- Y Diweddaraf sydd Ar Gael (Diwygiedig)
- Pwynt Penodol mewn Amser (26/02/2014)
- Gwreiddiol (Fel y’i mabwysiadwyd gan yr UE)
Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC (Text with EEA relevance)
Pan adawodd y DU yr UE, cyhoeddodd legislation.gov.uk ddeddfwriaeth yr UE a gyhoeddwyd gan yr UE hyd at ddiwrnod cwblhau’r cyfnod gweithredu (31 Rhagfyr 2020 11.00 p.m.). Ar legislation.gov.uk, mae'r eitemau hyn o ddeddfwriaeth yn cael eu diweddaru'n gyson ag unrhyw ddiwygiadau a wnaed gan y DU ers hynny.
Mae legislation.gov.uk yn cyhoeddi fersiwn y DU. Mae EUR-Lex yn cyhoeddi fersiwn yr UE. Mae Archif Gwe Ymadael â’r UE yn rhoi cipolwg ar fersiwn EUR-Lex o ddiwrnod cwblhau’r cyfnod gweithredu (31 Rhagfyr 2020 11.00 p.m.).
Cyhoeddir Cyfarwyddebau’r UE ar y wefan hon i gynorthwyo croesgyfeirio o ddeddfwriaeth y DU. Ers diwrnod cwblhau’r cyfnod gweithredu (31 Rhagfyr 2020 11.00 p.m.) nid oes unrhyw ddiwygiadau wedi'u cymhwyso i'r fersiwn hon.
Before launching a procurement procedure, contracting authorities may conduct market consultations with a view to preparing the procurement and informing economic operators of their procurement plans and requirements.
For this purpose, contracting authorities may for example seek or accept advice from independent experts or authorities or from market participants. That advice may be used in the planning and conduct of the procurement procedure, provided that such advice does not have the effect of distorting competition and does not result in a violation of the principles of non-discrimination and transparency.
Where a candidate or tenderer or an undertaking related to a candidate or tenderer has advised the contracting authority, whether in the context of Article 40 or not, or has otherwise been involved in the preparation of the procurement procedure, the contracting authority shall take appropriate measures to ensure that competition is not distorted by the participation of that candidate or tenderer.
Such measures shall include the communication to the other candidates and tenderers of relevant information exchanged in the context of or resulting from the involvement of the candidate or tenderer in the preparation of the procurement procedure and the fixing of adequate time limits for the receipt of tenders. The candidate or tenderer concerned shall only be excluded from the procedure where there are no other means to ensure compliance with the duty to observe the principle of equal treatment.
Prior to any such exclusion, candidates or tenderers shall be given the opportunity to prove that their involvement in preparing the procurement procedure is not capable of distorting competition. The measures taken shall be documented in the individual report required by Article 84.
1.The technical specifications as defined in point 1 of Annex VII shall be set out in the procurement documents. The technical specification shall lay down the characteristics required of a works, service or supply.
Those characteristics may also refer to the specific process or method of production or provision of the requested works, supplies or services or to a specific process for another stage of its life cycle even where such factors do not form part of their material substance provided that they are linked to the subject-matter of the contract and proportionate to its value and its objectives.
The technical specifications may also specify whether the transfer of intellectual property rights will be required.
For all procurement which is intended for use by natural persons, whether general public or staff of the contracting authority, the technical specifications shall, except in duly justified cases, be drawn up so as to take into account accessibility criteria for persons with disabilities or design for all users.
Where mandatory accessibility requirements are adopted by a legal act of the Union, technical specifications shall, as far as accessibility criteria for persons with disabilities or design for all users are concerned, be defined by reference thereto.
2.Technical specifications shall afford equal access of economic operators to the procurement procedure and shall not have the effect of creating unjustified obstacles to the opening up of public procurement to competition.
3.Without prejudice to mandatory national technical rules, to the extent that they are compatible with Union law, the technical specifications shall be formulated in one of the following ways:
(a)in terms of performance or functional requirements, including environmental characteristics, provided that the parameters are sufficiently precise to allow tenderers to determine the subject-matter of the contract and to allow contracting authorities to award the contract;
(b)by reference to technical specifications and, in order of preference, to national standards transposing European standards, European Technical Assessments, common technical specifications, international standards, other technical reference systems established by the European standardisation bodies or - when any of those do not exist - national standards, national technical approvals or national technical specifications relating to the design, calculation and execution of the works and use of the supplies; each reference shall be accompanied by the words ‘or equivalent’;
(c)in terms of performance or functional requirements as referred to in point (a), with reference to the technical specifications referred to in point (b) as a means of presuming conformity with such performance or functional requirements;
(d)by reference to the technical specifications referred to in point (b) for certain characteristics, and by reference to the performance or functional requirements referred to in point (a) for other characteristics.
4.Unless justified by the subject-matter of the contract, technical specifications shall not refer to a specific make or source, or a particular process which characterises the products or services provided by a specific economic operator, or to trade marks, patents, types or a specific origin or production with the effect of favouring or eliminating certain undertakings or certain products. Such reference shall be permitted on an exceptional basis, where a sufficiently precise and intelligible description of the subject-matter of the contract pursuant to paragraph 3 is not possible. Such reference shall be accompanied by the words ‘or equivalent’.
5.Where a contracting authority uses the option of referring to the technical specifications referred to in point (b) of paragraph 3, it shall not reject a tender on the grounds that the works, supplies or services tendered for do not comply with the technical specifications to which it has referred, once the tenderer proves in its tender by any appropriate means, including the means of proof referred to in Article 44, that the solutions proposed satisfy in an equivalent manner the requirements defined by the technical specifications.
6.Where a contracting authority uses the option laid down in point (a) of paragraph 3 to formulate technical specifications in terms of performance or functional requirements, it shall not reject a tender for works, supplies or services which comply with a national standard transposing a European standard, a European technical approval, a common technical specification, an international standard or a technical reference system established by a European standardisation body, where those specifications address the performance or functional requirements which it has laid down.
In its tender, the tenderer shall prove by any appropriate means, including those referred to in Article 44, that the work, supply or service in compliance with the standard meets the performance or functional requirements of the contracting authority.
1.Where contracting authorities intend to purchase works, supplies or services with specific environmental, social or other characteristics they may, in the technical specifications, the award criteria or the contract performance conditions, require a specific label as means of proof that the works, services or supplies correspond to the required characteristics, provided that all of the following conditions are fulfilled:
(a)the label requirements only concern criteria which are linked to the subject-matter of the contract and are appropriate to define characteristics of the works, supplies or services that are the subject-matter of the contract;
(b)the label requirements are based on objectively verifiable and non-discriminatory criteria;
(c)the labels are established in an open and transparent procedure in which all relevant stakeholders, including government bodies, consumers, social partners, manufacturers, distributors and non-governmental organisations, may participate;
(d)the labels are accessible to all interested parties;
(e)the label requirements are set by a third party over which the economic operator applying for the label cannot exercise a decisive influence.
Where contracting authorities do not require the works, supplies or services to meet all of the label requirements, they shall indicate which label requirements are referred to.
Contracting authorities requiring a specific label shall accept all labels that confirm that the works, supplies or services meet equivalent label requirements.
Where an economic operator had demonstrably no possibility of obtaining the specific label indicated by the contracting authority or an equivalent label within the relevant time limits for reasons that are not attributable to that economic operator, the contracting authority shall accept other appropriate means of proof, which may include a technical dossier from the manufacturer, provided that the economic operator concerned proves that the works, supplies or services to be provided by it fulfil the requirements of the specific label or the specific requirements indicated by the contracting authority.
2.Where a label fulfils the conditions provided in points (b), (c), (d) and (e) of paragraph 1 but also sets out requirements not linked to the subject-matter of the contract, contracting authorities shall not require the label as such but may define the technical specification by reference to those of the detailed specifications of that label, or, where necessary, parts thereof, that are linked to the subject-matter of the contract and are appropriate to define characteristics of this subject-matter.
1.Contracting authorities may require that economic operators provide a test report from a conformity assessment body or a certificate issued by such a body as means of proof of conformity with requirements or criteria set out in the technical specifications, the award criteria or the contract performance conditions.
Where contracting authorities require the submission of certificates drawn up by a specific conformity assessment body, certificates from equivalent other conformity assessment bodies shall also be accepted by the contracting authorities.
For the purpose of this paragraph, a conformity assessment body shall be a body that performs conformity assessment activities including calibration, testing, certification and inspection accredited in accordance with Regulation (EC) No 765/2008 of the European Parliament and of the Council(1).
2.Contracting authorities shall accept other appropriate means of proof than those referred to in paragraph 1, such as a technical dossier of the manufacturer where the economic operator concerned had no access to the certificates or test reports referred to in paragraph 1, or no possibility of obtaining them within the relevant time limits, provided that the lack of access is not attributable to the economic operator concerned and provided that the economic operator concerned thereby proves that the works, supplies or services provided by it meet the requirements or criteria set out in the technical specifications, the award criteria or the contract performance conditions.
3.Member States shall make available to other Member States, upon request, any information related to the evidence and documents submitted in accordance with Article 42(6), Article 43 and paragraphs 1 and 2 of this Article. The competent authorities of the Member State of establishment of the economic operator shall provide this information in accordance with Article 86.
1.Contracting authorities may authorise or require tenderers to submit variants. They shall indicate in the contract notice or, where a prior information notice is used as a means of calling for competition, in the invitation to confirm interest whether or not they authorise or require variants. Variants shall not be authorised without such indication. Variants shall be linked to the subject-matter of the contract.
2.Contracting authorities authorising or requiring variants shall state in the procurement documents the minimum requirements to be met by the variants and any specific requirements for their presentation, in particular whether variants may be submitted only where a tender, which is not a variant, has also been submitted. They shall also ensure that the chosen award criteria can be applied to variants meeting those minimum requirements as well as to conforming tenders which are not variants.
3.Only variants meeting the minimum requirements laid down by the contracting authorities shall be taken into consideration.
In procedures for awarding public supply or service contracts, contracting authorities that have authorised or required variants shall not reject a variant on the sole ground that it would, where successful, lead to either a service contract rather than a public supply contract or a supply contract rather than a public service contract.
1.Contracting authorities may decide to award a contract in the form of separate lots and may determine the size and subject-matter of such lots.
Contracting authorities shall, except in respect of contracts whose division has been made mandatory pursuant to paragraph 4 of this Article, provide an indication of the main reasons for their decision not to subdivide into lots, which shall be included in the procurement documents or the individual report referred to in Article 84.
2.Contracting authorities shall indicate, in the contract notice or in the invitation to confirm interest, whether tenders may be submitted for one, for several or for all of the lots.
Contracting authorities may, even where tenders may be submitted for several or all lots, limit the number of lots that may be awarded to one tenderer, provided that the maximum number of lots per tenderer is stated in the contract notice or in the invitation to confirm interest. Contracting authorities shall indicate in the procurement documents the objective and non-discriminatory criteria or rules they intend to apply for determining which lots will be awarded where the application of the award criteria would result in one tenderer being awarded more lots than the maximum number.
3.Member States may provide that, where more than one lot may be awarded to the same tenderer, contracting authorities may award contracts combining several or all lots where they have specified in the contract notice or in the invitation to confirm interest that they reserve the possibility of doing so and indicate the lots or groups of lots that may be combined.
4.Member States may implement the second subparagraph of paragraph 1 by rendering it obligatory to award contracts in the form of separate lots under conditions to be specified in accordance with their national law and having regard for Union law. In such circumstances the first subparagraph of paragraph 2 and, where appropriate, paragraph 3 shall apply.
1.When fixing the time limits for the receipt of tenders and requests to participate, contracting authorities shall take account of the complexity of the contract and the time required for drawing up tenders, without prejudice to the minimum time limits set out in Articles 27 to 31.
2.Where tenders can be made only after a visit to the site or after on-the-spot inspection of the documents supporting the procurement documents, the time limits for the receipt of tenders, which shall be longer than the minimum time limits set out in Articles 27 to 31, shall be fixed so that all economic operators concerned may be aware of all the information needed to produce tenders.
3.Contracting authorities shall extend the time limits for the receipt of tenders so that all economic operators concerned may be aware of all the information needed to produce tenders in the following cases:
(a)where, for whatever reason, additional information, although requested by the economic operator in good time, is not supplied at the latest six days before the time limit fixed for the receipt of tenders. In the event of an accelerated procedure as referred to in Article 27(3) and Article 28(6), that period shall be four days;
(b)where significant changes are made to the procurement documents.
The length of the extension shall be proportionate to the importance of the information or change.
Where the additional information has either not been requested in good time or its importance with a view to preparing responsive tenders is insignificant, contracting authorities shall not be required to extend the time limits.
1.Contracting authorities may make known their intentions of planned procurements through the publication of a prior information notice. Those notices shall contain the information set out in Annex V part B section I. They shall be published either by the Publications Office of the European Union or by the contracting authorities on their buyer profiles in accordance with point 2(b) of Annex VIII. Where the prior information notice is published by the contracting authorities on their buyer profile, they shall send a notice of the publication on their buyer profile to the Publications Office of the European Union in accordance with Annex VIII. Those notices shall contain the information set out in Annex V part A.
2.For restricted procedures and competitive procedures with negotiation, sub-central contracting authorities may use a prior information notice as a call for competition pursuant to Article 26(5), provided that the notice fulfils all of the following conditions:
(a)it refers specifically to the supplies, works or services that will be the subject of the contract to be awarded;
(b)it indicates that the contract will be awarded by restricted procedure or competitive procedure with negotiation without further publication of a call for competition and invites interested economic operators to express their interest;
(c)it contains, in addition to the information set out in Annex V part B section I, the information set out in Annex V part B section II;
(d)it has been sent for publication between 35 days and 12 months prior to the date on which the invitation referred to in Article 54(1) is sent.
Such notices shall not be published on a buyer profile. However, the additional publication at national level pursuant to Article 52, if any, may be made on a buyer profile.
The period covered by the prior information notice shall be a maximum of 12 months from the date the notice is transmitted for publication. However, in the case of public contracts for social and other specific services, the prior information notice referred to in point (b) of Article 75(1) may cover a period which is longer than 12 months.
Contract notices shall be used as a means of calling for competition in respect of all procedures, without prejudice to the second subparagraph of Article 26(5) and Article 32. Contract notices shall contain the information set out in Annex V part C and shall be published in accordance with Article 51.
1.Not later than 30 days after the conclusion of a contract or of a framework agreement, following the decision to award or conclude it, contracting authorities shall send a contract award notice on the results of the procurement procedure.
Such notices shall contain the information set out in Annex V part D and shall be published in accordance with Article 51.
2.Where the call for competition for the contract concerned has been made in the form of a prior information notice and the contracting authority has decided that it will not award further contracts during the period covered by the prior information notice, the contract award notice shall contain a specific indication to that effect.
In the case of framework agreements concluded in accordance with Article 33, contracting authorities shall not be bound to send a notice of the results of the procurement procedure for each contract based on that agreement. Member States may provide that contracting authorities shall group notices of the results of the procurement procedure for contracts based on the framework agreement on a quarterly basis. In that case, contracting authorities shall send the grouped notices within 30 days of the end of each quarter.
3.Contracting authorities shall send a contract award notice within 30 days after the award of each contract based on a dynamic purchasing system. They may, however, group such notices on a quarterly basis. In that case, they shall send the grouped notices within 30 days of the end of each quarter.
4.Certain information on the contract award or the conclusion of the framework agreement may be withheld from publication where its release would impede law enforcement or otherwise be contrary to the public interest, would harm the legitimate commercial interests of a particular economic operator, public or private, or might prejudice fair competition between economic operators.
1.Notices referred to in Articles 48, 49 and 50 shall include the information set out in Annex V in the format of standard forms, including standard forms for corrigenda.
The Commission shall establish those standard forms by means of implementing acts. Those implementing acts shall be adopted in accordance with the advisory procedure referred to in Article 89(2).
2.Notices referred to in Articles 48, 49 and 50 shall be drawn up, transmitted by electronic means to the Publications Office of the European Union and published in accordance with Annex VIII. Notices shall be published not later than five days after they are sent. The costs of publication of the notices by the Publications Office of the European Union shall be borne by the Union.
3.Notices referred to in Articles 48, 49 and 50 shall be published in full in the official language(s) of the institutions of the Union chosen by the contracting authority. That language version or those language versions shall constitute the sole authentic text(s). A summary of the important elements of each notice shall be published in the other official languages of the institutions of the Union.
4.The Publications Office of the European Union shall ensure that the full text and the summary of prior information notices referred to in Article 48(2) and calls for competition setting up a dynamic purchasing system, as referred to in point (a) of Article 34(4) continue to be published:
(a)in the case of prior information notices, for 12 months or until receipt of a contract award notice as provided for in Article 50 indicating that no further contracts will be awarded during the 12-month period covered by the call for competition. However, in the case of public contracts for social and other specific services, the prior information notice referred to in point (b) of Article 75(1) shall continue to be published until the end of its originally indicated period of validity or until receipt of a contract award notice as provided for in Article 50 indicating that no further contracts will be awarded during the period covered by the call for competition;
(b)in the case of calls for competition setting up a dynamic purchasing system, for the period of validity of the dynamic purchasing system.
5.Contracting authorities shall be able to supply proof of the dates on which notices are dispatched.
The Publications Office of the European Union shall give the contracting authority confirmation of the receipt of the notice and of the publication of the information sent, indicating the date of that publication. Such confirmation shall constitute proof of publication.
6.Contracting authorities may publish notices for public contracts that are not subject to the publication requirement laid down in this Directive provided that those notices are sent to the Publications Office of the European Union by electronic means in accordance with the format and procedures for transmission indicated in Annex VIII.
1.Notices referred to in Articles 48, 49 and 50 and the information contained therein shall not be published at national level before the publication pursuant to Article 51. However, publication may in any event take place at the national level where contracting authorities have not been notified of the publication within 48 hours after confirmation of the receipt of the notice in accordance with Article 51.
2.Notices published at national level shall not contain information other than that contained in the notices dispatched to the Publications Office of the European Union or published on a buyer profile, but shall indicate the date of dispatch of the notice to the Publications Office of the European Union or its publication on the buyer profile.
3.Prior information notices shall not be published on a buyer profile before the dispatch to the Publications Office of the European Union of the notice of their publication in that form. They shall indicate the date of that dispatch.
1.Contracting authorities shall by electronic means offer unrestricted and full direct access free of charge to the procurement documents from the date of publication of a notice in accordance with Article 51 or the date on which an invitation to confirm interest was sent. The text of the notice or the invitation to confirm interest shall specify the internet address at which the procurement documents are accessible.
Where unrestricted and full direct access free of charge by electronic means to certain procurement documents cannot be offered for one of the reasons set out in the second subparagraph of Article 22(1), contracting authorities may indicate in the notice or the invitation to confirm interest that the procurement documents concerned will be transmitted by other means than electronic means in accordance with paragraph 2 of this Article. In such a case, the time limit for the submission of tenders shall be prolonged by five days, except in the cases of duly substantiated urgency referred to in Article 27(3), Article 28(6) and in the fourth subparagraph of Article 29(1).
Where unrestricted and full direct access free of charge by electronic means to certain procurement documents cannot be offered because contracting authorities intend to apply Article 21(2) of this Directive, they shall indicate in the notice or the invitation to confirm interest which measures aimed at protecting the confidential nature of the information they require and how access can be obtained to the documents concerned. In such case, the time limit for the submission of tenders shall be prolonged by five days, except in the cases of duly substantiated urgency referred to in Article 27(3), Article 28(6) and in the fourth subparagraph of Article 29(1).
2.Provided that it has been requested in good time, the contracting authorities shall supply to all tenderers taking part in the procurement procedure additional information relating to the specifications and any supporting documents not later than six days before the time limit fixed for the receipt of tenders. In the event of an accelerated procedure as referred to in Article 27(3) and Article 28(6), that period shall be four days.
1.In restricted procedures, competitive dialogue procedures, innovation partnerships and competitive procedures with negotiation, contracting authorities shall simultaneously and in writing invite the selected candidates to submit their tenders or, in the case of a competitive dialogue, to take part in the dialogue.
Where a prior information notice is used as a call for competition pursuant to Article 48(2), contracting authorities shall simultaneously and in writing invite the economic operators which have expressed their interest to confirm their continuing interest.
2.The invitations referred to in paragraph 1 of this Article shall include a reference to the electronic address on which the procurement documents have been made directly available by electronic means. The invitations shall be accompanied by the procurement documents, where those documents have not been the subject of unrestricted and full direct access, free of charge, for the reasons set out in the second or third subparagraph of Article 53(1) and have not already been made otherwise available. In addition, the invitations referred to in paragraph 1 of this Article shall include the information set out in Annex IX.
