68Appointment by SEPA: engineers’ reports, certificates, recommendations etc.
Where SEPA makes a relevant appointment under section 67, the following are to be given to SEPA (instead of being given to the reservoir manager) and copied to the reservoir manager not later than 28 days after being given to SEPA—
(a)where the relevant appointment is that of a construction engineer, any safety report, safety measure certificate, preliminary certificate, construction certificate or final certificate by the construction engineer,
(b)where the relevant appointment is that of an inspecting engineer, any inspection report, interim inspection compliance certificate or inspection compliance certificate by the inspecting engineer,
(c)where the relevant appointment is that of a supervising engineer, any notice under section 50(2)(a) or (g), recommendation under section 50(3) or statement under section 50(8).