Chwilio Deddfwriaeth

Electricity Act 1989

 Help about what version

Pa Fersiwn

 Help about advanced features

Nodweddion Uwch

 Help about opening options

Dewisiadau AgorExpand opening options

Changes over time for: Cross Heading: Suspension of decision

 Help about opening options

Version Superseded: 01/04/2014

Alternative versions:

Status:

Point in time view as at 01/01/2013.

Changes to legislation:

Electricity Act 1989, Cross Heading: Suspension of decision is up to date with all changes known to be in force on or before 09 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

[F1Suspension of decisionU.K.

2.(1)The Commission may direct that, pending the determination of an appeal against a decision of the AuthorityU.K.

(a)the decision is not to have effect; or

(b)the decision is not to have effect to such extent as may be specified in the direction.

(2)The power to give a direction under this paragraph is exercisable only where—

(a)an application for its exercise has been made by the appellant at the same time the appellant made an application in accordance with paragraph 1(3) for permission to bring an appeal against a decision of the Authority;

(b)the Commission has given the Authority an opportunity of making representations or observations, in accordance with paragraph 3(2);

(c)the relevant licence holder, the licence holder or consumers whose interests are materially affected mentioned in section 11C(2) (as the case may be) would incur significant costs if the decision were to have effect before the determination of the appeal; and

(d)the balance of convenience does not otherwise require effect to be given to the decision pending that determination.

(3)The Commission’s decision on an application for a direction under this paragraph must be made—

(a)where the Authority makes representations or observations in accordance with paragraph 3(2), before the end of 10 working days beginning with the first working day after the day on which those representations or observations are received;

(b)in any other case, before the end of 14 working days beginning with the first working day following the day on which the application under sub-paragraph (2)(a) is received.

(4)The appellant must send the Authority a copy of the application for a direction under this paragraph at the same time as it is sent to the Commission.

(5)The Commission’s decision whether to give a direction is to be taken by an authorised member of the Commission.

(6)A direction under this paragraph must be—

(a)given by an authorised member of the Commission; and

(b)published, in such manner as the Commission considers appropriate, as soon as reasonably practicable after it is given.

(7)Section 11H(2) applies to the publication of a direction under sub-paragraph (6) as it does to the publication of a decision under section 11H.]