of the 1991 Act or the Water Environment (Controlled Activities) (Scotland) Regulations 2005 (SSI 2005/348).
(7)In this section—
“public sewer or drain” means a sewer or drain which belongs to Scottish Water, a private provider who has made an agreement with Scottish Water under section 1(2)(b) of the Sewerage (Scotland) Act 1968 (c. 47) (duty of local authority to provide sewerage for their area) or a roads authority; and
“watercourse” includes all rivers, streams, ditches, drains, cuts, culverts, dykes, sluices, sewers and passages through which water flows except a public sewer or drain.
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys