Supply of Goods and Services Act 1982

[F111QRelation to other remedies etc.U.K.

(1)If the transferee requires the transferor to repair or replace the goods the transferee must not act under subsection (2) until he has given the transferor a reasonable time in which to repair or replace (as the case may be) the goods.

(2)The transferee acts under this subsection if—

(a)in England and Wales or Northern Ireland he rejects the goods and terminates the contract for breach of condition;

(b)in Scotland he rejects any goods delivered under the contract and treats it as repudiated; or

(c)he requires the goods to be replaced or repaired (as the case may be).]

Textual Amendments

F1Pt. 1B inserted (31.3.2003) by The Sale and Supply of Goods to Consumers Regulations 2002. S.I. 2002/3045, reg. 9