Chwilio Deddfwriaeth

The Forestry (Environmental Impact Assessment) (Scotland) Regulations 2017

Changes over time for: PART 6

 Help about opening options

Version Superseded: 31/12/2020

Alternative versions:

Status:

Point in time view as at 16/05/2017.

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Forestry (Environmental Impact Assessment) (Scotland) Regulations 2017. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.

PART 6 SAVAILABILITY OF DIRECTIONS ETC. AND NOTIFICATION OF DECISIONS

Availability of opinions, directions etc. for inspectionS

23.—(1) Where any document mentioned in paragraph (2) is received, issued or adopted by the Commissioners, the Commissioners must make copies of that document available for inspection—

(a)on a website (or by other electronic means); and

(b)at all reasonable hours at an office of the Commissioners where the register may be inspected.

(2) The documents are any—

(a)request under regulation 15(1);

(b)copy of a request under regulation 15(8);

(c)direction given under regulation 9;

(d)screening opinion;

(e)screening direction;

(f)scoping opinion;

(g)scoping direction;

(h)EIA report and any additional information;

(i)reports or advice issued to the Commissioners at the time when notice is given under regulation 18(1); and

(j)statement of reasons accompanying any of the above.

Decision noticeS

24.—(1) Where an EIA application is determined by the Commissioners the notification of the decision to be given to the applicant, (referred to in these Regulations as “the decision notice”) must include the information specified in paragraph (2).

(2) The information is—

(a)a description of the forestry project;

(b)the terms of the decision;

(c)the main reasons and considerations on which the decision is based;

(d)information about the arrangements taken to ensure the public had the opportunity to participate in the decision making procedures;

(e)a summary of—

(i)the environmental information; and

(ii)the results of the consultations and information gathered pursuant to Parts 4, 5 and 6 and, where relevant, Part 7 and how those results, in particular comments received from an EEA State pursuant to consultation under regulation 27, have been incorporated or otherwise addressed;

(f)if the decision is to grant EIA consent—

(i)a statement of the mandatory conditions;

(ii)a statement of any further conditions to which the decision is subject including—

(aa)a description of any monitoring measures which may be required in accordance with regulation 25; and

(bb)a description of any mitigation measures which may be required;

(iii)the reasoned conclusion referred to in regulation 5(1)(d); and

(iv)a statement that the Commissioners are satisfied that the reasoned conclusion is still up to date; and

(g)information regarding the right to challenge the validity of the decision and the procedures for doing so.

(3) For the purposes of paragraph (2)(f)(iv), the reasoned conclusion referred to in regulation 5(1)(d) is still up to date if the Commissioners are satisfied, having regard to current knowledge and methods of assessment, that the reasoned conclusion addresses the likely significant effects of the forestry project on the environment.

(4) In this regulation and in regulation 25—

mitigation measures” means any features of the EIA forestry project and any measures envisaged in order to avoid, prevent or reduce and, if possible, offset likely significant adverse effects on the environment; and

monitoring measures” means measures requiring the monitoring of any significant adverse effects on the environment of the EIA forestry project.

Monitoring measuresS

25.—(1) Where an EIA application is determined by the Commissioners and the decision is to grant EIA consent, the Commissioners or the Scottish Ministers, as the case may be, must consider whether it is appropriate to require monitoring measures to be carried out.

(2) When considering whether to require monitoring measures to be carried out, and the nature of any such monitoring measures, the Commissioners must consider—

(a)whether monitoring measures are proportionate to the nature, location and size of the EIA forestry project and the significance of its effects on the environment having regard in particular to the type of parameters to be monitored and the duration of the monitoring;

(b)in order to avoid duplication of monitoring, whether monitoring arrangements required under Union legislation (other than legislation implementing the requirements of the Directive) or other legislation applicable in Scotland are more appropriate; and

(c)if monitoring measures are to be required, whether provision should be made to require appropriate remedial action.

(3) Where the Commissioners or the Scottish Ministers consider that it is appropriate to require monitoring measures they must do so.

(4) Where mitigation measures or monitoring measures are required, the Commissioners must take steps to ensure that those measures are implemented.

Duties to inform the applicant and public of final decisionsS

26.—(1) Where an EIA application is determined by the Commissioners, the Commissioners must—

(a)notify the applicant of the decision;

(b)notify those bodies consulted in accordance with regulation 19(1)(b) of the decision by sending a copy of the decision notice to such bodies;

(c)notify the public of the decision, and of where a copy of decision notice may be inspected, by publishing a notice in a newspaper circulating in the locality in which the land is situated, or by such other means as are reasonable in the circumstances; and

(d)make a copy of the decision notice available for public inspection—

(i)at an office of the Commissioners where the register may be inspected; and

(ii)on the application website.

(2) The Commissioners must, as soon as reasonably practicable after notification of the decision notice under regulation 30(8), comply with paragraph (1)(b) to (d) in relation to the decision so notified as if it were a decision of the Commissioners.

(3) Where regulation 28(1) applies, the Commissioners must, as soon as reasonably practicable after notification of a final decision from the EEA state concerned, comply with paragraph (1)(b) to (d) in relation to the decision so notified as if it were a decision of the Commissioners.

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Policy Note

Policy Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2012 onwards. Prior to this date these type of notes existed as ‘Executive Notes’ and accompanied Scottish Statutory Instruments from July 2005 until July 2012.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill