xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULES

SCHEDULE 2E+W Minerals

Modifications etc. (not altering text)

C1Sch. 2 excluded by Water Act 1989 (c. 15, SIF 130), s. 159, (with ss. 58(7), 101(1), 141(6), 160(1)(2)(4), 163, 189(4)–(10), 190, 193(1), Sch. 26 paras. 3(1)(2), 17, 40(4), 57(6), 58)

Sch. 2 excluded (1.12.1991) by Water Resources Act 1991 (c. 57, SIF 130), ss.182, 225(2) (with ss. 16(6), 179, 222(3), Sch. 22 para. 1, Sch. 23 para. 6)

Part IIE+W

Modifications etc. (not altering text)

C6Sch. 2 Pts. 2, 3 applied (with modifications) (13.2.1992) by Severn Bridges Act 1992 (c. 3), s. 2(6), Sch. 2 Pt. II para.3

C7Sch. 2 Pt. 2 applied (16.3.1992) by Avon Weir Act 1992 (c. v), s. 4(2) (with s. 61)

C8Sch. 2 Pts. 2, 3 applied (16.7.1992) by Cattewater Reclamation Act 1992 (c. xiv), s. 3(3)

Sch. 2 Pts. 2, 3 applied (5.11.1993) by 1993 c. 42, s. 5, Sch. 4 para. 2 (with s. 30(1), Sch. 2 para. 9).

Sch. 2 Pt. 2 applied (28.7.1998) by 1998 c. iv, s. 7(1) (with s. 41)

C9Sch. 2 Pts. 2, 3 applied (with modifications) by Dartford-Thurrock Crossing Act 1988 (c. 20, SIF 59), s. 2(5), Sch. 2 Pt. II para. 4(1)

Sch. 2 Pts. 2, 3 applied (with modifications) (3.6.1999) by S.I. 1999/1555, art. 9

Sch. 2 Pt 2 applied (with modifications) (E.) (29.3.2001) by S.I. 2001/1347, art. 36(1) (with arts. 15, 37, 38(2))

Sch. 2 Pt. 2 applied (with modifications) (E.) (29.3.2001) by S.I. 2001/1348, art. 12(1)

C10Sch. 2 Pt. 2 modified (18.12.1996) by 1996 c. 61, s. 4, Sch. 4 Pt. III para. 13

C11Sch. 2 Pt. 2 applied (with modifications) (12.8.2002) by The Channel Tunnel Rail Link (Thames Tunnel Approach) Order 2002 (S.I. 2002/1943), art. 6(2)

Sch. 2 Pt. 2 applied (with modifications) (14.3.2002) by The Chester Guided Busway Order 2002 (S.I. 2002/412), art. 39(1) (with art. 38)

C13Sch. 2 Pts. 2, 3 applied (with modifications) (22.7.2005) by The Midland Metro (Birmingham City Centre Extension, etc.) Order 2005 (S.I. 2005/1794), arts. 1, 46(1) (with art. 47)

C14Sch. 2 Pt. 2 applied (with modifications) (22.7.2008) by Crossrail Act 2008 (c. 18), Sch. 6 para. 17

C15Sch. 2 Pts. 2, 3 incorporated (with modifications) (15.8.2013) by The North Blyth Biomass Power Station Order 2013 (S.I. 2013/1873), arts. 1, 14 (with art. 30)

C16Sch. 2 Pt. 2 incorporated (with modifications) (7.5.2014) by The National Grid (North London Reinforcement Project) Order 2014 (S.I. 2014/1052), arts. 1, 23

Sch. 2 Pt. 2 incorporated (with modifications) (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 40

C17Sch. 2 Pts. 1-3 applied (with modifications) (2.10.2014) by The Clocaenog Forest Wind Farm Order 2014 (S.I. 2014/2441), arts. 1, 22 (with art. 33)

C18Sch. 2 Pt. 2 incorporated (with modifications) (29.10.2014) by The Able Marine Energy Park Development Consent Order 2014 (S.I. 2014/2935), art. 32 (with arts. 30(4), 53)

C20Sch. 2 Pt. 2 incorporated (with modifications) (25.2.2015) by The A160/A180 (Port of Immingham Improvement) Development Consent Order 2015 (S.I. 2015/129), arts. 1, 20

C21Sch. 2 Pt. 2 incorporated (with modifications) (1.4.2015) by The Knottingley Power Plant Order 2015 (S.I. 2015/680), arts. 1, 19 (with Sch. 8 para. 10)

C22Sch. 2 Pts. 2, 3 incorporated (with modifications) (9.6.2015) by The White Moss Landfill Order 2015 (S.I. 2015/1317), arts. 1, 13 (with art. 5)

C24Sch. 2 Pts. 2, 3 incorporated in part (with modifications) (14.8.2015) by The Hirwaun Generating Station Order 2015 (S.I. 2015/1574), arts. 1, 17(1) (with art. 30)

C25Sch. 2 Pt. 2 incorporated (with modifications) (26.8.2015) by The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 (S.I. 2015/1592), arts. 1, 23 (with arts. 40, 41)

C26Sch. 2 Pt. 2 incorporated in part (with modifications) (30.12.2015) by The Port Talbot Steelworks Generating Station Order 2015 (S.I. 2015/1984), arts. 1, 14 (with art. 26)

C27Sch. 2 Pts. 2, 3 incorporated (with modifications) (2.2.2016) by The East Midlands Gateway Rail Freight Interchange and Highway Order 2016 (S.I. 2016/17), arts. 1, 27

C28Sch. 2 Pt. 2 incorporated in part (with modifications) (9.2.2016) by The National Grid (Hinkley Point C Connection Project) Order 2016 (S.I. 2016/49), arts. 1, 20 (with art. 32)

C29Sch. 2 Pt. 2 incorporated (with modifications) (18.2.2016) by The A19/A1058 Coast Road (Junction Improvement) Development Consent Order 2016 (S.I. 2016/73), arts. 1, 19 (with art. 37)

C30Sch. 2 Pts. 2, 3 incorporated in part (with modifications) (25.3.2016) by The Thorpe Marsh Gas Pipeline Order 2016 (S.I. 2016/297), arts. 1, 21 (with art. 39)

C31Sch. 2 Pts. 2, 3 incorporated (with modifications) (1.6.2016) by The A14 Cambridge to Huntingdon Improvement Scheme Development Consent Order 2016 (S.I. 2016/547), arts. 1, 21 (with arts. 4, 5(3))

C33Sch. 2 Pts. 2, 3 incorporated (with modifications) (10.8.2016) by The York Potash Harbour Facilities Order 2016 (S.I. 2016/772), arts. 1, 26 (with arts. 35, 36)

C34Sch. 2 Pts. 2, 3 incorporated (with modifications) (15.9.2016) by The River Humber Gas Pipeline Replacement Order 2016 (S.I. 2016/853), arts. 1, 37 (with art. 43)

C35Sch. 2 Pts. 2, 3 incorporated in part (with modifications) (23.9.2016) by The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016 (S.I. 2016/863), arts. 1, 33

C37Sch. 2 Pt. 2 incorporated (with modifications) (24.8.2017) by The National Grid (Richborough Connection Project) Development Consent Order 2017 (S.I. 2017/817), arts. 1, 19 (with art. 22)

C38Sch. 2 Pts. 2, 3 incorporated (with modifications) (22.12.2017) by The M20 Junction 10a Development Consent Order 2017 (S.I. 2017/1202), arts. 1, 22 (with arts. 4, 37)

C39Sch. 2 Pts. 2, 3 incorporated (with modifications) (31.5.2018) by The Silvertown Tunnel Order 2018 (S.I. 2018/574), arts. 1(2), 20

C40Sch. 2 Pt. 2 incorporated (with modifications) (3.10.2018) by The A19/A184 Testos Junction Alteration Development Consent Order 2018 (S.I. 2018/994), arts. 1, 21 (with arts. 3(3), 5)

C42Sch. 2 Pt. 2 incorporated (with modifications) (10.10.2019) by The Abergelli Power Gas Fired Generating Station Order 2019 (S.I. 2019/1268), arts. 1, 19

C43Sch. 2 Pt. 2 incorporated (with modifications) (25.10.2019) by The Drax Power (Generating Stations) Order 2019 (S.I. 2019/1315), arts. 1, 33

C44Sch. 2 Pt. 2 incorporated in part (with modifications) (30.10.2019) by The Northampton Gateway Rail Freight Interchange Order 2019 (S.I. 2019/1358), arts. 1, 28 (with Sch. 13 Pt. 1 para. 19)

C45Sch. 2 Pt. 2 incorporated (with modifications) (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), arts. 1, 24 (with art. 3(1))

C47Sch. 2 Pt. 2 incorporated (with modifications) (30.4.2020) by The A585 Windy Harbour to Skippool Highway Development Consent Order 2020 (S.I. 2020/402), arts. 1, 21 (with arts. 5, 44)

C48Sch. 2 Pt. 2 incorporated in part (with modifications) (25.5.2020) by The West Midlands Rail Freight Interchange Order 2020 (S.I. 2020/511), arts. 1, 28(1) (with art. 28(2))

C49Sch. 2 Pt. 2 incorporated (with modifications) (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 25 (with art. 37)

C50Sch. 2 Pt. 2 incorporated (with modifications) (18.6.2020) by The A63 (Castle Street Improvement, Hull) Development Consent Order 2020 (S.I. 2020/556), arts. 1, 21 (with arts. 5, 44)

C51Sch. 2 Pt. 2 incorporated (with modifications) (6.8.2020) by The A19 Downhill Lane Junction Development Consent Order 2020 (S.I. 2020/746), arts. 1, 21 (with art. 5)

C53Sch. 2 Pt. 2 incorporated (with modifications) (15.10.2020) by The Great Yarmouth Third River Crossing Development Consent Order 2020 (S.I. 2020/1075), arts. 1, 26(b)

C54Sch. 2 Pt. 2 incorporated (with modifications) (9.2.2021) by The A1 Birtley to Coal House Development Consent Order 2021 (S.I. 2021/74), arts. 1, 24 (with art. 5, Sch. 27 para. 36)

C55Sch. 2 Pt. 2 applied (with modifications) (11.2.2021) by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), s. 64(1), Sch. 7 para. 4(3)(4)

C56Sch. 2 Pt. 2 incorporated (with modifications) (19.2.2021) by The A303 Sparkford to Ilchester Dualling Development Consent Order 2021 (S.I. 2021/125), arts. 1, 24 (with arts. 4, 47)

C57Sch. 2 Pt. 2 incorporated (with modifications) (22.12.2021) by The Morlais Demonstration Zone Order 2021 (S.I. 2021/1478), arts. 1, 30 (with arts. 15, 50, Sch. 11 para. 29)

C59Sch. 2 Pt. 2 incorporated (with modifications) (2.6.2022) by The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022 (S.I. 2022/549), arts. 1, 23 (with arts. 6, 34)

C60Sch. 2 Pts. 2, 3 incorporated (with modifications) (6.6.2022) by The M25 Junction 28 Development Consent Order 2022 (S.I. 2022/573), arts. 1, 26 (with arts. 5, 36)

C62Sch. 2 Pt. 2 incorporated (with modifications) (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), arts. 1, 29 (with arts. 62, 76, 87)

C64Sch. 2 Pt. 2 incorporated (with modifications) (8.9.2022) by The Manston Airport Development Consent Order 2022 (S.I. 2022/922), arts. 1, 20 (with arts. 5, 40)

C65Sch. 2 Pt. 2 incorporated (with modifications) (8.9.2022) by The A428 Black Cat to Caxton Gibbet Development Consent Order 2022 (S.I. 2022/934), arts. 1, 25

C67Sch. 2 Pt. 2 incorporated (with modifications) (7.12.2022) by The A57 Link Roads Development Consent Order 2022 (S.I. 2022/1206), arts. 1, 23 (with art. 5)

C68Sch. 2 Pt. 2 incorporated (with modifications) (7.12.2022) by The A417 Missing Link Development Consent Order 2022 (S.I. 2022/1248), arts. 1, 25 (with art. 4)

2(1)The acquiring authority shall not be entitled to any mines under the land comprised in the compulsory purchase order unless they have been expressly purchased, and all mines under the land shall be deemed to be excepted out of the conveyance of that land unless expressly named and conveyed.E+W

(2)Sub-paragraph (1) above shall not apply to minerals necessarily extracted or used in the construction of the undertaking.