Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a guideline on capacity allocation and congestion management (Text with EEA relevance)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Mae unrhyw newidiadau sydd wedi cael eu gwneud yn barod gan y tîm yn ymddangos yn y cynnwys a chyfeirir atynt gydag anodiadau.Ar ôl y diwrnod ymadael bydd tair fersiwn o’r ddeddfwriaeth yma i’w gwirio at ddibenion gwahanol. Y fersiwn legislation.gov.uk yw’r fersiwn sy’n weithredol yn y Deyrnas Unedig. Y Fersiwn UE sydd ar EUR-lex ar hyn o bryd yw’r fersiwn sy’n weithredol yn yr UE h.y. efallai y bydd arnoch angen y fersiwn hon os byddwch yn gweithredu busnes yn yr UE. EUR-Lex Y fersiwn yn yr archif ar y we yw’r fersiwn swyddogol o’r ddeddfwriaeth fel yr oedd ar y diwrnod ymadael cyn cael ei chyhoeddi ar legislation.gov.uk ac unrhyw newidiadau ac effeithiau a weithredwyd yn y Deyrnas Unedig wedyn. Mae’r archif ar y we hefyd yn cynnwys cyfraith achos a ffurfiau mewn ieithoedd eraill o EUR-Lex. The EU Exit Web Archive legislation_originated_from_EU_p3
EU_status_warning_original_version
This legislation may since have been updated - see the latest available (revised) version
1.From the intraday cross-zonal gate opening time until the intraday cross-zonal gate closure time, the continuous trading matching algorithm shall determine which orders to select for matching such that matching:
(a)aims at maximising economic surplus for single intraday coupling per trade for the intraday market time-frame by allocating capacity to orders for which it is feasible to match in accordance with the price and time of submission;
(b)respects the allocation constraints provided in accordance with Article 58(1);
(c)respects the cross-zonal capacity provided in accordance with Article 58(1);
(d)respects the requirements for the delivery of results set out in Article 60;
(e)is repeatable and scalable.
2.The continuous trading matching algorithm shall produce the results provided for in Article 52 and correspond to the product capabilities and functionalities set out in Article 53.
1.All NEMOs, as part of their MCO function, shall ensure that the continuous trading matching algorithm produces at least the following results:
(a)the execution status of orders and prices per trade;
(b)a single net position for each bidding zone and market time unit within the intraday market.
2.All NEMOs shall ensure the accuracy and efficiency of results produced by the continuous trading matching algorithm.
3.All TSOs shall verify that the results of the continuous trading matching algorithm are consistent with cross-zonal capacity and allocation constraints in accordance with Article 58(2).
1.No later than 18 months after the entry into force of this Regulation NEMOs shall submit a joint proposal concerning products that can be taken into account in the single intraday coupling. NEMOs shall ensure that all orders resulting from these products submitted to enable the MCO functions to be performed in accordance with Article 7 are expressed in euros and make reference to the market time and the market time unit.
2.All NEMOs shall ensure that orders resulting from these products are compatible with the characteristics of cross-zonal capacity, allowing them to be matched simultaneously.
3.All NEMOs shall ensure that the continuous trading matching algorithm is able to accommodate orders covering one market time unit and multiple market time units.
4.By two years after the entry into force of this Regulation and in every second subsequent year, all NEMOs shall consult in accordance with Article 12:
(a)market participants, to ensure that available products reflect their needs;
(b)all TSOs, to ensure products take due account of operational security;
(c)all regulatory authorities, to ensure that the available products comply with the objectives of this Regulation.
5.All NEMOs shall amend the products if needed pursuant to the results of the consultation referred to in paragraph 4.
1.By 18 months after the entry into force of this Regulation, all NEMOs shall, in cooperation with the relevant TSOs, develop a proposal on harmonised maximum and minimum clearing prices to be applied in all bidding zones which participate in single intraday coupling. The proposal shall take into account an estimation of the value of lost load.
The proposal shall be subject to consultation in accordance with Article 12.
2.All NEMOs shall submit the proposal to all regulatory authorities for approval. Where a Member State has provided that an authority other than the national regulatory authority has the power to approve maximum and minimum clearing prices at the national level, the regulatory authority shall consult the proposal with the relevant authority as regards its impact on national markets.
3.After receiving a decision from the regulatory authorities, all NEMOs shall inform the concerned TSOs of that decision without unjustifiable delay.
1.Once applied, the single methodology for pricing intraday cross-zonal capacity developed in accordance with Article 55(3) shall reflect market congestion and shall be based on actual orders.
