- Y Diweddaraf sydd Ar Gael (Diwygiedig)
- Pwynt Penodol mewn Amser (19/04/2013)
- Gwreiddiol (Fel y'i Deddfwyd)
Version Superseded: 01/10/2023
Point in time view as at 19/04/2013. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Building Act 1984, Section 19 is up to date with all changes known to be in force on or before 21 December 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)Where plans of a building are, in accordance with building regulations, deposited with a local authority, and the plans show that it is proposed to construct a building of materials to which this section applies, or to place or assemble on the site a building constructed of such materials, the authority may, notwithstanding that the plans conform with the regulations—
(a)reject the plans, or
(b)in passing the plans—
(i)fix a period on the expiration of which the building must be removed, and
(ii)impose with respect to the use of the building such reasonable conditions, if any, as having regard to the nature of the materials used in its construction they deem appropriate,
but no condition shall be imposed that conflicts with any condition imposed on the grant of planning permission for that building under Part III of [F1the Town and Country Planning Act 1990].
(2)If a building in respect of which plans ought under the building regulations to have been deposited, but have not been deposited, appears to the authority to be constructed of such materials as aforesaid, the authority, without prejudice to their right to take proceedings in respect of any contravention of the regulations, may—
(a)fix a period on the expiration of which the building must be removed, and
(b)if they think fit, impose such conditions with respect to the use of the building as might have been imposed under subsection (1) above upon the passing of plans for the building.
and where they fix such a period they shall forthwith give notice thereof, and of any conditions imposed, to the owner of the building.
(3)A local authority may from time to time extend any period fixed, or vary any conditions imposed, under this section; but, unless an application in that behalf is made to them by the owner of the building in question, they shall not exercise their power of varying conditions except when granting an extension, or further extension, of the period fixed with respect to the building.
(4)A person aggrieved by the action of a local authority under this section in rejecting plans, or in fixing or refusing to extend any period, or in imposing or refusing to vary any conditions, may appeal to a magistrates’ court.
(5)The owner of a building in respect of which a period has been fixed under this section shall, on the expiration of that period, or, as the case may be, of that period as extended, remove the building, and, if he fails to do so—
(a)the local authority shall remove it and may recover from him the expenses reasonably incurred by them in so doing, and
(b)without prejudice to the right of the authority to exercise that power, he is liable on summary conviction to a fine not exceeding level 1 on the standard scale and to a further fine not exceeding £5 for each day during which the building is allowed to remain after he is convicted.
(6)A person who uses a building in contravention of a condition imposed under this section, or who permits a building to be so used, is liable on summary conviction to a fine not exceeding level 1 on the standard scale and to a further fine not exceeding £5 for each day on which the offence continues after he is convicted.
(7)Building regulations may provide that this section applies to any materials specified in the regulations as being materials that are, in the absence of special care, liable to rapid deterioration, or are otherwise unsuitable for use in the construction of permanent buildings.
(8)This section applies in relation to an extension of an existing building as it applies in relation to a new building.
(9)This section ceases to have effect upon the coming into force of section 20 below (which supersedes it).
Textual Amendments
F1Words substituted by Planning (Consequential Provisions) Act 1990 (c. 11, SIF 123:1, 2), s. 4, Sch. 2 para. 67(1)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
Y Ddeddf Gyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys