Print Options
PrintThe Whole
Act
PrintThe Whole
Schedule
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Paragraph 2


Llinell Amser Newidiadau
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Version Superseded: 20/12/2000
Status:
Point in time view as at 01/10/1995. This version of this provision has been superseded.

Status
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Changes to legislation:
Electricity Act 1989, Paragraph 2 is up to date with all changes known to be in force on or before 09 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
2(1)Where a public electricity supplier has cut off the supply of electricity to any premises in consequence of any default on the part of a tariff customer, the supplier shall be under an obligation to resume the supply of electricity before the end of the period of two working days beginning with the time when the requirements of sub-paragraph (2) below are satisfied.
(2)The requirements of this sub-paragraph are that the customer in default—
(a)has made good the default;
(b)has paid the reasonable expenses of disconnecting and re-connecting the supply; and
(c)has given such security as is mentioned in section 20(1) of this Act.
(3)The obligation imposed by sub-paragraph (1) above shall be a duty owed to any person who may be affected by a failure to comply with the obligation.
(4)Where a duty is owed by virtue of sub-paragraph (3) above to any person any breach of the duty which causes that person to sustain loss or damage shall be actionable at the suit or instance of that person.
(5)In any proceedings brought against a public electricity supplier in pursuance of sub-paragraph (4) above, it shall be a defence for the supplier to prove that he took all reasonable steps and exercised all due diligence to avoid failing to comply with the obligation imposed by sub-paragraph (1) above.
(6)Without prejudice to any right which any person may have by virtue of sub-paragraph (4) above to bring civil proceedings in respect of any failure to comply with the obligation imposed by sub-paragraph (1) above, compliance with that obligation shall be enforceable by civil proceedings by the Director for an injunction or for interdict or for any other appropriate relief.