2.Prior to the approval of the single methodology for pricing intraday cross-zonal capacity set out in paragraph 3, TSOs may propose an intraday cross-zonal capacity allocation mechanism with reliable pricing consistent with the requirements of paragraph 1 for approval by the regulatory authorities of the relevant Member States. This mechanism shall ensure that the price of intraday cross-zonal capacity is available to the market participants at the time of matching the orders.
3.By 24 months after the entry into force of this Regulation, all TSOs shall develop a proposal for a single methodology for pricing intraday cross-zonal capacity. The proposal shall be subject to consultation in accordance with Article 12.
4.No charges, such as imbalance fees or additional fees, shall be applied to intraday cross-zonal capacity except for the pricing in accordance with paragraphs 1, 2 and 3.
1.By 16 months after the entry into force of this Regulation, the TSOs which intend to calculate scheduled exchanges resulting from single intraday coupling shall develop a proposal for a common methodology for this calculation.
The proposal shall be subject to consultation in accordance with Article 12.
2.The methodology shall describe the calculation and, where required, shall list the information which the relevant NEMOs shall provide to the scheduled exchange calculator and the time limits for delivering this information.
3.The calculation of scheduled exchanges shall be based on net positions as specified in Article 52(1)(b).
4.No later than two years after the approval by the regulatory authorities of the concerned region of the proposal referred to in paragraph 1, the relevant TSOs shall review the methodology. Thereafter, if requested by the competent regulatory authorities, the TSOs shall review the methodology every two years.
1.TSOs in bidding zones where more than one NEMO is designated and/or offers trading services, or where interconnectors which are not operated by TSOs certified according to Article 3 of Regulation (EC) No 714/2009 exist, shall develop a proposal for cross-zonal capacity allocation and other necessary arrangements for such bidding zones in cooperation with concerned TSOs, NEMOs and operators of interconnectors who are not certified as TSOs to ensure that the relevant NEMOs and interconnectors provide the necessary data and financial coverage for such arrangements. These arrangements must allow additional TSOs and NEMOs to join these arrangements.
2.The proposal shall be submitted for approval by the relevant national regulatory authorities within 4 months of more than one NEMO being designated and/or allowed to offer trading services in a bidding zone or if a new interconnector is not operated by a certified TSO. For existing interconnectors which are not operated by certified TSOs the proposal shall be submitted within 4 months after entry into force of this Regulation.
1.Each coordinated capacity calculator shall ensure that cross-zonal capacity and allocation constraints are provided to the relevant NEMOs no later than 15 minutes before the intraday cross-zonal gate opening time.
2.If updates to cross-zonal capacity and allocation constraints are required, due to operational changes on the transmission system, each TSO shall notify the coordinated capacity calculators in its capacity calculation region. The coordinated capacity calculators shall then notify the relevant NEMOs.
3.If any coordinated capacity calculator is unable to comply with paragraph 1, that coordinated capacity calculator shall notify the relevant NEMOs. These NEMOs shall publish a notice to all market participants without unjustifiable delay.
1.By 16 months after the entry into force of this Regulation, all TSOs shall be responsible for proposing the intraday cross-zonal gate opening and intraday cross-zonal gate closure times. The proposal shall be subject to consultation in accordance with Article 12.
2.The intraday cross-zonal gate closure time shall be set in such a way that it:
(a)maximises market participants' opportunities for adjusting their balances by trading in the intraday market time-frame as close as possible to real time; and
(b)provides TSOs and market participants with sufficient time for their scheduling and balancing processes in relation to network and operational security.
3.One intraday cross-zonal gate closure time shall be established for each market time unit for a given bidding zone border. It shall be at most one hour before the start of the relevant market time unit and shall take into account the relevant balancing processes in relation to operational security.
4.The intraday energy trading for a given market time unit for a bidding zone border shall start at the latest at the intraday cross-zonal gate opening time of the relevant bidding zone borders and shall be allowed until the intraday cross-zonal gate closure time.
5.Before the intraday cross-zonal gate closure time, market participants shall submit to relevant NEMOs all the orders for a given market time unit. All NEMOs shall submit the orders for a given market time unit for single matching immediately after the orders have been received from market participants.
6.Orders matched in single intraday coupling shall be considered firm.
7.MCO functions shall ensure the anonymity of orders submitted via the shared order book.
1.All NEMOs performing MCO functions shall deliver the continuous trading matching algorithm results:
(a)to all other NEMOs, for results on the execution status per trade specified in Article 52(1)(a);
(b)to all TSOs and scheduled exchange calculators, for results single net positions specified in Article 52(1)(b).
2.If, in accordance with paragraph 1(a), any NEMO, for reasons outside its responsibility, is unable to deliver these continuous trading matching algorithm results, it shall notify all other NEMOs.
