60.—(1) This regulation applies where—
(a)there is an arbitration agreement between a tied pub tenant and a pub-owning business;
(b)the pub-owning business commences arbitral proceedings about a matter which is, or which includes, an MRO dispute between the pub-owning business and the tied pub tenant; and
(c)the tied pub tenant would have been able to refer the MRO dispute to the Adjudicator (were it not for the commencement of arbitral proceedings by the pub-owning business) under —
(i)regulation 32(2) (disputes in connection with the full response);
(ii)regulation 35(1) (disputes in connection with the negotiation period);
(iii)regulation 37(9), (10) or 38(4) (disputes in connection with the independent assessor);
(iv)regulation 40(3) (disputes in connection with the MRO recoverable amount); or
(v)regulation 56(9) or (10) (disputes in connection with the investment agreement).
(2) The tied pub tenant may, by giving notice in writing to the pub-owning business and the Adjudicator, appoint the Adjudicator to arbitrate the MRO dispute.
(3) A notice under paragraph (2) must be given—
(a)where the arbitration agreement provides for the arbitrator to be appointed by a person other than the pub-owning business or the tied pub tenant, within the period of 21 days beginning with the day on which that person notifies the tied pub tenant of the person proposed to be appointed as arbitrator;
(b)otherwise, within the period of 21 days beginning with the day on which arbitral proceedings commenced.
(4) Where the Adjudicator is appointed to arbitrate the MRO dispute (whether under paragraph (2) or otherwise) the Adjudicator must—
(a)arbitrate the MRO dispute; or
(b)appoint another person to arbitrate that dispute.
(5) Section 14 of the Arbitration Act 1996(1) makes provision about the commencement of arbitral proceedings.
(6) An “MRO dispute” is a dispute relating to the offer of a market rent only option.
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Mae Memorandwm Esboniadol Drafft yn nodi datganiad byr o ddiben Offeryn Statudol Drafft ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Eu nod yw gwneud yr Offeryn Statudol Drafft yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd yn fanwl gerbron y Senedd o Fehefin 2004 ymlaen.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys