Compulsory Purchase Act 1965

[F111APowers of entry: further notices of entryE+W

(1)This section applies where—

(a)an acquiring authority have given a notice of entry under section 11(1) but have not yet entered on and taken possession of the land, and

(b)the authority become aware of an owner, lessee or occupier (“the newly identified person”) to whom they ought to have given a notice to treat under section 5(1) but have not.

(2)Any notice of entry already served under section 11(1) remains valid, but the authority may not enter on and take possession of the land unless they serve on the newly identified person—

(a)a notice to treat under section 5(1), and

(b)a notice of entry under section 11(1).

(3)Subsection (4) applies for the purpose of determining the period to be specified in the notice of entry under section 11(1) served on the newly identified person if—

(a)the person is an occupier of the land and the authority were not aware of the person because they were given misleading information when carrying out inquiries under section 5(1), or

(b)the person is not an occupier of the land.

(4)The period specified in the notice must be a period that ends—

(a)no earlier than the end of the period of 14 days beginning with the day on which the notice of entry is served, and

(b)no earlier than the end of the period specified in any previous notice of entry given by the acquiring authority in respect of the land.]

Textual Amendments

Modifications etc. (not altering text)

C1Pt. 1 applied (with modifications) (11.3.2024) by The Net Zero Teesside Order 2024 (S.I. 2024/174), arts. 1, 29, Sch. 8 paras. 4, 5 (with arts. 24(1)(a), 42, 43, Sch. 12)

C2Pt. 1 applied (with modifications) (11.3.2024) by The Net Zero Teesside Order 2024 (S.I. 2024/174), arts. 1, 29 (with arts. 24(1)(a), 42, 43, Sch. 12)

C11Pt. 1 applied (with modifications) (22.12.2017) by The M20 Junction 10a Development Consent Order 2017 (S.I. 2017/1202), art. 1, Sch. 6 paras. 4, 5 (with arts. 4, 37)

C12Pt. 1 applied (with modifcations) (2.1.2018) by The Boston Barrier Order 2017 (S.I. 2017/1329), arts. 1, 32 (with arts. 43(1), 55-57, Sch. 8 para. 13)

C13Pt. 1 applied (with modifcations) (2.1.2018) by The Boston Barrier Order 2017 (S.I. 2017/1329), art. 1, Sch. 3 paras. 1, 4-10 (with arts. 55-57, Sch. 8 para. 13)

C14Pt. 1 applied (with modifications) (4.1.2018) by The Blackpool Tramway (Blackpool North Extension) Order 2017 (S.I. 2017/1214), arts. 1, 27 (with arts. 58, 59)

C17Pt. 1 applied (with modifications) (18.4.2018) by The Network Rail (Hope Valley Capacity) Order 2018 (S.I. 2018/446), arts. 1, 18, 29 (with arts. 24(8), 33(2))

C18Pt. 1 applied (with modifications) (31.5.2018) by The Silvertown Tunnel Order 2018 (S.I. 2018/574), arts. 1(2), 25, Sch. 5 paras. 4, 5

C19Pt. 1 applied (with modifications) (31.5.2018) by The Silvertown Tunnel Order 2018 (S.I. 2018/574), art. 1(2), Sch. 5 paras. 4, 5

C21Pt. 1 applied (with modifications) (24.8.2018) by The Network Rail (Werrington Grade Separation) Order 2018 (S.I. 2018/923), arts. 1, 19, 28(1)(a) (with art. 31(2))

C27Pt. 1 applied (with modifications) (13.3.2019) by The Port of Tilbury (Expansion) Order 2019 (S.I. 2019/359), art. 1, Sch. 5 paras. 4, 5 (with arts. 55, 56)

C29Pt. 1 applied (with modifications) (3.4.2019) by The Millbrook Gas Fired Generating Station Order 2019 (S.I. 2019/578), arts. 1, 25

C35Pt. 1 applied (with modifications) (10.10.2019) by The Abergelli Power Gas Fired Generating Station Order 2019 (S.I. 2019/1268), arts. 1, 26

C36Pt. 1 applied (with modifications) (25.10.2019) by The Drax Power (Generating Stations) Order 2019 (S.I. 2019/1315), arts. 1, 26

C37Pt. 1 applied (with modifications) (25.10.2019) by The Drax Power (Generating Stations) Order 2019 (S.I. 2019/1315), art. 1, Sch. 9 paras. 4, 5

C47Pt. 1 applied (with modifications) (1.5.2020) by The Riverside Energy Park Order 2020 (S.I. 2020/419), arts. 1, 29 (with art. 7)

C48Pt. 1 applied (with modifications) (1.5.2020) by The Riverside Energy Park Order 2020 (S.I. 2020/419), art. 1, Sch. 8 paras. 4, 5 (with art. 7)

C49Pt. 1 applied (with modifications) (21.5.2020) by The Lake Lothing (Lowestoft) Third Crossing Order 2020 (S.I. 2020/474), art. 1, Sch. 7 paras. 4, 5 (with arts. 51, 57)

C51Pt. 1 applied (with modifications) (21.5.2020) by The Lake Lothing (Lowestoft) Third Crossing Order 2020 (S.I. 2020/474), arts. 1, 32 (with arts. 51, 57)

C53Pt. 1 applied (with modifications) (25.5.2020) by The West Midlands Rail Freight Interchange Order 2020 (S.I. 2020/511), arts. 1, 30

C55Pt. 1 applied (with modifications) (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), art. 1, Sch. 9 paras. 4, 5 (with art. 37)

C56Pt. 1 applied (with modifications) (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 29 (with art. 37)

C60Pt. 1 applied (with modifications) (19.6.2020) by The Cleve Hill Solar Park Order 2020 (S.I. 2020/547), art. 1, Sch. 6 para. 4 (with art. 37)

C61Pt. 1 applied (with modifications) (19.6.2020) by The Cleve Hill Solar Park Order 2020 (S.I. 2020/547), arts. 1, 22 (with art. 37)

C66Pt. 1 applied (with modifications) (1.9.2020) by The Immingham Open Cycle Gas Turbine Order 2020 (S.I. 2020/847), arts. 1, 25 (with Sch. 9 para. 144)

C78Pt. 1 applied (with modifications) (27.7.2023) by The Boston Alternative Energy Facility Order 2023 (S.I. 2023/778), arts. 1, 31 (with arts. 5, 27, 53, Sch. 8 paras. 6, 64)