1.Contracting authorities shall as soon as possible inform each candidate and tenderer of decisions reached concerning the conclusion of a framework agreement, the award of the contract or admittance to a dynamic purchasing system, including the grounds for any decision not to conclude a framework agreement, not to award a contract for which there has been a call for competition, to recommence the procedure or not to implement a dynamic purchasing system.
2.On request from the candidate or tenderer concerned, the contracting authority shall as quickly as possible, and in any event within 15 days from receipt of a written request, inform:
(a)any unsuccessful candidate of the reasons for the rejection of its request to participate,
(b)any unsuccessful tenderer of the reasons for the rejection of its tender, including, for the cases referred to in Article 42(5) and (6), the reasons for its decision of non-equivalence or its decision that the works, supplies or services do not meet the performance or functional requirements,
(c)any tenderer that has made an admissible tender of the characteristics and relative advantages of the tender selected as well as the name of the successful tenderer or the parties to the framework agreement,
(d)any tenderer that has made an admissible tender of the conduct and progress of negotiations and dialogue with tenderers.
3.Contracting authorities may decide to withhold certain information referred to in paragraphs 1 and 2, regarding the contract award, the conclusion of framework agreements or admittance to a dynamic purchasing system, where the release of such information would impede law enforcement or would otherwise be contrary to the public interest, would prejudice the legitimate commercial interests of a particular economic operator, whether public or private, or might prejudice fair competition between economic operators.
1.Contracts shall be awarded on the basis of criteria laid down in accordance with Articles 67 to 69, provided that the contracting authority has verified in accordance with Articles 59 to 61 that all of the following conditions are fulfilled:
(a)the tender complies with the requirements, conditions and criteria set out in the contract notice or the invitation to confirm interest and in the procurement documents, taking into account, where applicable, Article 45;
(b)the tender comes from a tenderer that is not excluded in accordance with Article 57 and that meets the selection criteria set out by the contracting authority in accordance with Article 58 and, where applicable, the non-discriminatory rules and criteria referred to in Article 65.
Contracting authorities may decide not to award a contract to the tenderer submitting the most economically advantageous tender where they have established that the tender does not comply with the applicable obligations referred to in Article 18(2).
2.In open procedures, contracting authorities may decide to examine tenders before verifying the absence of grounds for exclusion and the fulfilment of the selection criteria in accordance with Articles 57 to 64. Where they make use of that possibility, they shall ensure that the verification of absence of grounds for exclusion and of fulfilment of the selection criteria is carried out in an impartial and transparent manner so that no contract is awarded to a tenderer that should have been excluded pursuant to Article 57 or that does not meet the selection criteria set out by the contracting authority.
Member States may exclude the use of the procedure in the first subparagraph for, or restrict it to, certain types of procurement or specific circumstances.
3.Where information or documentation to be submitted by economic operators is or appears to be incomplete or erroneous or where specific documents are missing, contracting authorities may, unless otherwise provided by the national law implementing this Directive, request the economic operators concerned to submit, supplement, clarify or complete the relevant information or documentation within an appropriate time limit, provided that such requests are made in full compliance with the principles of equal treatment and transparency.
4.The Commission shall be empowered to adopt delegated acts in accordance with Article 87 to amend the list in Annex X, where necessary, to add new international agreements that have been ratified by all Member States or where the existing international agreements referred to are no longer ratified by all Member States or they are otherwise changed, for instance in respect of their scope, content or denomination.
1.Contracting authorities shall exclude an economic operator from participation in a procurement procedure where they have established, by verifying in accordance with Articles 59, 60 and 61, or are otherwise aware that that economic operator has been the subject of a conviction by final judgment for one of the following reasons:
(a)participation in a criminal organisation, as defined in Article 2 of Council Framework Decision 2008/841/JHA(2);
(b)corruption, as defined in Article 3 of the Convention on the fight against corruption involving officials of the European Communities or officials of Member States of the European Union(3) and Article 2(1) of Council Framework Decision 2003/568/JHA(4) as well as corruption as defined in the national law of the contracting authority or the economic operator;
(c)fraud within the meaning of Article 1 of the Convention on the protection of the European Communities’ financial interests(5);
(d)terrorist offences or offences linked to terrorist activities, as defined in Articles 1 and 3 of Council Framework Decision 2002/475/JHA(6) respectively, or inciting or aiding or abetting or attempting to commit an offence, as referred to in Article 4 of that Framework Decision;
(e)money laundering or terrorist financing, as defined in Article 1 of Directive 2005/60/EC of the European Parliament and of the Council(7);
(f)child labour and other forms of trafficking in human beings as defined in Article 2 of Directive 2011/36/EU of the European Parliament and of the Council(8).
The obligation to exclude an economic operator shall also apply where the person convicted by final judgment is a member of the administrative, management or supervisory body of that economic operator or has powers of representation, decision or control therein.
2.An economic operator shall be excluded from participation in a procurement procedure where the contracting authority is aware that the economic operator is in breach of its obligations relating to the payment of taxes or social security contributions and where this has been established by a judicial or administrative decision having final and binding effect in accordance with the legal provisions of the country in which it is established or with those of the Member State of the contracting authority.
Furthermore, contracting authorities may exclude or may be required by Member States to exclude from participation in a procurement procedure an economic operator where the contracting authority can demonstrate by any appropriate means that the economic operator is in breach of its obligations relating to the payment of taxes or social security contributions.
This paragraph shall no longer apply when the economic operator has fulfilled its obligations by paying or entering into a binding arrangement with a view to paying the taxes or social security contributions due, including, where applicable, any interest accrued or fines.
3.Member States may provide for a derogation from the mandatory exclusion provided for in paragraphs 1 and 2, on an exceptional basis, for overriding reasons relating to the public interest such as public health or protection of the environment.
Member States may also provide for a derogation from the mandatory exclusion provided in paragraph 2, where an exclusion would be clearly disproportionate, in particular where only minor amounts of taxes or social security contributions are unpaid or where the economic operator was informed of the exact amount due following its breach of its obligations relating to the payment of taxes or social security contributions at such time that it did not have the possibility of taking measures as provided for in the third subparagraph of paragraph 2 before expiration of the deadline for requesting participation or, in open procedures, the deadline for submitting its tender.
