Article 275U.K.Time limits for procedures(Article 190 of the Financial Regulation)
1.Tenders must reach the contracting authority at the address and by no later than the date and time shown in the invitation to tender. The time limit for receipt of tenders and requests to participate, laid down by the contracting authorities, shall be long enough to allow interested parties a reasonable and appropriate period to prepare and submit their tenders.
For service contracts, the minimum time between the date of dispatch of the letter of invitation to tender and the final date for receipt of tenders shall be 50 days. However, in urgent cases other time limits may be authorised.
2.Tenderers may put questions in writing before the closing date for receipt of tenders. The contracting authority shall provide the answers to the questions before the closing date for receipt of tenders.
3.In international restricted procedures, the time limit for receipt of requests to participate shall be no less than 30 days from the date on which the contract notice is published. The period between the date on which the letter of invitation is sent and the final date for the receipt of tenders shall be no less than 50 days. However, in certain exceptional cases other time limits may be authorised.
4.In international open procedures, the time limits for receipt of tenders, running from the date on which the contract notice is sent, shall be at least:
(a)90 days for works contracts;
(b)60 days for supply contracts.
However, in certain exceptional cases other time limits may be authorised.
5.In local open procedures, the time limits for receipt of tenders, running from the date when the contract notice is published, shall be at least:
(a)60 days for works contracts;
(b)30 days for supply contracts.
However, in certain exceptional cases other time limits may be authorised.
6.For the competitive negotiated procedures referred to in Articles 265(1)(b), 267(1)(c) and 269(1)(c), candidates shall be allowed at least 30 days from the date of dispatch of the letter of invitation to tender in which to submit their tenders.
7.The time limits specified in paragraphs 1 to 6 are expressed in calendar days.