xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

PART TWO U.K. COMMON PROVISIONS APPLICABLE TO THE ESI FUNDS

TITLE IXU.K. FINANCIAL MANAGEMENT, EXAMINATION AND ACCEPTANCE OF ACCOUNTS AND FINANCIAL CORRECTIONS, DECOMMITMENT

CHAPTER I U.K. Financial management

Article 76U.K.Budget commitments

The budget commitments of the Union in respect of each programme shall be made in annual instalments for each Fund during the period between 1 January 2014 and 31 December 2020. The budget commitments relating to the performance reserve in each programme shall be made separately from the remaining allocation to the programme.

[X1The decision of the Commission adopting a programme shall constitute a financing decision within the meaning of [F1Article 110(1) of the Financial Regulation] ] and once notified to the Member State concerned, a legal commitment within the meaning of that Regulation.

For each programme, the budget commitments for the first instalment shall follow the adoption of the programme by the Commission.

The budget commitments for subsequent instalments shall be made by the Commission before 1 May of each year, on the basis of the decision referred to in the second paragraph of this Article, except where Article 16 of the Financial Regulation applies.

Following application of the performance framework in accordance with Article 22, where priorities have not achieved their milestones, the Commission shall where necessary decommit the corresponding appropriations committed to the programmes concerned as part of the performance reserve and shall make them available again for the programmes for which the allocation is increased as a result of an amendment approved by the Commission in accordance with Article 22(5).