4.Contracting authorities may exclude or may be required by Member States to exclude from participation in a procurement procedure any economic operator in any of the following situations:
(a)where the contracting authority can demonstrate by any appropriate means a violation of applicable obligations referred to in Article 18(2);
(b)where the economic operator is bankrupt or is the subject of insolvency or winding-up proceedings, where its assets are being administered by a liquidator or by the court, where it is in an arrangement with creditors, where its business activities are suspended or it is in any analogous situation arising from a similar procedure under national laws and regulations;
(c)where the contracting authority can demonstrate by appropriate means that the economic operator is guilty of grave professional misconduct, which renders its integrity questionable;
(d)where the contracting authority has sufficiently plausible indications to conclude that the economic operator has entered into agreements with other economic operators aimed at distorting competition;
(e)where a conflict of interest within the meaning of Article 24 cannot be effectively remedied by other less intrusive measures;
(f)where a distortion of competition from the prior involvement of the economic operators in the preparation of the procurement procedure, as referred to in Article 41, cannot be remedied by other, less intrusive measures;
(g)where the economic operator has shown significant or persistent deficiencies in the performance of a substantive requirement under a prior public contract, a prior contract with a contracting entity or a prior concession contract which led to early termination of that prior contract, damages or other comparable sanctions;
(h)where the economic operator has been guilty of serious misrepresentation in supplying the information required for the verification of the absence of grounds for exclusion or the fulfilment of the selection criteria, has withheld such information or is not able to submit the supporting documents required pursuant to Article 59; or
(i)where the economic operator has undertaken to unduly influence the decision-making process of the contracting authority, to obtain confidential information that may confer upon it undue advantages in the procurement procedure or to negligently provide misleading information that may have a material influence on decisions concerning exclusion, selection or award.
Notwithstanding point (b) of the first subparagraph, Member States may require or may provide for the possibility that the contracting authority does not exclude an economic operator which is in one of the situations referred to in that point, where the contracting authority has established that the economic operator in question will be able to perform the contract, taking into account the applicable national rules and measures on the continuation of business in the case of the situations referred to in point (b).
5.Contracting authorities shall at any time during the procedure exclude an economic operator where it turns out that the economic operator is, in view of acts committed or omitted either before or during the procedure, in one of the situations referred to in paragraphs 1 and 2.
At any time during the procedure, contracting authorities may exclude or may be required by Member States to exclude an economic operator where it turns out that the economic operator is, in view of acts committed or omitted either before or during the procedure, in one of the situations referred to in paragraph 4.
6.Any economic operator that is in one of the situations referred to in paragraphs 1 and 4 may provide evidence to the effect that measures taken by the economic operator are sufficient to demonstrate its reliability despite the existence of a relevant ground for exclusion. If such evidence is considered as sufficient, the economic operator concerned shall not be excluded from the procurement procedure.
For this purpose, the economic operator shall prove that it has paid or undertaken to pay compensation in respect of any damage caused by the criminal offence or misconduct, clarified the facts and circumstances in a comprehensive manner by actively collaborating with the investigating authorities and taken concrete technical, organisational and personnel measures that are appropriate to prevent further criminal offences or misconduct.
The measures taken by the economic operators shall be evaluated taking into account the gravity and particular circumstances of the criminal offence or misconduct. Where the measures are considered to be insufficient, the economic operator shall receive a statement of the reasons for that decision.
An economic operator which has been excluded by final judgment from participating in procurement or concession award procedures shall not be entitled to make use of the possibility provided for under this paragraph during the period of exclusion resulting from that judgment in the Member States where the judgment is effective.
7.By law, regulation or administrative provision and having regard to Union law, Member States shall specify the implementing conditions for this Article. They shall, in particular, determine the maximum period of exclusion if no measures as specified in paragraph 6 are taken by the economic operator to demonstrate its reliability. Where the period of exclusion has not been set by final judgment, that period shall not exceed five years from the date of the conviction by final judgment in the cases referred to in paragraph 1 and three years from the date of the relevant event in the cases referred to in paragraph 4.
1.Selection criteria may relate to:
(a)suitability to pursue the professional activity;
(b)economic and financial standing;
(c)technical and professional ability.
Contracting authorities may only impose criteria referred to in paragraphs 2, 3 and 4 on economic operators as requirements for participation. They shall limit any requirements to those that are appropriate to ensure that a candidate or tenderer has the legal and financial capacities and the technical and professional abilities to perform the contract to be awarded. All requirements shall be related and proportionate to the subject-matter of the contract.
2.With regard to suitability to pursue the professional activity, contracting authorities may require economic operators to be enrolled in one of the professional or trade registers kept in their Member State of establishment, as described in Annex XI, or to comply with any other request set out in that Annex.
In procurement procedures for services, in so far as economic operators have to possess a particular authorisation or to be members of a particular organisation in order to be able to perform in their country of origin the service concerned, the contracting authority may require them to prove that they hold such authorisation or membership.
3.With regard to economic and financial standing, contracting authorities may impose requirements ensuring that economic operators possess the necessary economic and financial capacity to perform the contract. For that purpose, contracting authorities may require, in particular, that economic operators have a certain minimum yearly turnover, including a certain minimum turnover in the area covered by the contract. In addition, contracting authorities may require that economic operators provide information on their annual accounts showing the ratios, for instance, between assets and liabilities. They may also require an appropriate level of professional risk indemnity insurance.
The minimum yearly turnover that economic operators are required to have shall not exceed two times the estimated contract value, except in duly justified cases such as relating to the special risks attached to the nature of the works, services or supplies. The contracting authority shall indicate the main reasons for such a requirement in the procurement documents or the individual report referred to in Article 84.
The ratio, for instance, between assets and liabilities may be taken into consideration where the contracting authority specifies the methods and criteria for such consideration in the procurement documents. Such methods and criteria shall be transparent, objective and non-discriminatory.
Where a contract is divided into lots this Article shall apply in relation to each individual lot. However, the contracting authority may set the minimum yearly turnover that economic operators are required to have by reference to groups of lots in the event that the successful tenderer is awarded several lots to be executed at the same time.
Where contracts based on a framework agreement are to be awarded following a reopening of competition, the maximum yearly turnover requirement referred to in the second subparagraph of this paragraph shall be calculated on the basis of the expected maximum size of specific contracts that will be performed at the same time, or, where it is not known, on the basis of the estimated value of the framework agreement. In the case of dynamic purchasing systems, the maximum yearly turnover requirement referred to in the second subparagraph shall be calculated on the basis of the expected maximum size of specific contracts to be awarded under that system.
4.With regard to technical and professional ability, contracting authorities may impose requirements ensuring that economic operators possess the necessary human and technical resources and experience to perform the contract to an appropriate quality standard.
Contracting authorities may require, in particular, that economic operators have a sufficient level of experience demonstrated by suitable references from contracts performed in the past. A contracting authority may assume that an economic operator does not possess the required professional abilities where the contracting authority has established that the economic operator has conflicting interests which may negatively affect the performance of the contract.
In procurement procedures for supplies requiring siting or installation work, services or works, the professional ability of economic operators to provide the service or to execute the installation or the work may be evaluated with regard to their skills, efficiency, experience and reliability.
5.Contracting authorities shall indicate the required conditions of participation which may be expressed as minimum levels of ability, together with the appropriate means of proof, in the contract notice or in the invitation to confirm interest.
