Chwilio Deddfwriaeth

Directive 2004/18/EC of the European Parliament and of the Council (repealed)Dangos y teitl llawn

Directive 2004/18/EC of the European Parliament and of the Council of 31 March 2004 on the coordination of procedures for the award of public works contracts, public supply contracts and public service contracts (repealed)

 Help about what version

Pa Fersiwn

 Help about opening options

Dewisiadau Agor

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

Mae hon yn eitem o ddeddfwriaeth sy’n deillio o’r UE

Mae unrhyw newidiadau sydd wedi cael eu gwneud yn barod gan y tîm yn ymddangos yn y cynnwys a chyfeirir atynt gydag anodiadau.Ar ôl y diwrnod ymadael bydd tair fersiwn o’r ddeddfwriaeth yma i’w gwirio at ddibenion gwahanol. Y fersiwn legislation.gov.uk yw’r fersiwn sy’n weithredol yn y Deyrnas Unedig. Y Fersiwn UE sydd ar EUR-lex ar hyn o bryd yw’r fersiwn sy’n weithredol yn yr UE h.y. efallai y bydd arnoch angen y fersiwn hon os byddwch yn gweithredu busnes yn yr UE. EUR-Lex Y fersiwn yn yr archif ar y we yw’r fersiwn swyddogol o’r ddeddfwriaeth fel yr oedd ar y diwrnod ymadael cyn cael ei chyhoeddi ar legislation.gov.uk ac unrhyw newidiadau ac effeithiau a weithredwyd yn y Deyrnas Unedig wedyn. Mae’r archif ar y we hefyd yn cynnwys cyfraith achos a ffurfiau mewn ieithoedd eraill o EUR-Lex. The EU Exit Web Archive legislation_originated_from_EU_p3

Status:

Dyma’r fersiwn wreiddiol (fel y’i gwnaed yn wreiddiol).

CHAPTER IRules governing public works concessions

Article 56Scope

This Chapter shall apply to all public works concession contracts concluded by the contracting authorities where the value of the contracts is equal to or greater than EUR 6 242 000.

The value shall be calculated in accordance with the rules applicable to public works contracts defined in Article 9.

Article 57Exclusions from the scope

This Title shall not apply to public works concessions which are awarded:

(a)

in the cases referred to in Articles 13, 14 and 15 of this Directive in respect of public works contracts;

(b)

by contracting authorities exercising one or more of the activities referred to in Articles 3 to 7 of Directive 2004/17/EC where those concessions are awarded for carrying out those activities.

However, this Directive shall continue to apply to public works concessions awarded by contracting authorities carrying out one or more of the activities referred to in Article 6 of Directive 2004/17/EC and awarded for those activities, insofar as the Member State concerned takes advantage of the option referred to in the second subparagraph of Article 71 thereof to defer its application.

Article 58Publication of the notice concerning public works concessions

1.Contracting authorities which wish to award a public works concession contract shall make known their intention by means of a notice.

2.Notices of public works concessions shall contain the information referred to in Annex VII C and, where appropriate, any other information deemed useful by the contracting authority, in accordance with the standard forms adopted by the Commission pursuant to the procedure in Article 77(2).

3.Notices shall be published in accordance with Article 36(2) to (8).

4.Article 37 on the publication of notices shall also apply to public works concessions.

Article 59Time limit

When contracting authorities resort to a public works concession, the time limit for the presentation of applications for the concession shall be not less than 52 days from the date of dispatch of the notice, except where Article 38(5) applies.

Article 38(7) shall apply.

Article 60Subcontracting

The contracting authority may either:

(a)

require the concessionaire to award contracts representing a minimum of 30 % of the total value of the work for which the concession contract is to be awarded, to third parties, at the same time providing the option for candidates to increase this percentage, this minimum percentage being specified in the concession contract, or

(b)

request the candidates for concession contracts to specify in their tenders the percentage, if any, of the total value of the work for which the concession contract is to be awarded which they intend to assign to third parties.

Article 61Awarding of additional works to the concessionaire

This Directive shall not apply to additional works not included in the concession project initially considered or in the initial contract but which have, through unforeseen circumstances, become necessary for the performance of the work described therein, which the contracting authority has awarded to the concessionaire, on condition that the award is made to the economic operator performing such work:

  • when such additional works cannot be technically or economically separated from the initial contract without major inconvenience to the contracting authorities, or

  • when such works, although separable from the performance of the initial contract, are strictly necessary for its completion.

However, the aggregate value of contracts awarded for additional works may not exceed 50 % of the amount of the original works concession contract.

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i mabwysiadwyd gan yr UE): Mae'r wreiddiol version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel adopted version that was used for the EU Official Journal
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel adopted fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill