Print Options
PrintThe Whole
Act
PrintThe Whole
Part
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Section 90GA


Llinell Amser Newidiadau
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 04/11/2022.
Changes to legislation:
Highways Act 1980, Section 90GA is up to date with all changes known to be in force on or before 04 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
90GA Special procedure for certain traffic calming works in London.E+W
(1)Traffic calming works fall within this section if—
(a)the works are constructed by a local highway authority in Greater London, and
(b)the requirements of [subsections (2), (3) and (4)] below have been complied with.
(2)The requirement of this subsection is that before starting to construct the works the authority concerned gives the Secretary of State notice stating—
(a)the nature, dimensions and location of the proposed works,
(b)the type and description of signs which are proposed to be located in the highway in connection with the proposed hump, and
(c)the period (of not less than one month) within which, and the address to which, the Secretary of State may send any comments on the proposal to the authority.
(3)The requirement of this subsection is that in deciding—
(a)whether to proceed with the construction of the works, and
(b)what the nature, dimensions and location of the works as constructed are to be,
the authority concerned has regard to any comments made by the Secretary of State within the period stated in the notice.
[(4)The requirement of this subsection is that the authority concerned complies with such requirements as to consultation and publicity as may be prescribed by regulations made by the Secretary of State.]