1.At the time of submission of requests to participate or of tenders, contracting authorities shall accept the European Single Procurement Document (ESPD), consisting of an updated self-declaration as preliminary evidence in replacement of certificates issued by public authorities or third parties confirming that the relevant economic operator fulfils the following conditions:
(a)it is not in one of the situations referred to in Article 57 in which economic operators shall or may be excluded;
(b)it meets the relevant selection criteria that have been set out pursuant to Article 58;
(c)where applicable, it fulfils the objective rules and criteria that have been set out pursuant to Article 65.
Where the economic operator relies on the capacities of other entities pursuant to Article 63, the ESPD shall also contain the information referred to in the first subparagraph of this paragraph in respect of such entities.
The ESPD shall consist of a formal statement by the economic operator that the relevant ground for exclusion does not apply and/or that the relevant selection criterion is fulfilled and shall provide the relevant information as required by the contracting authority. The ESPD shall further identify the public authority or third party responsible for establishing the supporting documents and contain a formal statement to the effect that the economic operator will be able, upon request and without delay, to provide those supporting documents.
Where the contracting authority can obtain the supporting documents directly by accessing a database pursuant to paragraph 5, the EPSD shall also contain the information required for this purpose, such as the internet address of the database, any identification data and, where applicable, the necessary declaration of consent.
Economic operators may reuse an ESPD which has already been used in a previous procurement procedure, provided that they confirm that the information contained therein continues to be correct.
2.The ESPD shall be drawn up on the basis of a standard form. The Commission shall establish that standard form, by means of implementing acts. Those implementing acts shall be adopted in accordance with the examination procedure referred to in Article 89(3).
The ESPD shall be provided exclusively in electronic form.
3.Notwithstanding Article 92, the Commission shall review the practical application of the ESPD taking into account the technical development of databases in the Member States and report thereon to the European Parliament and the Council by 18 April 2017.
Where appropriate, the Commission shall make proposals for solutions optimising the cross-border access to such databases and the use of certificates and attestations in the internal market.
4.A contracting authority may ask tenderers and candidates at any moment during the procedure to submit all or part of the supporting documents where this is necessary to ensure the proper conduct of the procedure.
Before awarding the contract, the contracting authority shall, except in respect of contracts based on framework agreements where such contracts are concluded in accordance with Article 33(3) or point (a) of Article 33(4), require the tenderer to which it has decided to award the contract to submit up-to-date supporting documents in accordance with Article 60 and, where appropriate, Article 62. The contracting authority may invite economic operators to supplement or clarify the certificates received pursuant to Articles 60 and 62.
5.Notwithstanding paragraph 4, economic operators shall not be required to submit supporting documents or other documentary evidence where and in so far as the contracting authority has the possibility of obtaining the certificates or the relevant information directly by accessing a national database in any Member State that is available free of charge, such as a national procurement register, a virtual company dossier, an electronic document storage system or a prequalification system.
Notwithstanding paragraph 4, economic operators shall not be required to submit supporting documents where the contracting authority having awarded the contract or concluded the framework agreement already possesses these documents.
For the purpose of the first subparagraph, Member States shall ensure that databases which contain relevant information on economic operators and which may be consulted by their contracting authorities may also be consulted, under the same conditions, by contracting authorities of other Member States.
6.Member States shall make available and up-to-date in e-Certis a complete list of databases containing relevant information on economic operators which can be consulted by contracting authorities from other Member States. Upon request, Member States shall communicate to other Member States any information related to the databases referred to in this Article.
1.Contracting authorities may require the certificates, statements and other means of proof referred to in paragraphs 2, 3 and 4 of this Article and Annex XII as evidence for the absence of grounds for exclusion as referred to in Article 57 and for the fulfilment of the selection criteria in accordance with Article 58.
Contracting authorities shall not require means of proof other than those referred to in this Article and in Article 62. In respect of Article 63, economic operators may rely on any appropriate means to prove to the contracting authority that they will have the necessary resources at their disposal.
2.Contracting authorities shall accept the following as sufficient evidence that none of the cases specified in Article 57 apply to the economic operator:
(a)as regards paragraph 1 of that Article, the production of an extract from the relevant register, such as judicial records or, failing that, of an equivalent document issued by a competent judicial or administrative authority in the Member State or country of origin or the country where the economic operator is established showing that those requirements have been met;
(b)as regards paragraph 2 and point (b) of paragraph 4 of that Article, a certificate issued by the competent authority in the Member State or country concerned.
Where the Member State or country in question does not issue such documents or certificates, or where these do not cover all the cases specified in paragraphs 1 and 2 and point (b) of paragraph 4 of Article 57, they may be replaced by a declaration on oath or, in Member States or countries where there is no provision for declarations on oath, by a solemn declaration made by the person concerned before a competent judicial or administrative authority, a notary or a competent professional or trade body, in the Member State or country of origin or in the Member State or country where the economic operator is established.
A Member State shall, where relevant, provide an official declaration stating that the documents or certificates referred to in this paragraph are not issued or that they do not cover all the cases specified in paragraphs 1 and 2 and point (b) of paragraph 4 of Article 57. Such official declarations shall be made available through the online repository of certificates (e-Certis) referred to in Article 61.
3.Proof of the economic operator’s economic and financial standing may, as a general rule, be provided by one or more of the references listed in Annex XII Part I.
Where, for any valid reason, the economic operator is unable to provide the references requested by the contracting authority, it may prove its economic and financial standing by any other document which the contracting authority considers appropriate.
4.Evidence of the economic operators’ technical abilities may be provided by one or more of the means listed in Annex XII Part II, in accordance with the nature, quantity or importance, and use of the works, supplies or services.
5.Upon request, Member States shall make available to other Member States any information relating to the grounds for exclusion listed in Article 57, the suitability to pursue the professional activity, and the financial and technical capacities of tenderers referred to in Article 58, and any information relating to the means of proof referred to in this Article.
1.With a view to facilitating cross-border tendering, Member States shall ensure that the information concerning certificates and other forms of documentary evidence introduced in e-Certis established by the Commission is constantly kept up-to-date.
2.Contracting authorities shall have recourse to e-Certis and shall require primarily such types of certificates or forms of documentary evidence that are covered by e-Certis.
3.The Commission shall make available all language versions of the ESPD in e-Certis.
1.Contracting authorities shall, where they require the production of certificates drawn up by independent bodies attesting that the economic operator complies with certain quality assurance standards, including on accessibility for disabled persons, refer to quality assurance systems based on the relevant European standards series certified by accredited bodies. They shall recognise equivalent certificates from bodies established in other Member States. They shall also accept other evidence of equivalent quality assurance measures where the economic operator concerned had no possibility of obtaining such certificates within the relevant time limits for reasons that are not attributable to that economic operator provided that the economic operator proves that the proposed quality assurance measures comply with the required quality assurance standards.
2.Where contracting authorities require the production of certificates drawn up by independent bodies attesting that the economic operator complies with certain environmental management systems or standards, they shall refer to the Eco-Management and Audit Scheme (EMAS) of the Union or to other environmental management systems as recognised in accordance with Article 45 of Regulation (EC) No 1221/2009 or other environmental management standards based on the relevant European or international standards by accredited bodies. They shall recognise equivalent certificates from bodies established in other Member States.
Where an economic operator had demonstrably no access to such certificates, or no possibility of obtaining them within the relevant time limits for reasons that are not attributable to that economic operator, the contracting authority shall also accept other evidence of environmental management measures, provided that the economic operator proves that these measures are equivalent to those required under the applicable environmental management system or standard.
3.Upon request, Member States shall make available to other Member States, in accordance with Article 86, any information relating to the documents produced as evidence of compliance with quality and environmental standards referred to in paragraphs 1 and 2.
1.With regard to criteria relating to economic and financial standing as set out pursuant to Article 58(3), and to criteria relating to technical and professional ability as set out pursuant to Article 58(4), an economic operator may, where appropriate and for a particular contract, rely on the capacities of other entities, regardless of the legal nature of the links which it has with them. With regard to criteria relating to the educational and professional qualifications as set out in point (f) of Annex XII Part II, or to the relevant professional experience, economic operators may however only rely on the capacities of other entities where the latter will perform the works or services for which these capacities are required. Where an economic operator wants to rely on the capacities of other entities, it shall prove to the contracting authority that it will have at its disposal the resources necessary, for example, by producing a commitment by those entities to that effect.
The contracting authority shall, in accordance with Articles 59, 60 and 61, verify whether the entities on whose capacity the economic operator intends to rely fulfil the relevant selection criteria and whether there are grounds for exclusion pursuant to Article 57. The contracting authority shall require that the economic operator replaces an entity which does not meet a relevant selection criterion, or in respect of which there are compulsory grounds for exclusion. The contracting authority may require or may be required by the Member State to require that the economic operator substitutes an entity in respect of which there are non-compulsory grounds for exclusion.
Where an economic operator relies on the capacities of other entities with regard to criteria relating to economic and financial standing, the contracting authority may require that the economic operator and those entities be jointly liable for the execution of the contract.
Under the same conditions, a group of economic operators as referred to in Article 19(2) may rely on the capacities of participants in the group or of other entities.
2.In the case of works contracts, service contracts and siting or installation operations in the context of a supply contract, contracting authorities may require that certain critical tasks be performed directly by the tenderer itself or, where the tender is submitted by a group of economic operators as referred to in Article 19(2), by a participant in that group.
1.Member States may establish or maintain either official lists of approved contractors, suppliers or service providers or provide for a certification by certification bodies complying with European certification standards within the meaning of Annex VII.
They shall inform the Commission and the other Member States of the address of the certification body or the body responsible for the official lists, to which applications shall be sent.
2.Member States shall adapt the conditions for registration on the official lists referred to in paragraph 1 and for the issue of certificates by certification bodies to the provisions of this subsection.
Member States shall also adapt those conditions to Article 63 as regards applications for registration submitted by economic operators belonging to a group and claiming resources made available to them by the other companies in the group. In such cases, those operators shall prove to the authority establishing the official list that they will have those resources at their disposal throughout the period of validity of the certificate attesting to their registration on the official list and that throughout the same period those companies continue to fulfil the qualitative selection requirements encompassed by the official list or certificate on which operators rely for their registration.
3.Economic operators registered on the official lists or having a certificate may, for each contract, submit to the contracting authority a certificate of registration issued by the competent authority or the certificate issued by the competent certification body.
Those certificates shall state the references which enabled those economic operators to be registered on the official list or to obtain certification and the classification given in that list.
4.Certified registration on official lists by the competent bodies or a certificate issued by the certification body shall constitute a presumption of suitability with regard to requirements for qualitative selection encompassed by the official list or certificate.
5.Information that can be deduced from registration on official lists or certification shall not be questioned without justification. With regard to the payment of social security contributions and taxes, an additional certificate may be required of any registered economic operator whenever a contract is to be awarded.
The contracting authorities of other Member States shall apply paragraph 3 and the first subparagraph of this paragraph only in favour of economic operators established in the Member State holding the official list.
6.The requirements of proof for the criteria for qualitative selection encompassed by the official list or certificate shall comply with Article 60 and, where appropriate, Article 62. For any registration of economic operators of other Member States on an official list or for their certification, no further proof or statements shall be required other than those requested of national economic operators.
Economic operators may request at any time their registration on an official list or the issuance of a certificate. They shall be informed within a reasonably short period of time of the decision of the authority drawing up the official list or of the competent certification body.
7.Economic operators from other Member States shall not be obliged to undergo such registration or certification in order to participate in a public contract. The contracting authorities shall recognise equivalent certificates from bodies established in other Member States. They shall also accept other equivalent means of proof.
8.Upon request, Member States shall make available to other Member States any information relating to the documents produced as evidence that the economic operators fulfil the requirements to be registered on the official list of approved economic operators or as evidence that economic operators from another Member State possess an equivalent certification.
1.In restricted procedures, competitive procedures with negotiation, competitive dialogue procedures and innovation partnerships, contracting authorities may limit the number of candidates meeting the selection criteria that they will invite to tender or to conduct a dialogue, provided the minimum number, in accordance with paragraph 2, of qualified candidates is available.
2.The contracting authorities shall indicate, in the contract notice or in the invitation to confirm interest, the objective and non-discriminatory criteria or rules they intend to apply, the minimum number of candidates they intend to invite and, where appropriate, the maximum number.
In the restricted procedure the minimum number of candidates shall be five. In the competitive procedure with negotiation, in the competitive dialogue procedure and in the innovation partnership the minimum number of candidates shall be three. In any event the number of candidates invited shall be sufficient to ensure genuine competition.
The contracting authorities shall invite a number of candidates at least equal to the minimum number. However, where the number of candidates meeting the selection criteria and the minimum levels of ability as referred to in Article 58(5) is below the minimum number, the contracting authority may continue the procedure by inviting the candidates with the required capabilities. In the context of the same procedure, the contracting authority shall not include economic operators that did not request to participate, or candidates that do not have the required capabilities.
Where contracting authorities exercise the option of reducing the number of tenders to be negotiated as provided for in Article 29(6) or of solutions to be discussed as provided for in Article 30(4), they shall do so by applying the award criteria stated in the procurement documents. In the final stage, the number arrived at shall make for genuine competition in so far as there are enough tenders, solutions or qualified candidates.
1.Without prejudice to national laws, regulations or administrative provisions concerning the price of certain supplies or the remuneration of certain services, contracting authorities shall base the award of public contracts on the most economically advantageous tender.
2.The most economically advantageous tender from the point of view of the contracting authority shall be identified on the basis of the price or cost, using a cost-effectiveness approach, such as life-cycle costing in accordance with Article 68, and may include the best price-quality ratio, which shall be assessed on the basis of criteria, including qualitative, environmental and/or social aspects, linked to the subject-matter of the public contract in question. Such criteria may comprise, for instance:
(a)quality, including technical merit, aesthetic and functional characteristics, accessibility, design for all users, social, environmental and innovative characteristics and trading and its conditions;
(b)organisation, qualification and experience of staff assigned to performing the contract, where the quality of the staff assigned can have a significant impact on the level of performance of the contract; or
(c)after-sales service and technical assistance, delivery conditions such as delivery date, delivery process and delivery period or period of completion.
The cost element may also take the form of a fixed price or cost on the basis of which economic operators will compete on quality criteria only.
Member States may provide that contracting authorities may not use price only or cost only as the sole award criterion or restrict their use to certain categories of contracting authorities or certain types of contracts.
3.Award criteria shall be considered to be linked to the subject-matter of the public contract where they relate to the works, supplies or services to be provided under that contract in any respect and at any stage of their life cycle, including factors involved in:
(a)the specific process of production, provision or trading of those works, supplies or services; or
(b)a specific process for another stage of their life cycle,
even where such factors do not form part of their material substance.
4.Award criteria shall not have the effect of conferring an unrestricted freedom of choice on the contracting authority. They shall ensure the possibility of effective competition and shall be accompanied by specifications that allow the information provided by the tenderers to be effectively verified in order to assess how well the tenders meet the award criteria. In case of doubt, contracting authorities shall verify effectively the accuracy of the information and proof provided by the tenderers.
5.The contracting authority shall specify, in the procurement documents, the relative weighting which it gives to each of the criteria chosen to determine the most economically advantageous tender, except where this is identified on the basis of price alone.
Those weightings may be expressed by providing for a range with an appropriate maximum spread.
Where weighting is not possible for objective reasons, the contracting authority shall indicate the criteria in decreasing order of importance.
1.Life-cycle costing shall to the extent relevant cover parts or all of the following costs over the life cycle of a product, service or works:
(a)costs, borne by the contracting authority or other users, such as:
costs relating to acquisition,
costs of use, such as consumption of energy and other resources,
maintenance costs,
end of life costs, such as collection and recycling costs.
(b)costs imputed to environmental externalities linked to the product, service or works during its life cycle, provided their monetary value can be determined and verified; such costs may include the cost of emissions of greenhouse gases and of other pollutant emissions and other climate change mitigation costs.
2.Where contracting authorities assess the costs using a life-cycle costing approach, they shall indicate in the procurement documents the data to be provided by the tenderers and the method which the contracting authority will use to determine the life-cycle costs on the basis of those data.
The method used for the assessment of costs imputed to environmental externalities shall fulfil all of the following conditions:
(a)it is based on objectively verifiable and non-discriminatory criteria. In particular, where it has not been established for repeated or continuous application, it shall not unduly favour or disadvantage certain economic operators;
(b)it is accessible to all interested parties;
(c)the data required can be provided with reasonable effort by normally diligent economic operators, including economic operators from third countries party to the GPA or other international agreements by which the Union is bound.
3.Whenever a common method for the calculation of life-cycle costs has been made mandatory by a legislative act of the Union, that common method shall be applied for the assessment of life-cycle costs.
A list of such legislative acts, and where necessary the delegated acts supplementing them, is set out in Annex XIII. The Commission shall be empowered to adopt delegated acts in accordance with Article 87 concerning the update of that list, when an update of the list is necessary due to the adoption of new legislation making a common method mandatory or the repeal or modification of existing legal acts.
1.Contracting authorities shall require economic operators to explain the price or costs proposed in the tender where tenders appear to be abnormally low in relation to the works, supplies or services.
2.The explanations referred to in paragraph 1 may in particular relate to:
(a)the economics of the manufacturing process, of the services provided or of the construction method;
(b)the technical solutions chosen or any exceptionally favourable conditions available to the tenderer for the supply of the products or services or for the execution of the work;
(c)the originality of the work, supplies or services proposed by the tenderer;
(d)compliance with obligations referred to in Article 18(2);
(e)compliance with obligations referred to in Article 71;
(f)the possibility of the tenderer obtaining State aid.
3.The contracting authority shall assess the information provided by consulting the tenderer. It may only reject the tender where the evidence supplied does not satisfactorily account for the low level of price or costs proposed, taking into account the elements referred to in paragraph 2.
Contracting authorities shall reject the tender, where they have established that the tender is abnormally low because it does not comply with applicable obligations referred to in Article 18(2).
4.Where a contracting authority establishes that a tender is abnormally low because the tenderer has obtained State aid, the tender may be rejected on that ground alone only after consultation with the tenderer where the latter is unable to prove, within a sufficient time limit fixed by the contracting authority, that the aid in question was compatible with the internal market within the meaning of Article 107 TFEU. Where the contracting authority rejects a tender in those circumstances, it shall inform the Commission thereof.
5.Upon request, Member States shall make available to other Member States by means of administrative cooperation any information at its disposal, such as laws, regulations, universally applicable collective agreements or national technical standards, relating to the evidence and documents produced in relation to details listed in paragraph 2.
Regulation (EC) No 765/2008 of the European Parliament and of the Council of 9 July 2008 setting out the requirements for accreditation and market surveillance relating to the marketing of products and repealing Regulation (EEC) No 339/93 (OJ L 218, 13.8.2008, p. 30).
Council Framework Decision 2008/841/JHA of 24 October 2008 on the fight against organised crime (OJ L 300, 11.11.2008, p. 42).
Council Framework Decision 2003/568/JHA of 22 July 2003 on combating corruption in the private sector (OJ L 192, 31.7.2003, p. 54).
Council Framework Decision of 13 June 2002 on combating terrorism (OJ L 164, 22.6.2002, p. 3).
Directive 2005/60/EC of the European Parliament and of the Council of 26 October 2005 on the prevention of the use of the financial system for the purpose of money laundering and terrorist financing (OJ L 309, 25.11.2005, p. 15).
Directive 2011/36/EU of the European Parliament and of the Council of 5 April 2011 on preventing and combating trafficking in human beings and protecting its victims, and replacing Council Framework Decision 2002/629/JHA (OJ L 101, 15.4.2011, p. 1).
The Whole Directive you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i mabwysiadwyd gan yr UE): Mae'r wreiddiol version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Mae’r llinell amser yma yn dangos y fersiynau gwahanol a gymerwyd o EUR-Lex yn ogystal ag unrhyw fersiynau dilynol a grëwyd ar ôl y diwrnod ymadael o ganlyniad i newidiadau a wnaed gan ddeddfwriaeth y Deyrnas Unedig.
Cymerir dyddiadau fersiynau’r UE o ddyddiadau’r dogfennau ar EUR-Lex ac efallai na fyddant yn cyfateb â’r adeg pan ddaeth y newidiadau i rym ar gyfer y ddogfen.
Ar gyfer unrhyw fersiynau a grëwyd ar ôl y diwrnod ymadael o ganlyniad i newidiadau a wnaed gan ddeddfwriaeth y Deyrnas Unedig, bydd y dyddiad yn cyd-fynd â’r dyddiad cynharaf y daeth y newid (e.e. ychwanegiad, diddymiad neu gyfnewidiad) a weithredwyd i rym. Am ragor o wybodaeth gweler ein canllaw i ddeddfwriaeth ddiwygiedig ar Ddeall Deddfwriaeth.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys