- Y Diweddaraf sydd Ar Gael (Diwygiedig)
- Pwynt Penodol mewn Amser (29/12/2003)
- Gwreiddiol (Fel y'i Deddfwyd)
Version Superseded: 01/04/2013
Point in time view as at 29/12/2003.
Electricity Act 1989, Cross Heading: Alteration of works is up to date with all changes known to be in force on or before 01 December 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
3(1)A licence holder may execute works in pursuance of paragraph 1 or 2 above, notwithstanding that they involve a temporary or permanent alteration of any of the following, namely—E+W
(a)any electric line or electrical plant under the control of another licence holder;
(b)any gas pipe [F2operated by a public gas transporter];
(c)any relevant pipe (within the meaning of [F3section 159 of the Water Resources Act 1991 or section 158 of the Water Industry Act 1991 which (whether or not it is in a street) is]) under the control of the National Rivers Authority, a water undertaker or a sewerage undertaker or, in Scotland, any water pipe under the control of a person supplying water in the exercise of statutory powers;
(d)any [F4electronic communications apparatus] used for the purposes of [F5an electronic communications code network] which is operated by a person to whom the [F6electronic communications code] applies; or
(e)any system apparatus (within the meaning of Part II of the M1Road Traffic (Driver Licensing and Information Systems) Act 1989) of an operator of a driver information system who is licensed under Part II of that Act.
(2)Where a licence holder is proposing to execute works in pursuance of paragraph 1 or 2 above which involve or are likely to involve any such alteration as is mentioned in sub-paragraph (1)(a), (b) or (c) above, the following provisions of this paragraph shall apply; and in those provisions “the relevant undertaker” means the other licence holder, the [F7public gas transporter] or the person supplying water in the exercise of statutory powers, as the case may be.
(3)The licence holder shall, not less than one month before the works are commenced, give the relevant undertaker a notice specifying the nature of the licence holder’s works, the alteration or likely alteration involved and the time and place at which the works will be commenced.
(4)Sub-paragraph (3) above shall not apply in relation to any emergency works of which the licence holder gives the relevant undertaker notice as soon as practicable after commencing the works.
(5)Where a notice has been given under sub-paragraph (3) above by the licence holder to the relevant undertaker, the undertaker may within the period of seven days beginning with the giving of the notice give the licence holder a counter-notice which may state either—
(a)that the undertaker intends himself to make any alteration made necessary or expedient by the licence holder’s proposed works; or
(b)that he requires the licence holder in making any such alteration to do so under the supervision and to the satisfaction of the undertaker.
(6)Where a counter-notice given under sub-paragraph (5) above states that the relevant undertaker intends himself to make any alteration—
(a)the undertaker shall (subject to sub-paragraph (8) below) have the right, instead of the licence holder, to execute any works for the purpose of making that alteration; and
(b)any expenses incurred by the undertaker in or in connection with the execution of those works and the amount of any loss or damage sustained by the undertaker in consequence of the alteration shall be recoverable by the undertaker from the licence holder in any court of competent jurisdiction.
(7)Where a counter-notice given under sub-paragraph (5) above states that any alteration is to be made under the supervision and to the satisfaction of the relevant undertaker—
(a)the licence holder shall not make the alteration except as required by the notice or under sub-paragraph (8) below; and
(b)any expenses incurred by the undertaker in or in connection with the provision of that supervision and the amount of any loss or damage sustained by the undertaker in consequence of the alteration shall be recoverable by the undertaker from the licence holder in any court of competent jurisdiction.
(8)Where—
(a)no counter-notice is given under sub-paragraph (5) above; or
(b)the relevant undertaker, having given a counter-notice falling within that sub-paragraph, fails to make any alteration made necessary or expedient by the licence holder’s proposed works within such period (being not less than 48 hours) as the licence holder may by notice specify or, as the case may be, unreasonably fails to provide the required supervision,
the licence holder may himself execute works for the purpose of making the alteration or, as the case may be, may execute such works without the supervision of the undertaker; but in either case the licence holder shall execute the works to the satisfaction of the undertaker.
(9)If the licence holder or any of his agents—
(a)executes any works without the notice required by sub-paragraph (3) above having been given; or
(b)unreasonably fails to comply with any reasonable requirement of the relevant undertaker under this paragraph,
he shall be liable on summary conviction to a fine not exceeding level 3 on the standard scale.
Extent Information
E1This version of this provision extends to England and Wales only; a separate version has been created for Scotland only.
Textual Amendments
F2Words in Sch. 4 para. 3(1)(b) substituted (1.3.1996) by 1995 c. 45, s. 16(1), Sch. 4 para. 17(1)(a); S.I. 1996/218, art. 2
F3Words in Sch. 4 para. 3(1)(c) substituted (E.W.) (01.12.1991) by Water Consolidation (Consequential Provisions) Act 1991 (c. 60, SIF 130), ss. 2(1), 4(2), Sch. 1 para. 51(2).
F4Words in Sch. 4 para. 3(1)(d) substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), s. 411(2), Sch. 17 para. 99(2)(a) (with Sch. 18); S.I. 2003/1900, arts. 1(2), 2(1), Sch. 1 (with art. 3) (as amended by S.I. 2003/3142, art. 1(3)); S.I. 2003/3142, art. 3(2) (with art. 11)
F5Words in Sch. 4 para. 3(1)(d) substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), s. 411(2), Sch. 17 para. 99(2)(b) (with Sch. 18); S.I. 2003/1900, arts. 1(2), 2(1), Sch. 1 (with art. 3) (as amended by S.I. 2003/3142, art. 1(3)); S.I. 2003/3142, art. 3(2) (with art. 11)
F6Words in Sch. 4 para. 3(1)(d) substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), s. 411(2), Sch. 17 para. 99(2)(c) (with Sch. 18); S.I. 2003/1900, arts. 1(2), 2(1), Sch. 1 (with art. 3) (as amended by S.I. 2003/3142, art. 1(3)); S.I. 2003/3142, art. 3(2) (with art. 11)
F7Words in Sch. 4 para. 3(2) substituted (1.3.1996) by 1995 c. 45, s. 16(1), Sch. 4 para. 17(1)(b); S.I. 1996/218, art. 2
Marginal Citations
3(1)A licence holder may execute works in pursuance of paragraph 1 or 2 above, notwithstanding that they involve a temporary or permanent alteration of any of the following, namely—S
(a)any electric line or electrical plant under the control of another licence holder;
(b)any gas pipe [F11operated by a public gas transporter];
(c)any relevant pipe (within the meaning of Schedule 19 to the M3Water Act 1989) under the control of the National Rivers Authority, a water undertaker or a sewerage undertaker or, in Scotland, any water pipe under the control of a person supplying water in the exercise of statutory powers;
(d)any [F4electronic communications apparatus] used for the purposes of [F5an electronic communications code network] which is operated by a person to whom the [F6electronic communications code] applies; or
(e)any system apparatus (within the meaning of Part II of the M4Road Traffic (Driver Licensing and Information Systems) Act 1989) of an operator of a driver information system who is licensed under Part II of that Act.
(2)Where a licence holder is proposing to execute works in pursuance of paragraph 1 or 2 above which involve or are likely to involve any such alteration as is mentioned in sub-paragraph (1)(a), (b) or (c) above, the following provisions of this paragraph shall apply; and in those provisions “the relevant undertaker” means the other licence holder, the [F12public gas transporter] or the person supplying water in the exercise of statutory powers, as the case may be.
(3)The licence holder shall, not less than one month before the works are commenced, give the relevant undertaker a notice specifying the nature of the licence holder’s works, the alteration or likely alteration involved and the time and place at which the works will be commenced.
(4)Sub-paragraph (3) above shall not apply in relation to any emergency works of which the licence holder gives the relevant undertaker notice as soon as practicable after commencing the works.
(5)Where a notice has been given under sub-paragraph (3) above by the licence holder to the relevant undertaker, the undertaker may within the period of seven days beginning with the giving of the notice give the licence holder a counter-notice which may state either—
(a)that the undertaker intends himself to make any alteration made necessary or expedient by the licence holder’s proposed works; or
(b)that he requires the licence holder in making any such alteration to do so under the supervision and to the satisfaction of the undertaker.
(6)Where a counter-notice given under sub-paragraph (5) above states that the relevant undertaker intends himself to make any alteration—
(a)the undertaker shall (subject to sub-paragraph (8) below) have the right, instead of the licence holder, to execute any works for the purpose of making that alteration; and
(b)any expenses incurred by the undertaker in or in connection with the execution of those works and the amount of any loss or damage sustained by the undertaker in consequence of the alteration shall be recoverable by the undertaker from the licence holder in any court of competent jurisdiction.
(7)Where a counter-notice given under sub-paragraph (5) above states that any alteration is to be made under the supervision and to the satisfaction of the relevant undertaker—
(a)the licence holder shall not make the alteration except as required by the notice or under sub-paragraph (8) below; and
(b)any expenses incurred by the undertaker in or in connection with the provision of that supervision and the amount of any loss or damage sustained by the undertaker in consequence of the alteration shall be recoverable by the undertaker from the licence holder in any court of competent jurisdiction.
(8)Where—
(a)no counter-notice is given under sub-paragraph (5) above; or
(b)the relevant undertaker, having given a counter-notice falling within that sub-paragraph, fails to make any alteration made necessary or expedient by the licence holder’s proposed works within such period (being not less than 48 hours) as the licence holder may by notice specify or, as the case may be, unreasonably fails to provide the required supervision,
the licence holder may himself execute works for the purpose of making the alteration or, as the case may be, may execute such works without the supervision of the undertaker; but in either case the licence holder shall execute the works to the satisfaction of the undertaker.
(9)If the licence holder or any of his agents—
(a)executes any works without the notice required by sub-paragraph (3) above having been given; or
(b)unreasonably fails to comply with any reasonable requirement of the relevant undertaker under this paragraph,
he shall be liable on summary conviction to a fine not exceeding level 3 on the standard scale.
Extent Information
E2This version of this provision extends to Scotland only; a separate version has been created for England and wales only.
Textual Amendments
F4Words in Sch. 4 para. 3(1)(d) substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), s. 411(2), Sch. 17 para. 99(2)(a) (with Sch. 18); S.I. 2003/1900, arts. 1(2), 2(1), Sch. 1 (with art. 3) (as amended by S.I. 2003/3142, art. 1(3)); S.I. 2003/3142, art. 3(2) (with art. 11)
F5Words in Sch. 4 para. 3(1)(d) substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), s. 411(2), Sch. 17 para. 99(2)(b) (with Sch. 18); S.I. 2003/1900, arts. 1(2), 2(1), Sch. 1 (with art. 3) (as amended by S.I. 2003/3142, art. 1(3)); S.I. 2003/3142, art. 3(2) (with art. 11)
F6Words in Sch. 4 para. 3(1)(d) substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), s. 411(2), Sch. 17 para. 99(2)(c) (with Sch. 18); S.I. 2003/1900, arts. 1(2), 2(1), Sch. 1 (with art. 3) (as amended by S.I. 2003/3142, art. 1(3)); S.I. 2003/3142, art. 3(2) (with art. 11)
F11Words in Sch. 4 para. 3(1)(b) substituted (1.3.1996) by 1995 c. 45, s. 16(1), Sch. 4 para. 17(1)(a); S.I. 1996/218, art. 2
F12Words in Sch. 4 para. 3(2) substituted (1.3.1996) by 1995 c. 45, s. 16(1), Sch. 4 para. 17(1)(b); S.I. 1996/218, art. 2
Marginal Citations
4(1)Any of the following who is authorised by or under any enactment to execute works corresponding to those authorised by paragraph 1 or 2 above, namely—E+W+S
(a)any [F8public gas transporter];
(b)the [F9Environment Agency], any water undertaker or any sewerage undertaker or, in Scotland, any person supplying water in the exercise of statutory powers;
[F10(c)any electronic communications code operator or any former PTO; and]
(d)any operator of a driver information system who is licensed under Part II of the M2Road Traffic (Driver Licensing and Information Systems) Act 1989,
(in this paragraph referred to as a “relevant undertaker”) may execute such works, notwithstanding that they involve a temporary or permanent alteration of any electric line or electrical plant under the control of a licence holder.
(2)Where a relevant undertaker is proposing to execute any such works as are mentioned in sub-paragraph (1) above which involve or are likely to involve any such alteration as is there mentioned, sub-paragraphs (3) to (9) of paragraph 3 above shall apply as if—
(a)any reference to the licence holder were a reference to the relevant undertaker; and
(b)any reference to the relevant undertaker were a reference to the licence holder.
Textual Amendments
F8Words in Sch. 4 para. 4(1)(a) substituted (1.3.1996) by 1995 c. 45, s. 16(1), Sch. 4 para. 17(2); S.I. 1996/218, art. 2
F9Words in Sch. 4 para. 4(1)(b) substituted (1.4.1996) by 1995 c. 25, s. 120(1), Sch. 22 para. 40 (with ss. 7(6), 115, 117); S.I. 1996/186, art. 3
F10Sch. 4 para. 4(1)(c) substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), s. 411(2), Sch. 17 para. 99(3) (with Sch. 18); S.I. 2003/1900, arts. 1(2), 2(1), Sch. 1 (with art. 3) (as amended by S.I. 2003/3142, art. 1(3)); S.I. 2003/3142, art. 3(2) (with art. 11)
Marginal Citations
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
Y Ddeddf Gyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys: