Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)For the purpose of providing practical guidance with respect to the requirements of any provision of building regulations, the [F1appropriate national authority] or a body designated by [F2the appropriate national authority] for the purposes of this section may—
(a)approve and issue any document (whether or not prepared by [F2the appropriate national authority] or by the body concerned), or
(b)approve any document issued or proposed to be issued otherwise than by [F2the appropriate national authority] or by the body concerned,
if in the opinion of the [F1appropriate national authority] or, as the case may be, the body concerned the document is suitable for that purpose.
(2)References in this section and section 7 below to a document include references to a part of a document; and accordingly, in relation to a document of which part only is approved, a reference in the following provisions of this section or in section 7 below to the approved document is a reference only to the part of it that is approved.
(3)An approval given under subsection (1) above takes effect in accordance with a notice that is issued by the [F1appropriate national authority] or, as the case may be, the body giving the approval and that—
(a)identifies the approved document in question,
(b)states the date on which the approval of it is to take effect, and
(c)specifies the provisions of building regulations for the purposes of which the document is approved.
(4)The [F1appropriate national authority] or, as the case may be, the body that gave the approval may—
(a)from time to time approve and issue a revision of the whole or any part of an approved document issued by F3... it for the purposes of this section, and
(b)approve any revision or proposed revision of the whole or any part of an approved document,
and subsection (3) above, with the necessary modifications, applies in relation to an approval that is given under this subsection to a revision as it applies in relation to an approval that is given under subsection (1) above to a document.
(5)The [F1appropriate national authority] or, as the case may be, the body that gave the approval may withdraw F4... its approval of a document under this section; and such a withdrawal of approval takes effect in accordance with a notice that is issued by the [F1appropriate national authority] or body concerned and that—
(a)identifies the approved document in question, and
(b)states the date on which the approval of it is to cease to have effect.
[F5(5A)A notice under subsection (3) or (5) may contain transitional or saving provision (and different provision may be made for different purposes or for different areas).
(5B)A body may give an approval under subsection (1) or (4), or withdraw an approval under subsection (5), only with the consent of the appropriate national authority.]
(6)References in subsections (4) and (5) above and in section 7 below to an approved document are references to that document as it has effect for the time being, regard being had to any revision of the whole or any part of it that has been approved under subsection (4) above.
(7)Where a body ceases to be a body designated by the [F1appropriate national authority] for the purposes of this section, subsections (4) and (5) above have effect as if any approval given by that body had been given by the Secretary of State.
(8)The power to designate a body for the purposes of this section is exercisable by order made by statutory instrument, which is [F6—
(a)in the case of a statutory instrument made by the Secretary of State, subject to annulment in pursuance of a resolution of either House of Parliament;
(b)in the case of a statutory instrument made by the Welsh Ministers, subject to annulment in pursuance of a resolution of Senedd Cymru.]
[F7(9)An order under subsection (8) may provide that a body is designated only in relation to—
(a)buildings of a specified description;
(b)work of a specified description;
(c)specified provisions of building regulations.]
Textual Amendments
F1Words in s. 6 substituted (28.6.2022 for E., 5.9.2023 for W.) by Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 5 para. 9(2); S.I. 2022/561, reg. 3(f), Sch. para. 9; S.I. 2023/914, reg. 2(b)(xiii), Sch. para. 6
F2Words in s. 6(1) substituted (28.6.2022 for E., 5.9.2023 for W.) by Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 5 para. 9(3); S.I. 2022/561, reg. 3(f), Sch. para. 9; S.I. 2023/914, reg. 2(b)(xiii), Sch. para. 6
F3Words in s. 6(4)(a) omitted (28.6.2022 for E., 5.9.2023 for W.) by virtue of Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 5 para. 9(4); S.I. 2022/561, reg. 3(f), Sch. para. 9; S.I. 2023/914, reg. 2(b)(xiii), Sch. para. 6
F4Words in s. 6(5) omitted (28.6.2022 for E., 5.9.2023 for W.) by virtue of Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 5 para. 9(5); S.I. 2022/561, reg. 3(f), Sch. para. 9; S.I. 2023/914, reg. 2(b)(xiii), Sch. para. 6
F5S. 6(5A)(5B) inserted (28.6.2022 for E., 5.9.2023 for W.) by Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 5 para. 9(6); S.I. 2022/561, reg. 3(f), Sch. para. 9; S.I. 2023/914, reg. 2(b)(xiii), Sch. para. 6
F6Words in s. 6(8) substituted (28.6.2022 for E., 5.9.2023 for W.) by Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 5 para. 9(7); S.I. 2022/561, reg. 3(f), Sch. para. 9; S.I. 2023/914, reg. 2(b)(xiii), Sch. para. 6
F7S. 6(9) inserted (28.6.2022 for E., 5.9.2023 for W.) by Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 5 para. 9(8); S.I. 2022/561, reg. 3(f), Sch. para. 9; S.I. 2023/914, reg. 2(b)(xiii), Sch. para. 6
(1)A failure on the part of a person to comply with an approved document does not of itself render him liable to any civil or criminal proceedings; but if, in any proceedings whether civil or criminal, it is alleged that a person has at any time contravened a provision of building regulations—
(a)a failure to comply with a [F8relevant approved document] may be relied upon as tending to establish liability, and
(b)proof of compliance with such a document may be relied on as tending to negative liability.
[F9(1A)In subsection (1) “relevant approved document” means a document approved for the purposes of the provision that applies in relation to the work in question.]
(2)In any proceedings, whether civil or criminal—
(a)a document purporting to be a notice issued as mentioned in section 6(3) above shall be taken to be such a notice unless the contrary is proved, and
(b)a document that appears to the court [F10or tribunal] to be the approved document to which such a notice refers shall be taken to be that approved document unless the contrary is proved.
Textual Amendments
F8Words in s. 7(1)(a) substituted (28.6.2022 for E., 5.9.2023 for W.) by Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 5 para. 10(2); S.I. 2022/561, reg. 3(f), Sch. para. 10; S.I. 2023/914, reg. 2(b)(xiii), Sch. para. 7
F9S. 7(1A) inserted (28.6.2022 for E., 5.9.2023 for W.) by Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 5 para. 10(3); S.I. 2022/561, reg. 3(f), Sch. para. 10; S.I. 2023/914, reg. 2(b)(xiii), Sch. para. 7
F10Words in s. 7(2)(b) inserted (1.10.2023 except in relation to W., 6.4.2024 for W.) by Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 6 para. 10; S.I. 2023/993, reg. 2(o)(i) (with reg. 6); S.I. 2024/207, reg. 2(d)(xii) (with regs. 3, 4, 8-12)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
Y Ddeddf Gyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Ddeddf Gyfan heb Atodlenni you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys