Article 53U.K.Infrastructure capacity for maintenance work
1.Requests for infrastructure capacity to enable maintenance work to be performed shall be submitted during the scheduling process.
2.Adequate account shall be taken by the infrastructure manager of the effect of infrastructure capacity reserved for scheduled track maintenance work on applicants.
3.The infrastructure manager shall inform, as soon as possible, interested parties about the unavailability of infrastructure capacity due to unscheduled maintenance work.