3.If, in accordance with paragraph 1(b), any NEMO, for reasons outside its responsibility, is unable to deliver these continuous trading matching algorithm results, it shall notify all TSOs and each scheduled exchange calculator as soon as reasonably practicable. All NEMOs shall notify the market participants concerned.
4.All NEMOs shall send, without undue delay, the necessary information to market participants to ensure that the actions specified in Articles 68 and 73(3) can be undertaken.
1.Each scheduled exchange calculator shall calculate scheduled exchanges between bidding zones for each market time unit in accordance with the methodology established in accordance with Article 56.
2.Each scheduled exchange calculator shall notify the relevant NEMOs, central counter parties, shipping agents, and TSOs of the agreed scheduled exchanges.
1.As soon as the orders are matched, each NEMO shall publish for relevant market participants at least the status of execution of orders and prices per trade produced by the continuous trading matching algorithm in accordance with Article 52(1)(a).
2.Each NEMO shall ensure that information on aggregated executed volumes and prices is made publicly available in an easily accessible format for at least 5 years. The information to be published shall be proposed by all NEMOS within the proposal for continuous trading matching algorithm pursuant to Article 37(5).
1.By 18 months after the entry into force of this Regulation, the relevant NEMOs and TSOs on bidding zone borders may jointly submit a common proposal for the design and implementation of complementary regional intraday auctions. The proposal shall be subject to consultation in accordance with Article 12.
2.Complementary regional intraday auctions may be implemented within or between bidding zones in addition to the single intraday coupling solution referred to in Article 51. In order to hold regional intraday auctions, continuous trading within and between the relevant bidding zones may be stopped for a limited period of time before the intraday cross-zonal gate closure time, which shall not exceed the minimum time required to hold the auction and in any case 10 minutes.
3.For complementary regional intraday auctions, the methodology for pricing intraday cross-zonal capacity may differ from the methodology established in accordance with Article 55(3) but it shall nevertheless meet the principles provided for in Article 55(1).
4.The competent regulatory authorities may approve the proposal for complementary regional intraday auctions if the following conditions are met:
(a)regional auctions shall not have an adverse impact on the liquidity of the single intraday coupling;
(b)all cross-zonal capacity shall be allocated through the capacity management module;
(c)the regional auction shall not introduce any undue discrimination between market participants from adjacent regions;
(d)the timetables for regional auctions shall be consistent with single intraday coupling to enable market participants to trade as close as possible to real-time;
(e)regulatory authorities shall have consulted the market participants in the Member States concerned.
5.At least every two years after the decision on complementary regional auctions, the regulatory authorities of the Member States concerned shall review the compatibility of any regional solutions with single intraday coupling to ensure that the conditions above continue to be fulfilled.
1.Where jointly requested by the regulatory authorities of the Member States of each of the bidding zone borders concerned, the TSOs concerned shall also provide explicit allocation, in addition to implicit allocation, that is to say, capacity allocation separate from the electricity trade, via the capacity management module on bidding zone borders.
2.The TSOs on the bidding zone borders concerned shall jointly develop a proposal on the conditions that shall be fulfilled by market participants to participate in explicit allocation. The proposal shall be subject to the joint approval by the regulatory authorities of the Member States of each of the bidding zone borders concerned.
3.When establishing the capacity management module, discrimination shall be avoided when simultaneously allocating capacity implicitly and explicitly. The capacity management module shall determine which orders to select for matching and which explicit capacity requests to accept, according to a ranking of price and time of entrance.
1.The NEMOs concerned shall cooperate closely with the TSOs concerned and shall consult market participants in accordance with Article 12 in order to translate the needs of market participants linked to explicit capacity allocation rights into non-standard intraday products.
2.Prior to deciding on the removal of explicit allocation, the regulatory authorities of the Member States of each of the bidding zone borders concerned shall jointly organise a consultation to assess whether the proposed non-standard intraday products meet the market participants' needs for intraday trading.
3.The competent regulatory authorities of the Member States of each of the bidding zone borders concerned shall jointly approve the introduced non-standard products and the removal of explicit allocation.
1.Market participants shall ensure the completion of nomination, clearing and settlement related to explicit allocation of cross-zonal capacity.
2.Market participants shall fulfil any financial obligations, relating to clearing and settlement arising from explicit allocation.
3.The participating TSOs shall publish relevant information on the interconnections to which explicit allocation is applicable, including the cross-zonal capacity for explicit allocation.
A request for explicit cross-zonal capacity may be submitted by a market participant only for an interconnection where the explicit allocation is applicable. For each request for explicit capacity the market participant shall submit the volume and the price to the capacity management module. The price and volume of explicit allocated capacity shall be made publicly available by the relevant TSOs.
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i mabwysiadwyd gan yr UE): Mae'r wreiddiol version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys