The Pollution Prevention and Control (Scotland) Regulations 2012

Permits: authorised operationsS

This adran has no associated Nodiadau Polisi

14.—(1) A permit may authorise the operation of more than one—

(a)Part A installation,

(b)Part B installation,

(c)mobile plant, or

(d)solvents installation,

on the same site if operated by the same operator.

(2) Where the operation of mobile plant is authorised by a permit, and the—

(a)plant is used to carry out an activity on the site of an installation authorised by a separate permit, and

(b)mobile plant and installation permits impose different requirements as respects the carrying out of the activity,

the requirements of the installation permit shall prevail to the extent of any inconsistency in those requirements.

(3) Subject to paragraph (4), a permit for an installation must include a map or plan showing the site, and the location on the site, of the installation.

(4) A standard rules permit for an installation, other than a hybrid permit in respect of a standard installation, must include either—

(a)a plan as specified in paragraph (3), or

(b)the national grid reference number of the location of the installation.