Print Options
PrintThe Whole
Act
PrintThe Whole
Part
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Section 41A
Llinell Amser Newidiadau
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Version Superseded: 24/01/1992
Status:
Point in time view as at 01/02/1991. This version of this provision has been superseded.
Status
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Changes to legislation:
There are currently no known outstanding effects for the Town and Country Planning (Scotland) Act 1972 (repealed 27.5.1997), Section 41A.
Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
[41A Limit of duration of planning permission for winning and working of minerals.S
(1)Every planning permission for development consisting of the winning and working of minerals shall be subject to a condition as to the duration of the development.
(2)Except where a condition is specified under subsection (3) of this section the condition in the case of planning permission granted or deemed to be granted after the date of the commencement of section 24 of the Town and Country Planning (Minerals) Act 1981 is that the development must cease not later than the expiration of the period of sixty years beginning with the date of the permission.
(3)An authority granting planning permission after the date of the commencement of the said section 24 or directing after that date that planning permission shall be deemed to be granted may specify a longer or shorter period than sixty years, and if they do so, the condition is that the development must cease not later than the expiration of a period of the specified length beginning with the date of the permission.
(4)A longer or shorter period than sixty years may be prescribed for the purposes of subsections (2) and (3) of this section.
(5)The condition in the case of planning permission granted or the commencement of section 24 of the Town and Country Planning (Minerals) Act 1981 is that the development must cease not later than the expiration of the period of sixty years beginning with the date of the commencement of that section.
(6)A condition to which planning permission for development consisting of the winning and working of minerals is subject by virtue of this section is not to be regarded for the purposes of this Act as a condition such as is mentioned in subsection (1)(b) of section 27 of this Act.
(7)Where planning permission for development consisting of the winning and working of minerals is granted by the planning authority, any condition to which it is subject by virtue of this section is to be regarded for the purposes of section 33 of this Act as a condition imposed by a decision of the planning authority, and may accordingly be the subject of an appeal under that section.]
Textual Amendments
Marginal Citations