xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

TITLE IIU.K.RULES ON PUBLIC CONTRACTS

CHAPTER VU.K.Procedures

Article 28U.K.Use of open, restricted and negotiated procedures and of competitive dialogue

In awarding their public contracts, contracting authorities shall apply the national procedures adjusted for the purposes of this Directive.

They shall award these public contracts by applying the open or restricted procedure. In the specific circumstances expressly provided for in Article 29, contracting authorities may award their public contracts by means of the competitive dialogue. In the specific cases and circumstances referred to expressly in Articles 30 and 31, they may apply a negotiated procedure, with or without publication of the contract notice.

Article 29U.K.Competitive dialogue

1.In the case of particularly complex contracts, Member States may provide that where contracting authorities consider that the use of the open or restricted procedure will not allow the award of the contract, the latter may make use of the competitive dialogue in accordance with this Article.

A public contract shall be awarded on the sole basis of the award criterion for the most economically advantageous tender.

2.Contracting authorities shall publish a contract notice setting out their needs and requirements, which they shall define in that notice and/or in a descriptive document.

3.Contracting authorities shall open, with the candidates selected in accordance with the relevant provisions of Articles 44 to 52, a dialogue the aim of which shall be to identify and define the means best suited to satisfying their needs. They may discuss all aspects of the contract with the chosen candidates during this dialogue.

During the dialogue, contracting authorities shall ensure equality of treatment among all tenderers. In particular, they shall not provide information in a discriminatory manner which may give some tenderers an advantage over others.

Contracting authorities may not reveal to the other participants solutions proposed or other confidential information communicated by a candidate participating in the dialogue without his/her agreement.

4.Contracting authorities may provide for the procedure to take place in successive stages in order to reduce the number of solutions to be discussed during the dialogue stage by applying the award criteria in the contract notice or the descriptive document. The contract notice or the descriptive document shall indicate that recourse may be had to this option.

5.The contracting authority shall continue such dialogue until it can identify the solution or solutions, if necessary after comparing them, which are capable of meeting its needs.

6.Having declared that the dialogue is concluded and having so informed the participants, contracting authorities shall ask them to submit their final tenders on the basis of the solution or solutions presented and specified during the dialogue. These tenders shall contain all the elements required and necessary for the performance of the project.

These tenders may be clarified, specified and fine-tuned at the request of the contracting authority. However, such clarification, specification, fine-tuning or additional information may not involve changes to the basic features of the tender or the call for tender, variations in which are likely to distort competition or have a discriminatory effect.

7.Contracting authorities shall assess the tenders received on the basis of the award criteria laid down in the contract notice or the descriptive document and shall choose the most economically advantageous tender in accordance with Article 53.

At the request of the contracting authority, the tenderer identified as having submitted the most economically advantageous tender may be asked to clarify aspects of the tender or confirm commitments contained in the tender provided this does not have the effect of modifying substantial aspects of the tender or of the call for tender and does not risk distorting competition or causing discrimination.

8.The contracting authorities may specify prices or payments to the participants in the dialogue.

Article 30U.K.Cases justifying use of the negotiated procedure with prior publication of a contract notice

1.Contracting authorities may award their public contracts by negotiated procedure, after publication of a contract notice, in the following cases:

(a)in the event of irregular tenders or the submission of tenders which are unacceptable under national provisions compatible with Articles 4, 24, 25, 27 and Chapter VII, in response to an open or restricted procedure or a competitive dialogue insofar as the original terms of the contract are not substantially altered.

Contracting authorities need not publish a contract notice where they include in the negotiated procedure all of, and only, the tenderers which satisfy the criteria of Articles 45 to 52 and which, during the prior open or restricted procedure or competitive dialogue, have submitted tenders in accordance with the formal requirements of the tendering procedure;

(b)in exceptional cases, when the nature of the works, supplies, or services or the risks attaching thereto do not permit prior overall pricing;

(c)in the case of services, inter alia services within category 6 of Annex II A, and intellectual services such as services involving the design of works, insofar as the nature of the services to be provided is such that contract specifications cannot be established with sufficient precision to permit the award of the contract by selection of the best tender according to the rules governing open or restricted procedures;

(d)in respect of public works contracts, for works which are performed solely for purposes of research, testing or development and not with the aim of ensuring profitability or recovering research and development costs.

2.In the cases referred to in paragraph 1, contracting authorities shall negotiate with tenderers the tenders submitted by them in order to adapt them to the requirements which they have set in the contract notice, the specifications and additional documents, if any, and to seek out the best tender in accordance with Article 53(1).

3.During the negotiations, contracting authorities shall ensure the equal treatment of all tenderers. In particular, they shall not provide information in a discriminatory manner which may give some tenderers an advantage over others.

4.Contracting authorities may provide for the negotiated procedure to take place in successive stages in order to reduce the number of tenders to be negotiated by applying the award criteria in the contract notice or the specifications. The contract notice or the specifications shall indicate whether recourse has been had to this option.

Article 31U.K.Cases justifying use of the negotiated procedure without publication of a contract notice

Contracting authorities may award public contracts by a negotiated procedure without prior publication of a contract notice in the following cases:

(1)

for public works contracts, public supply contracts and public service contracts:

(a)

when no tenders or no suitable tenders or no applications have been submitted in response to an open procedure or a restricted procedure, provided that the initial conditions of contract are not substantially altered and on condition that a report is sent to the Commission if it so requests;

(b)

when, for technical or artistic reasons, or for reasons connected with the protection of exclusive rights, the contract may be awarded only to a particular economic operator;

(c)

insofar as is strictly necessary when, for reasons of extreme urgency brought about by events unforeseeable by the contracting authorities in question, the time limit for the open, restricted or negotiated procedures with publication of a contract notice as referred to in Article 30 cannot be complied with. The circumstances invoked to justify extreme urgency must not in any event be attributable to the contracting authority;

(2)

for public supply contracts:

(a)

when the products involved are manufactured purely for the purpose of research, experimentation, study or development; this provision does not extend to quantity production to establish commercial viability or to recover research and development costs;

(b)

for additional deliveries by the original supplier which are intended either as a partial replacement of normal supplies or installations or as the extension of existing supplies or installations where a change of supplier would oblige the contracting authority to acquire material having different technical characteristics which would result in incompatibility or disproportionate technical difficulties in operation and maintenance; the length of such contracts as well as that of recurrent contracts may not, as a general rule, exceed three years;

(c)

for supplies quoted and purchased on a commodity market;

(d)

for the purchase of supplies on particularly advantageous terms, from either a supplier which is definitively winding up its business activities, or the receivers or liquidators of a bankruptcy, an arrangement with creditors, or a similar procedure under national laws or regulations;

(3)

for public service contracts, when the contract concerned follows a design contest and must, under the applicable rules, be awarded to the successful candidate or to one of the successful candidates, in the latter case, all successful candidates must be invited to participate in the negotiations;

(4)

for public works contracts and public service contracts:

(a)

for additional works or services not included in the project initially considered or in the original contract but which have, through unforeseen circumstances, become necessary for the performance of the works or services described therein, on condition that the award is made to the economic operator performing such works or services:

  • when such additional works or services cannot be technically or economically separated from the original contract without major inconvenience to the contracting authorities,

    or

  • when such works or services, although separable from the performance of the original contract, are strictly necessary for its completion.

However, the aggregate value of contracts awarded for additional works or services may not exceed 50 % of the amount of the original contract;

(b)

for new works or services consisting in the repetition of similar works or services entrusted to the economic operator to whom the same contracting authorities awarded an original contract, provided that such works or services are in conformity with a basic project for which the original contract was awarded according to the open or restricted procedure.

As soon as the first project is put up for tender, the possible use of this procedure shall be disclosed and the total estimated cost of subsequent works or services shall be taken into consideration by the contracting authorities when they apply the provisions of Article 7.

This procedure may be used only during the three years following the conclusion of the original contract.

Article 32U.K.Framework agreements

1.Member States may provide that contracting authorities may conclude framework agreements.

2.For the purpose of concluding a framework agreement, contracting authorities shall follow the rules of procedure referred to in this Directive for all phases up to the award of contracts based on that framework agreement. The parties to the framework agreement shall be chosen by applying the award criteria set in accordance with Article 53.

Contracts based on a framework agreement shall be awarded in accordance with the procedures laid down in paragraphs 3 and 4. Those procedures may be applied only between the contracting authorities and the economic operators originally party to the framework agreement.

When awarding contracts based on a framework agreement, the parties may under no circumstances make substantial amendments to the terms laid down in that framework agreement, in particular in the case referred to in paragraph 3.

The term of a framework agreement may not exceed four years, save in exceptional cases duly justified, in particular by the subject of the framework agreement.

Contracting authorities may not use framework agreements improperly or in such a way as to prevent, restrict or distort competition.

3.Where a framework agreement is concluded with a single economic operator, contracts based on that agreement shall be awarded within the limits of the terms laid down in the framework agreement.

For the award of those contracts, contracting authorities may consult the operator party to the framework agreement in writing, requesting it to supplement its tender as necessary.

4.Where a framework agreement is concluded with several economic operators, the latter must be at least three in number, insofar as there is a sufficient number of economic operators to satisfy the selection criteria and/or of admissible tenders which meet the award criteria.

Contracts based on framework agreements concluded with several economic operators may be awarded either:

Article 33U.K.Dynamic purchasing systems

1.Member States may provide that contracting authorities may use dynamic purchasing systems.

2.In order to set up a dynamic purchasing system, contracting authorities shall follow the rules of the open procedure in all its phases up to the award of the contracts to be concluded under this system. All the tenderers satisfying the selection criteria and having submitted an indicative tender which complies with the specification and any possible additional documents shall be admitted to the system; indicative tenders may be improved at any time provided that they continue to comply with the specification. With a view to setting up the system and to the award of contracts under that system, contracting authorities shall use solely electronic means in accordance with Article 42(2) to (5).

3.For the purposes of setting up the dynamic purchasing system, contracting authorities shall:

(a)publish a contract notice making it clear that a dynamic purchasing system is involved;

(b)indicate in the specification, amongst other matters, the nature of the purchases envisaged under that system, as well as all the necessary information concerning the purchasing system, the electronic equipment used and the technical connection arrangements and specifications;

(c)offer by electronic means, on publication of the notice and up to the expiry of the system, unrestricted, direct and full access to the specification and to any additional documents and shall indicate in the notice the internet address at which such documents may be consulted.

4.Contracting authorities shall give any economic operator, throughout the entire period of the dynamic purchasing system, the possibility of submitting an indicative tender and of being admitted to the system under the conditions referred to in paragraph 2. They shall complete evaluation within a maximum of 15 days from the date of submission of the indicative tender. However, they may extend the evaluation period provided that no invitation to tender is issued in the meantime.

The contracting authority shall inform the tenderer referred to in the first subparagraph at the earliest possible opportunity of its admittance to the dynamic purchasing system or of the rejection of its indicative tender.

5.Each specific contract must be the subject of an invitation to tender. Before issuing the invitation to tender, contracting authorities shall publish a simplified contract notice inviting all interested economic operators to submit an indicative tender, in accordance with paragraph 4, within a time limit that may not be less than 15 days from the date on which the simplified notice was sent. Contracting authorities may not proceed with tendering until they have completed evaluation of all the indicative tenders received by that deadline.

6.Contracting authorities shall invite all tenderers admitted to the system to submit a tender for each specific contract to be awarded under the system. To that end they shall set a time limit for the submission of tenders.

They shall award the contract to the tenderer which submitted the best tender on the basis of the award criteria set out in the contract notice for the establishment of the dynamic purchasing system. Those criteria may, if appropriate, be formulated more precisely in the invitation referred to in the first subparagraph.

7.A dynamic purchasing system may not last for more than four years, except in duly justified exceptional cases.

Contracting authorities may not resort to this system to prevent, restrict or distort competition.

No charges may be billed to the interested economic operators or to parties to the system.

Article 34U.K.Public works contracts: particular rules on subsidised housing schemes

In the case of public contracts relating to the design and construction of a subsidised housing scheme the size and complexity of which, and the estimated duration of the work involved require that planning be based from the outset on close collaboration within a team comprising representatives of the contracting authorities, experts and the contractor to be responsible for carrying out the works, a special award procedure may be adopted for selecting the contractor most suitable for integration into the team.

In particular, contracting authorities shall include in the contract notice as accurate as possible a description of the works to be carried out so as to enable interested contractors to form a valid idea of the project. Furthermore, contracting authorities shall, in accordance with the qualitative selection criteria referred to in Articles 45 to 52, set out in such a contract notice the personal, technical, economic and financial conditions to be fulfilled by candidates.

Where such a procedure is adopted, contracting authorities shall apply Articles 2, 35, 36, 38, 39, 41, 42, 43 and 45 to 52.