22.—(1) Where an EIA application is determined by the Scottish Ministers and the decision is to grant Electricity Act consent, the Scottish Ministers must consider whether it is appropriate to require monitoring measures to be carried out.

(2) When considering whether to require monitoring measures to be carried out, and the nature of any such monitoring measures, the Scottish Ministers must consider—

(a)whether monitoring measures are proportionate to the nature, location and size of the proposed development and the significance of its effects on the environment having regard in particular to the type of parameters to be monitored and the duration of the monitoring;

(b)in order to avoid duplication of monitoring, whether monitoring arrangements required under [F1retained EU law] (other than legislation implementing the requirements of [F2any law that implemented] the Directive) or other legislation applicable in Scotland are more appropriate; and

(c)if monitoring measures are to be required, whether provision should be made to require appropriate remedial action.

(3) Where the Scottish Ministers consider that it is appropriate to require monitoring measures they must do so.

(4) Where mitigation measures or monitoring measures are required by a condition imposed on the grant of an Electricity Act consent the Scottish Ministers must take steps to ensure that those measures are implemented.

(5) Where mitigation measures or monitoring measures are required by—

(a)a condition subject to which any planning permission is deemed to be granted by virtue of a direction given under section 57(2) or (2ZA) of the 1997 Act M1; or

(b)a planning obligation,

the planning authority must take steps to ensure that those measures are implemented.